ML20203N750
ML20203N750 | |
Person / Time | |
---|---|
Site: | Millstone, Hatch |
Issue date: | 04/22/1986 |
From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
To: | |
Shared Package | |
ML20203N746 | List: |
References | |
50-366-86-09, 50-366-86-9, NUDOCS 8605060038 | |
Download: ML20203N750 (1) | |
Category:NOTICE OF VIOLATION OF A REGULATION
MONTHYEARML20207F1521999-05-25025 May 1999
[Table view]Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys ML20237B0741998-08-12012 August 1998 Notice of Violation from Insp on 980428-0629.Violation Noted:Licensee Failed to Direct Test Personnel to Close & Lock RHR Outboard Drain Valve ML20237D3041998-08-12012 August 1998 Notice of Violation from Insp on 980413-0508.Violations Noted:Two Examples Identified Where Licensee Not Performing Leakage Testing of safety-related Valves in Sys That Could Contain Highly Radioactive Fluids During Accident ML20249C6931998-06-19019 June 1998 Notice of Violations from Combined Insp on 980301-0427. Violations Noted:Prior to 980424,instrument Min Accuracy of Wind Speed Channels Were Not Measured as Required by Table 3.3-8 of Unit 2 TS 3/4.3.3.4 ML20249B0421998-06-12012 June 1998 Notice of Violations from Insp on 980413-24.Violations Noted:Only 1 RCS Loop Operable W/Plant in Mode 4 on 980407 ML20236L5381998-06-11011 June 1998 Notice of Violation from Insp on 980302-0409.Violation noted:post-mod Test Procedure Did Not Incorporate Requirements Contained in Design Documents ML20249B0811998-06-11011 June 1998 Notice of Violation from Insp on 980209-20.Violation Noted: Between 1992 & 1993,appropriate C/A Not Taken to Prevent Recurring Air Binding Problems for Boric Acid Transfer Pumps ML20248E5951998-05-26026 May 1998 Notice of Violation from Insp on 980101-0228.Violation Noted:On 980225,NRC Determined That Written Equipment Control Procedures Were Not Established to Process Revs to Sys Valve Lineups ML20249B2171998-05-26026 May 1998 Revised Notice of Violation from Insp on 980101-0228. Violations Noted:As of 980210,21 nonsafety-related SOVs in High Pressure & Low Pressure Safety Injection Sys & Four nonsafety-related SOV in RCS Not Included in EQ Program ML20248A7781998-05-22022 May 1998 Notice of Violation from Insp on 980302-31 & 980412. Violation Noted:Structural Steel Support Members Did Not Meet 3-h Fire Barrier Criterion,In That on & Before 980304, Columns D2-54,D2-53 & A4-52 Had Gaps in Fire Rated Coating ML20248F3061998-05-0808 May 1998 Notice of Violation from Insp on 980223-0306.Violation Noted:Listed Examples Were Identified Where Requirements of 10CFR50 App B,Criterion Xvi, Corrective Action, Were Not Met ML20247D8561998-05-0606 May 1998 Notice of Violation from Insp on 980223-26.Violation Noted: Between 1988 & 980226,licensee Failed to Maintain Adequate PASS Program That Ensured Capability to Obtain & Analyze Samples Under Post Accident Conditions ML20217N1101998-04-21021 April 1998 Notice of Violation from Insp on 980208-0321.Violation Noted:Maint Personnel Did Not Follow Procedures & Conducted Work That Was Not Specified on Maint Work Order Which Was Outside Approved Personnel Protection Clearance Boundary ML20217M9091998-04-0808 April 1998 Notice of Violation from Insp on 980209-27.Violation Noted:As of 980227,measures Were Not Established to Assure That Design Basis of safety-related MOVs Was Correctly Translated Into Specifications,Drawings & Instructions ML20216F9841998-04-0303 April 1998 Notice of Violation from Insp on 980105-0206.Violation Noted:Certain Measures for Verifying Adequacy of Plant Design Inadequate ML20216G0921998-04-0101 April 1998 Notice of Violation from Insp on 971027-980128.Violation Noted:Licensee Failed to Perform & Include in Written Records,Safety Evaluations for Approx 250 Changes to FSAR Made Between mid-1996 & mid-1997 ML20216E7931998-03-10010 March 1998 Notice of Violation from Insp on 971228-980207.Violation Noted:As of 980207,measures Not Correctly Implemented in That Proposed Vendor Manual Change for Sys Not Submitted to Reflect Lower Set Point Requirement for PCV 2T48-F466 ML20196J5911998-03-0909 March 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:As of Sept 1997, Condition Adverse to Quality Existed at Facility Which Had Not Been Promptly Identified & Corrected ML20203H0981998-02-25025 February 1998 Notice of Violation from Insp on 971201-31.Violation Noted: on 971222,equipment Located in safety-related Area,Unit 2 Control Room,Not Restrained in Accordance W/Attachment 3 in Procedure Oa 8 ML20199F5061998-01-23023 January 1998 Notice of Violation from Insp on 971116-1227.Violation Noted:On 971118,4 H Reporting Requirement Was Not Met. Several Workers Involved in Unit 2 Outage Activities Signed Into RCA on Improper RWPs Between 970317-0411 ML20198F0501997-12-30030 December 1997 Notice of Violation from Insp on 970825-29.Violation Noted: as of 970829,adequate Dose Assessment Methods Were Not in Use.Page 23 of Incoming Submittal Was Not Included ML20197F3571997-12-15015 December 1997 Notice of Violation from Insp on 971005-1115.Violation Noted:Licensee Failed to Label Properly Eight Spent Vacuum Filters Having Max Contact Dose Rates Ranging from 4.7 to 7.5 Rem Per Hour Which Were Suspended from Unit 1 Catwalk ML20202J7221997-12-10010 December 1997 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $2,100,000.Violation Noted:Licensee Did Not Translate Design Features Into Work Instructions & Did Not Verify Adequacy of Designs ML20202J7891997-12-0505 December 1997 Notice of Violation from Insp on 970818-29 & 0908-19. Violations Noted:During NRC Insp That Ended 970919,listed Instances Were Identified Where Requirements of TS 6.8.1a Were Not Met ML20199G9381997-12-0101 December 1997 Notice of Violation from Insp on 970406-0517.Violation Noted:On 970320,L Tillman Engaged in Deliberate Misconduct Causing Licensee to Be in Violation of TS 5.4,by Failing to Rept That Work Was Mistakenly Performed on Valve 2E51-F102 ML20202A7491997-11-21021 November 1997 Notice of Violation Form Insp on 970722-1001.Violation Noted:On 971215 Activities Affecting Quality Were Not Prescribed by Documented Instructions,Procedures or Drawings ML20199B8121997-11-0303 November 1997 Notice of Violation from Insp on 970817-1004.Violation Noted:Written Procedures Were Not Implemented on 970815 & Maintenance Work Was Completed Using Maintenance Work Order W/Inadequate Instructions ML20210S8701997-08-29029 August 1997 Notice of Violation from Insp on 970520-0721.Violations Noted:Overcoat Window Was Exceeded by 45 Minutes to 2 H & 45 Minutes ML20216C7471997-08-29029 August 1997 Notice of Violation from Insp on 970529-0721.Violation Noted:On Several Occasions in May & June 1997,overcoat Window Was Exceeded by 45 Minutes to 2 Hours & 41 Minutes ML20196J7051997-07-25025 July 1997 Notice of Violation from Insp on 970518-0628.Violation Noted:On 970609,steps 8.4.5 & 8.5.2 of Administration Control Procedure 30AC-OPS-001-OS,rev 15 Were Not Correctly Implemented ML20149H6581997-07-17017 July 1997 Notice of Violation from Insp on 970609-13.Violation Noted: Improperly Stored Matl,Which Had Potential to Impact Performance of Safety Related Equipment in Control Room, Was Identified ML20141E3101997-06-24024 June 1997 Notice of Violation from Insp on 970311-0519.Violation Noted:Since Commencement of Operations at Unit 1,applicable Regulatory Requirements & Design Basis Not Correctly Translated Into Drawings & Procedures ML20141F8641997-06-17017 June 1997 Notice of Violation from Insp on 970406-0517.Violation Noted:Listed Examples of Inadequate Testing Procedures Were Identified ML20140F1121997-06-11011 June 1997 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000.Violation Noted:Licensee Identified Seven Incidents Where Items Containing Safeguards Info Had Not Been Under Control of an Authorized Individual ML20140C2301997-05-30030 May 1997 Notice of Violation from Insp on 970428-0502.Violation Noted:Policies & Procedures Were Not Adequately Implemented in Employee Assistance Program Info & Released W/O Written Permission from Employee ML20148B8191997-05-0505 May 1997 Notice of Violation from Insp on 970223-0405.Violation Noted:Sections 8.12,8.13,4.2.2,4.7.7 & 8.8.3 of Procedure 30AC-OPS-001-OS Were Not Correctly Implemented ML20140C5551997-04-11011 April 1997 Notice of Violations from Insp on 970101-0310.Violations Noted:Since Commencement of Operations,Unit 1 Failed to Determine Concentration of Nuclides in Gaseous Effluents Released from Radwaste Storage Bldg Through Exhaust Fan ML20137F3921997-03-24024 March 1997 Notice of Violation from Insp on 961222-970208.Violations Noted:When Repeatedly Depressurizing Unit 2 RHR Sys from 970123-30,operators Did Not Properly Implement Procedures as Required ML20137F6301997-03-24024 March 1997 Notice of Violation from Insp on 970119-0222.Violation Noted:Design Control Requirements Not Translated Into Specifications ML20135E6111997-02-24024 February 1997 Notice of Violation from Insp on 961026-1231.Violation Noted:Individual Gained Access to PA W/O Having Authorized or Hand Geometry Confirmed ML20134L0771997-02-13013 February 1997 Notice of Violation from Insp on 961208-970118.Violation Noted:Written Procedures Were Not Implemented & Listed Examples of Failure to Implement Procedures for Radiation Control Activities Were Identified ML20134G3911997-02-0303 February 1997 Notice of Violation from Insp on 961112-22.Violation Noted: Licensee Failed to Establish & Implement Procedure to Verify That Design Basis Relative to Ventilation Air Supply Involving Radwaste Was Maintained as Described by UFSAR ML20133G9861997-01-0606 January 1997 Notice of Violation from Insp on 961027-1207.Violation Noted:Configuration Management & Adequate Design Control Measures Were Not Implemented 1999-05-25 Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS MONTHYEARIR 05000321/19990091999-10-0707 October 1999
[Table view]Insp Repts 50-321/99-09 & 50-366/99-09 on 990607-11 & 0823- 27.One Violation Being Treated as Ncv.Major Areas Inspected: Maint & Engineering IR 05000321/19990051999-09-16016 September 1999 Insp Repts 50-321/99-05 & 50-366/99-05 on 990711-0821.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000321/19990041999-08-0404 August 1999 Insp Repts 50-321/99-04 & 50-366/99-04 on 990530-0710.One Violation Noted & Being Treated as Ncv.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000321/19990101999-07-20020 July 1999 Insp Repts 50-321/99-10 & 50-366/99-10 on 990616-25.One Violation Occurred & Being Treated as Ncv.Major Areas Inspected:Aspects of Licensee Operations,Maint,Problem Identification & Resolution & Corrective Actions IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000321/19990031999-06-25025 June 1999 Insp Repts 50-321/99-03 & 50-366/99-03 on 990418-0529.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support PNO-II-99-025, on 990615,CR Operators Manually Shutdown Unit 2 Reactor from 41% Power,Due to Decreasing Condenser Vacuum. Cause of Decreasing Vacuum Has Not Been Determined.All Rods Installed as Required & All Safety Sys Functioned Properly1999-06-17017 June 1999 PNO-II-99-025:on 990615,CR Operators Manually Shutdown Unit 2 Reactor from 41% Power,Due to Decreasing Condenser Vacuum. Cause of Decreasing Vacuum Has Not Been Determined.All Rods Installed as Required & All Safety Sys Functioned Properly IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection PNO-II-99-016, on 990505,Hatch Unit 2 Had Main Generator Trip Form 98% Power,Due to Electrical Fault.Licensee Continuing Investigation Has Been Hampered Due to Inclement Local Weather Conditions.Plant Being Depressurized1999-05-0707 May 1999 PNO-II-99-016:on 990505,Hatch Unit 2 Had Main Generator Trip Form 98% Power,Due to Electrical Fault.Licensee Continuing Investigation Has Been Hampered Due to Inclement Local Weather Conditions.Plant Being Depressurized IR 05000321/19990021999-05-0606 May 1999 Insp Repts 50-321/99-02 & 50-366/99-02 on 990307-0417.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000321/19990011999-04-0202 April 1999 Insp Repts 50-321/99-01 & 50-366/99-01 on 990124-0306.Non- Cited Violations Identified.Major Areas Inspected:Maint, Operations & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000321/19980091999-02-24024 February 1999 Insp Repts 50-321/98-09 & 50-366/98-09 on 981213-990123.No Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support.Rept Covers Insp in Health Physics & Independent Spent Fuel Storage PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power IR 05000321/19980071998-12-29029 December 1998 Insp Repts 50-321/98-07 & 50-366/98-07 on 981101-1212.No Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch IR 05000321/19980061998-11-24024 November 1998 Insp Repts 50-321/98-06 & 50-366/98-06 on 980920-1031. Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000321/19980051998-10-15015 October 1998 Insp Repts 50-321/98-05 & 50-366/98-05 on 980802-0919.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support.Insp Also Included Insps by Regional Maint & Emergency Preparedness IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support PNO-II-98-040, on 980917,licensee Declared Notification of Unusual Event Based on Transport of Two Injured & Potentially Contaminated Individuals to Local Hospital.Two Individuals Found Not to Have Sustained Serious Injury1998-09-18018 September 1998 PNO-II-98-040:on 980917,licensee Declared Notification of Unusual Event Based on Transport of Two Injured & Potentially Contaminated Individuals to Local Hospital.Two Individuals Found Not to Have Sustained Serious Injury ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys 1999-09-16 |
Text
I l
i l
ENCLOSURE 1 l
NOTICE OF VIOLATION Georgia Power Company Docket No. 50-366
- Hatch Unit 2 License No. NPF-5 i
i The following violation was identified during an inspection conducted on February 22 - March 21, 1986. The severity level was assigned in accordance with the NPC Enforcement Policy (10 CFR Part 2, Appendix C).
Unit 2 Technical Specification (TS) 6.8.1.a requires that procedures shall
- be implemerted for Energency Core Cooling Systems (ECCS) in accordance with Appendix "A of Regulatory Guide 1.33. Revision 2, February 1978.
l Contrary to the above, on February 25, 1986, the Core Spray (CS) system jockey pump, 2E21-C002A, was found in a turned "0FF" position rather than in i its "AUT0/RUN" position, as required by procedure, 3450-E21-001-2, Revision l 0. This pump had been turned "0FF" on February 22, 1986, for oil addition, and equipment status change was not entered into the Plant Operator's Log, as required by procedure, 31G0-0PS-007-05, Revision 0.
This is a Severity Level V violation (Supplement 1).
Pursuant to 10 CFR 2.201, you are required to submit to this office within 30 days of the date of this Notice, a written statement or explanation in reply,
> including: (1) admission or denial of the alleged violation; (2) the reasons for the violation, if admitted; (3) the corrective steps which have been taken and the results achieved; (4) corrective steps which will be taken to avoid further violation; and (5) the date when full compliance will be achieved.
Security or safeguards information should be submitted as enclosure to facilitate withholding it from public disclosure as required by 10 CFR 2.790(d) or 10 CFR 73.21.