r JUN 3 01986 Docket No. 50-461 Mr. Frank A. Spangenberg Manager - Licensing and Safety Clinton Power Station P.O. Box 678 Mail Code V920 Clinton, Illinois 61727
Dear Mr. Spangenberg:
SUBJECT:
EXPIRATION DATE FOR CONSTRUCTION PERMIT NO. CPPR-137, CLINTON POWER STATION, UNIT NO. 1 As you are aware, Construction Permit No. CPPR-137 for the Clinton Power Station, Unit No.1 expires October 1, 1986. Although it is currently antici-pated that an operating license will be issued for Clinton prior to that time, we wish to remind you that a request for extension of the construction permit should be submitted at least 30 days prior to its expiration date to protect against any unforeseeable circumstances that could delay issuance of an operating license.
Original signed by Walter R. Butler, Director BWR Project Directorate No. 4 Division of BWR Licensing cc: See next page DISTRIBUTION Docket File NRC PDR LPDR PD#4 Rdg.
RBernero WHouston JPartlow B607090550 860630 BGrimes
{M ADOCK o g
Edordan M0'Brien BSiegel ACRS (10)
/3
/
Goddard, OELD i
BSiegel I WButler DBL:PD#
DBL:PD#4 6/p/86 6/,10 /86
N (p**"c%'o UNITED STATES g,
g NUCLEAR REGULATORY COMMISSION e
g E
WASHINGTON, D. C. 20555
\\
/
JUN 30 W Docket No. 50-461 Mr. Frank A. Spangenberg Manager - Licensing and Safety Clinton Power Station P.O. Box 678 Mail Code V920 Clinton, Illinois 61727
Dear Mr. Spangenberg:
SUBJECT:
EXPIRATION DATE FOR CONSTRUCTION PERMIT N0. CPPR-137, CLINTON POWER STATION, UNIT NO. 1 As you are aware, Construction Permit No. CPPR-137 for the Clinton Power Station, Unit No.1 expires October 1, 1986. Although it is currently antici-pated that an operating license will be issued for Clinton prior to that time, we wish to remind you that a request for extension of the construction permit should be submitted at least 30 days prior to its expiration date to protect against any unforeseeable circumstances that could delay issuance of an operating license.
Walter R. Butl'er, Director BWR Project Directorate No. 4 Division of BWR Licensing cc:
See next page
N Mr. Frank A. Spangenberg Clinton Power Station Illinois Power Company Unit I cc:
Mark Jason Assistant Attorney General Public Utilities Division Office of the Attorney General State of Illinois Center Richard B. Hubbard 100 West Randolph Street - 12th Floor Vice President Chicago, Illinois 60601 Technical Associates 1723 Hamilton Avenue - Suite K Mr. D. P. Hall San Jose, California 95125 Vice President Clinton Power Station Cnairman of DeWitt County P. O. Box 678 c/o County Clerk's Office Clinton, Illinois, 61727 DeWitt County Courthouse Clinton, Illinois 61727 Mr. John Greene Manager-Nuclear Station Engineering Dpt.
Director, Criteria & Standards (ANR-460)
Clinton Power Station Office of Radiation Programs P. O. Box 678 U. S. Environmental Protection Agency Clinton, Illinois 61727 Washington, DC 20460 Sheldon Zabel, Esquire EIS Review Coordinator Schiff, Hardin & Waite Environmental Protection Agency 7200 Sears Tower Region V 233 Wacker Drive 230 S. Dearborn Street Chicago, Illinois 60606 Chicago, Illinois 60604 Resident Inspector Director, Eastern Environmental V. S. Nuclear Regulatory Commission Radiation Facility RR 3, Box 229 A U. S. Environmental Protection Agency Clinton, Illinois 61727 P. O. Box 3009 Montgomery, Alabama 36193 Mr. R. C. Heider Project Manager Illinois Department of Nuclear Safety Sargent & Lundy Engineers Division of Engineering 55 East Monroe Street 1035 Outer Park Drive, 5th Floor Chicago, Illinois 60603 Springfield, Illinois 62704 Mr. L. Larson Project Manager General Electric Company 175 Curtner Avenue, N/C 395 San Jose, California 95125 Regional Administrator, Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 26