Forwards Safety Insp Rept 50-293/86-10 on 860324-27 & Notice of Violation.Correction of Violations & Deviations Identified in 840608 & s Verified
ML20204A415
Person / Time
Site: Pilgrim
Issue date: 05/06/1986
From: Martin T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Harrington W
BOSTON EDISON CO.
Shared Package
ML20204A416 List:
References
NUDOCS 8605120187
Download: ML20204A415 (2)


See also: IR 05000293/1986010

Text

T

4

MAY 0 6198G

.

Docket No. 50-293

Boston Edison Company M/C Nuclear

ATTN: Mr. William D. Harrington

Senior Vice President, Nuclear

800 Boylston Street

Boston, Massachusetts 02199

Gentlemen:

Subject: Inspection No. 50-293/86-10

This refers to the routine safety inspection conducted by Ms. M. Miller of this

office on March 24-27, 1986, at Pilgrim Nuclear Power Station, of activities

authorized by NRC License No. DPR-35 and to the discussions of our findings

held by Ms. Miller with Mr. J. Seery and others of your staff at the conclusion

of the inspection.

Areas examined during this inspection of your solid radioactive waste pre-

paration, packaging and transportation program are described in the NRC

Region I Inspection Report which is enclosed with this letter.

Our inspector also verified the steps you had taken to correct the violations

and deviation brought to your attention in letters dated June 8,1984 and

February 12, 1986. We have no further questions regarding your action at this

time.

Based on the results of this inspection, it appears that certain of your

activities were not conducted in full compliance with NRC requirements, as set

forth in the Notice of Violation, enclosed herewith as Appendix A. These vio-

lations have been categorized by severity level in accordance with the revised

NRC Enforcement Policy (10 CFR 2, Appendix C) published in the Federal Register

Notice (49 FR 8583) dated March 8, 1984. You are required to respond to this

letter and in preparing your response, you should follow the instructions in

Appendix A.

The responses directed by this letter and the accompanying Notice are not

subject to the clearance procedures of the Office of Management and Budget

as required by the Paperwork Reduction Act of 1980, PL 96-511.

Your cooperation with us in this matter is appreciated.

Sincerely,

Orts nni sf_ a

O 93 - 7)(1 N

O

PDR homasT. Martin,Direc68

vision of Radiation Safety

and Safeguards

OFFICIAL RECORD COPY IR PILGRIM 86-10 - 0001.0.0

04/23/86 r6 0(

k 1.

,p

o

Boston Edison Company 2

.

Enclosure:

1. Appendix A, Notice of Violation

2. NRC Region I Inspection Report No. 50-293/86-10

cc w/ enc 1:

L. Oxsen, Vice President, Nuclear Operations

C. J. Mathis, Station Manager

Joanne Shotwell, Assistant Attorney General

Paul Levy, Chairman, Department of Public Utilities

W. J. Nolan, Chairman, Plymouth Board of Selectmen

Plymouth Civil Defense Director

Senator Edward P. Kirby

Public Document Room (PDR)

local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

Commonwealth of Massachusetts (2)

bcc w/ encl:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encl)

Section Chief, DRP

W. Raymond, SRI, Vermont Yankee

T. Shedlosky, SRI, Millstone 1&2

H. Eichenholz, SRI, Yankee

P. Leech, LPM, NRR

'

%'#L

RI.DRS5 RItDRSS RI[:DRSS

Miller /fi Pasciak Be) lamy

04/Al/86 04/J3/86 Of/ (p/86

0FFICIAL RECORD COPY IR PILGRIM 86-10 - 0002.0.0

04/23/86

'

,