ML20199L020

From kanterella
Jump to navigation Jump to search
Response Team Activities Insp Repts 50-445/85-16 & 50-446/85-13 on 851101-30.Violation Noted: Failure to Verify Performance to Procedure Requirements for Hilti Bolt Installation
ML20199L020
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/04/1986
From: Barnes I, Ellershaw L, Hale C, Andrea Johnson, Will Smith, Wagner P, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20199K948 List:
References
50-445-85-16-01, 50-445-85-16-1, 50-446-85-13, NUDOCS 8604100278
Download: ML20199L020 (34)


See also: IR 05000445/1985016

Text

.

APPENDIX D

COMANCHE PEAK RESPONSE TEAM ACTIVITIES INSPECTION REPORT

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

,

NRC Inspection Report:

50-445/85-16

Permits: CPPR-126

50-446/85-13

CPPR-127

Category: A2

Dockets:

50-445

e

50-446

Applicant: Texas Utilities Electric Company (TUEC)

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas

75201

Facility Name: Comanche Peak Steam Electric Station (CPSES). Units 1 & 2

Inspection At: Glen Rose, Texas

Inspection Conducted: November 1-30, 1985

Inspectors:

e

d

Y / 76

L' E. Ellershaw, Reactor Inspector, Region IV

Dalfe /

CPSES Group

(paragraphs 1, 5, 6.g - 6.h, 6.k. 7.f - 7.t)

3htf86

W. F. Smith, Resident Reactor Inspector (RRI)

Date

Region IV CPSES Group

(paragraphs 1, 6.c - 6.f)

ck$t s

+/Wh6

[ C. J. Hale, Reactor Inspector, Region IV

Date

CPSES Group

(paragraphs 1, 2, 3, 4, 6.b, 6.1 - 6.j)

_

&Oh$

?

G

.

.

2

9 C.uk e

ahus6

P. C. Wagner, ReactTr Inspector, Region IV

Date

CPSES Group

d

,

(paragraphs 1, 6.a. 7.a - 7.e)

Sm

B/&/P&

p A. R. Johnson, Reactor Inspector, Region IV

Date

CPSES Group

Consultants: EG&G - R. Bonnenberg, J. Dale, L. Jones, A. Maughan, W. Richins,

R. VanderBeek

Parameter - J. Birmingham, D. Brown, J. Gibson, K. Graham,

D. Jew

Reviewed By:

%

w4//J%

I. Barnes, Group Leader, Region IV CPSES

Date

Group

//hj/C

Approved:

'

T. F. Westerman, Chief, Region IV CPSES Group

Date

Inspection Summary

Inspection Conducted: November 1-30, 1985 (Report 50-445/85-16; 50-446/85-13)

Areas Inspected: Nonroutine, unannounced inspection of applicant actions on

previous inspection findings, Hilti bolt inspections, and Comanche Peak Response

Team (CPRT) issue - specific action plans (ISAPs). The inspection involved

2008 inspector-hours onsite by 6 NRC inspectors and 11 consultants. A summary

of NRR and IE audit / inspection activities is provided in paragraph 4 of this

appendix.

i

Results: Within the three areas inspected, four violations (unacceptable design

basis for grouting Richmond inserts, paragraph 5; failure of QC inspectors to

detect undersize welds, paragraph 6.k; failure to verify confomance to procedure

requirements for Hilti bolt installation, paragraph 6.k; QC inspector acceptance

of an HVAC duct system exhibiting damage and an unacceptable gasket gap, para-

graph 7.k) and three deviations (failure to comply with approved instructions in

'

performance of reinspections, paragraphs 7.a. 7.b

7.e. 7.1, 7.1, 7.n, and 7.q;

inadequate quality instruction (QI) for liner measurements, paragraph 7.1;

inadequate review of reinspection documentation, paragraph 7.n) were identified.

.

'

.

3

DETAILS

1.

Persons Contacted

  • S. R. Ali, TUGCo Staff Engineer, TUGCo Nuclear Engineering (TNE)

W. Bailey, ERC Supervisor, QA/QC Reinspection Engineering

  • C. T. Brandt, TUGCo Quality Engineering Supervisor
  • D. W. Braswell, TUGCo Engineering Superintendent, Plant Operations

C. I. Browne, Project Manager, R. L. Cloud & Associates, Inc.

-

(RLCA)

R. Brown, ERC Lead Civil / Structural Engineer

  • R. E. Camp, Assistant Project General Manager, Ur.it 1 (Impell

Corp.)

J. Cardoza, TUGCo System Engineer

J. D. Christensen, ERC Deputy QA/QC Review Team Leader

  • D. E. Deviney, TUGCo Operations QA Supervisor

J. Finneran, TUGCo Lead Pipe Support Engineer

  • S. M. Franks, Special Projects and Technical Support Lead (Impell

Corp.)

E. L. Gastenel, TUGCo System Test Engineer

  • P. Halstead, TUGCo Site QC Manager
  • J. L. Hansel, ERC QA/QC Review Team Leader

J. Honekamp, TERA TRT Issues Manager

  • C. R. Hooten, TUGCo Project Supervisor, THE Civil
  • R. A Jones, TUGCo Manager, Plant Operations

D. M. McAfee, TUGCo QA Manager

G. M. McGrath, TUGCo Licensing / Compliance Supervisor

  • J. T. Merritt, TUGCo Assistant Project General Manager, Unit 2
  • C. K. Moehlman, TUGCo Project Mechanical Engineer
  • A. A. Patterson, ERC Reinspection Engineering Supervisor
  • F. L. Powers, TUGCo Unit 1 Building Manager

C. M. Puffer, TUGCo System Test Engineer

  • G. R. Purdy, Brown & Root (B&R) QA Manager

J. G. Red, TUGCo Technical Support Supervisor

  • R. B. Seidel, TUGCo Operations Superintendent
  • J. C. Smith, TUGCo Operations QA

C. Spinks, ERC Inspection Supervisor

  • J. Streeter, TUGCo Executive Assistant to Executive Vice President

P. Streeter, TERA Senior Mechanical Engineer

P. Turi, TEPA Issue Coordinator

  • W. I. Vogelsang, TUGCo Coordinator, Electrical and Instrumentation

and Controls

  • C. H. Welch, TUGCo QC Services Supervisor
  • D. W. Westbrook, TUGCo Project Control Supervisor, Pipe Support

Engineering

M. J. Wise, CPRT Testing Review Team Leader

  • Denotes those persons who attended the exit interview.

The NRC inspectors also contacted other CPRT and applicant employees during

this inspection period.

.

.

4

2.

Applicant Actions on Previous Inspections Findings

(Closed) Unresolved Item (445/8514-U-19):

Certification to QI-QP-11.8-7

could not be located for a TUGCo inspector who performed original inspec-

tion with respect to instrumentation installation Verification Package

No. R-E-ININ-060. Additional documentation was located by the applicant

i

during this report period which resolved the question concerning the TUGCo

'

inspector's certification to QI-QP-11.8-7.

3.

CPRT Program

The applicant's responses to the detailed NRC staff coments on the CPRT

Program Plan, Revision 2, were forwarded to NRR by TUGCo letter of

November 22, 1985. This submittal included a preliminary copy of the

umbrella QA program; i.e., CPRT Third-Party Quality Assurance Program.

4.

NRR and IE Audit / Inspection Activities

a.

NRR: A site inspection was performed on November 5 and 20, 1985, of

the Stone and Webster (SWEC) walkdown. An audit was performed at

Ebasco, New York, on November 8, 1985, to review specifications and

design documents related to cable tray / conduit supports. A site audit

was performed on November 11, 1985, of the construction adequacy

program as it relates to the SWEC piping and pipe support effort. A

CCL test of conduit supports and components was observed at Charlotte,

North Carolina, on November 13, 1985.

A site inspection was performed

with Region IV participation during November 18-22, 1985, of as-built

drawings for Unit 1 cable tray supports. An audit of homogeneity of

design activities was performed at TERA, Bethesda, Maryland, on

November 4-6 and 12-13, 1985. An audit was performed on November 25,

1985, at SWEC, New York, with respect to nonseismic piping effects on

seismic design piping.

b.

IE:

Inspection activity which was performed, in part, in November 1985

Es previously documented in NRC Inspection Report 50-445/85-14;

50-446/85-11.

Copies of reports for these activities will be placed in the Public

Document Room upon completion. The results of the Unit 1 cable tray

support inspection performed by NRR and Region IV will be documented in a

Region IV inspection report.

5.

Hilti Bolt Inspection

An independent measurement inspection was performed by NRC Region I

personnel during September 9-19, 1985, which was documented by Appendix F

of NRC Inspection Report 50-445/85-13; 50-446/85-09. This inspection

included examination of 124 installed Hilti anchor bolts with respect to

'

.

5

embedment depth, bolt spacing and length, and diameter of individual bolts.

One bolt was identified by ultrasonic examination (UT) during this inspec-

tion as appearing to be underlength.

Separate subsequent reexaminations by

applicant and Region IV personnel confirmed that the questioned bolt was,

in fact, of the correct length. Applicant personnel noted, however, during

their verification activity that six other Hilti bolts used in the support

installation were identified by their marking (i.e., star stamp) as being a

Super-Hilti type, although the drawing required use of only a regular Hilti

type. UT by applicant personnel of these bolts identified that the bolts

were misidentified, in that they were established to actually be regular

Hilti bolts.

As a result, nonconformance report (NCR) M-18708 was initiated on

September 26, 1985, in order to properly document and correct this

condition. Concurrently, corrective action report (CAR) 058 was initiated

,

in order to:

(a) identify Super-Hilti design required installation loca-

'

tions which were installed prior to March 1982, and (b) to perform UT on a

randomly selected sample of 60 supports. March 1982 was the date on

which application of the star stamp, designating Super-Hilti type bolts,

became a QC controlled operation.

The CAR further stated that any identi-

fied deviations from design would be cause for expansion of the sample to

100% of all Super-Hilti installations made prior to March 1982.

Because of the potential for installation of misidentified regular Hilti

bolts rather than the design required Super-Hilti bolts, NRC Region IV

initiated an independent inspection. A total of 64 ASME component

supports, which were located inside containment and containing 247 anchor-

bolts, were selected for UT. Of the 247 anchor bolts examined, 246 were

identified with the star-stamp marking. All of these were verified to be

of the Super-Hilti type.

UT of the one unmarked anchor bolt revealed that this bolt was not a Hilti.

The original construction / installation documentation package was reviewed

in order to assess the condition. The package did not reflect usage of

anything other than the required Hilti bolt. Discussions with applicant

personnel resulted in their review and subsequent identification of

Component Modification Cards (CMCs) which had been misfiled. The CMCs

revealed that a Richmond insert had been substituted for a Super-Hilti

bolt. Further investigation revealed that Design Change Authorization

(DCA) 10633 dated July 20, 1981, had been issued which allowed the use of a

shorter Super-Hilti than what was originally called for; i.e.,11 inches.

This apparently was the result of an interference.

The 11-inch Super-Hilti was installed between July 20, 1981, and August 24,

1981. Subsequently, DCA 13349 dated May 17, 1982, was issued allowing the

replacement of i.he Super-Hilti with a Richmond insert. An associated

Concrete Chipping Request (CCR) dated May 24, 1982, indicated that the

Super-Hilti had pulled out.

Required calculations to support the modifica-

tion were performed on June 19, 1982. The CCR provides the following

instruction: " Chip out concrete 5 inches dia. x 8 inches deep for 1 inch

Richmond insert." A handwritten note on the CCR states, " Complete 5-26-82."

An inspection report (IR) No. IRC-7542 dated February 10, 1983, attests

that all grouting pre-placemeat, placement, and inspection attributes were

satisfactory.

0

6

During the NRC inspector's review of the above documentation, it was noted

that DCA 13349 failed to provide instructions or procedures for the accomp-

lishment of the modification activity.

It was further noted that the

calculations failed to consider the shear capacity of the grout-concrete

interface.

These conditions constitute a violation of Criterion III of Appendix B to

,

10 CFR Part 50 (445/8516-V-08).

s

6.

CPRT ISAPs (Excluding ISAP No. VII.c)

a.

Inspection Reports on Butt Splices (ISAP No. I.a.2) and Butt Splice

Qualification (ISAP No. I.a.3)

Status of CPRT Activity

Phase II actions for ISAP No. I.a.2 have been completed and Phase III

reinspections are in progress.

The splices involved in the reinspec-

tions are environmental butt splices, and uninsulated splices covered

with heat shrink tubing.

The applicant has completed the reinspection

of 38 of the 76 cables listed in NCR E-85-1006305, Revision 1.

Status of NRC Inspection Activity

The review of CPRT ISAP Nos. I.a.2 and I.a.3 has been completed and

the review of the Phase III program is in progress.

A review of the

results of 10 cable reinspections, Work Orders C850003404 and 3441,

showed that the following NCRs were generated:

NCR No.

Item (s) Identified

E85-101532

One conductor was twisted and the cable

bend radius was violated.

E85-101533

Butt splice " shims" were not installed

as had been indicated on a previous IR.

E85-101534

The flexible conduit had a cut in the

outer jacket.

E85-101535, Revision 1

Two torminal blocks were broken.

E85-101536, Revision 1

Butt splice " shims" were not installed

as had been previously indicated in an

IR and the heat shrink tubing was not

installed in accordance with the

manufacturer's instructions.

E85-1016575

The heat shrink tubing was not installed

per the manufacturer's instructions.

E85-101762

Seven terminal blocks were cracked or

broken.

..

.

(

_

-

-

.

7

NRC inspectors witnessed reinspections of cables E0119863A, E0119865A,

E0100821Z, E0100822Z, and EG100861Z.

During inspections of cables

E0119863A and E0119865A, it was noted that the length of the conduits

between the end device and the associated junction box was longer than

allowed by Drawing 2323-EI-1701, Revision 11.

This is an unresolved

item pending completion of review of the applicability of the drawing

detail to the installation (445/8516-U-09).

No NRC violations or deviations were identified.

b.

QC Inspector Qualifications (ISAP No. I.d.1)

Status of CPRT Activity

The Special Evaluation Team (SET) is evaluating information received

in TUGCo memorandum TUQ 3426. This memorandum was a response to the

SET evaluation of historical electrical and all current non-ASME

inspectors' qualifications.

If this additional information is

determined to not establish the qualifications for the inspectors, a

letter detailing the specific area of inadequacy is sent to the QC

manager requesting additional response.

Discrepancies not resolved

advance the inspector to Phase III of ISAP No

I.d.1 for reinspection.

Reinspection activity for the seventh inspector placed into Phase III

of ISAP No. I.d.1 has been completed and the results report is in

preparation.

Reinspection activity for an A5ME-related inspector

identified for Phase III has not begun and is awaiting inspection

packages from B&R.

Status of NRC Inspection Activity

The NRC inspector reinspected 33 conductor terminations as part of a

continuing check on the adequacy of ERC reinspection effort conducted

for Phase III of ISAP No. I.d.1.

The NRC reinspection results were

in agreement with those obtained by ERC. The SET transmittal and

TUGCo response pertaining to qualification status of non-ASME

inspectors has been reviewed.

Further SET evaluations will be

monitored as they are made.

No NRC violations or deviations were identified.

c.

Hot Functional Testing Data Packages (ISAP No. III.a.1)

In order to maintain a correlation between areas inspected and the

applicable sections of the ISAP, this inspection report will address

each area using the ISAP paragraph number assigned by the applicant.

During the inspection period of August 1-31, 1985 (see Appendix E of

InspectionReport'50-445/85-11), paragraphs 4 1.1 thru 4.1.6 were

followup inspected, and paragraph 4.1.7 was started but not completed.

During the inspection period of September 1-30, 1985 (see Appendix E

of NRC Inspection Report 50-445/85-13), paragraphs 4.1.7 and 4.1.8

'

.

8

were comple

ing this inspection period, the remaining

paragraphs i.

i No. III.a.1 were followup inspected as indicated

below:

4.1.9

In accordance with the sampling plan guidelines established

by the applicant for the remaining 139 completed preopera-

tional test data packages, the applicant committed to sample

60 items comprising test deficiency reports (TDRs), test

procedure deviations (TPDs), and FSAR commitments to

demonstrate the capability of systems to function as

designed.

These items were reevaluated utilizing the

attributes in Attachment 1 of ISAP No. III.a.1.

A followup

inspection was conducted by the NRC inspector to ensure both

that the results of reevaluations were consistent with the

guidelines delineated in Attachment 1, and that the

dispositions were consistent with regulatory requirements.

The NRC inspector sampled 20% of the list of items identi-

fied by the applicant. This sampling consisted of seven

TPDs, three Tuus, and two FSAR commitments.

No NRC violations or deviations were identified.

4.1.10

The applicant committed to incorporate the guidelines of

ISAP No. III.a.1, Attachment 1, into the applicable startup

administrative procedures to assure that the concerns

expressed by the NRC Technical Review Team (TRT) would be

addressed in a consistent manner during future test results

reviews.

The NRC inspector reviewed the Startup Administra-

tion Procedures Manual and verified that the above guidelines

were incorporated into Revision 6 of CP-SAP-11, " Review,

Approval and Retention of Test Results," dated July 8, 1985.

In addition, the applicant incorporated an improved method

of Joint Test Group (JTG) reviews. The procedure now

requires all JTG members to document their review comments

and submit them to TUGC0 Startup for resolution.

The

resolutions are then to be documented and redistributed to

all of the JTG members, so that each has an opportunity to

evaluate the resolution to all comments before approving the

data package.

The NRC inspector questioned whether or not

the comments and resolutions would become a permanent part

of the JTG-approved data packages.

The response was that

the intent of Section 4.2.1.5 of CP-SAP-11, which describes

supporting documentation requirements for data packages, is

to include the JTG comments and resolutions.

4.1.11

The applicant committed to determine the root cause(s) and

evaluate the potential for generic implications related to

the issues and findings in ISAP No. III.a.1.

When asked by

the NRC inspector to produce evidence that this had been

done, the applicant indicated that the final results report

would contain the information, but it had not been completed

yet. As such, this shall be tracked as an open item

(50-445/8516-0-10).

,-

'

.

9

Followup inspection of ISAP No. III.a.1 is completed pending closure

of the above open item and those items identified in Appendix E of

NRC Inspection Reports 50-445/85-11;50-446/85-06 and 50-445/85-13;

50-446/85-09; i.e., unresolved item 445/8511-U-02 and open items

445/8511-0-02, 445/8511-0-03, 445/8513-0-07, and 445/8513-0-08.

No NRC violations or deviations were identified.

d.

JTG Approval of Test Data (ISAP No. III.a.2)

During the 1984 TRT inspection of testing programs, the NRC inspector

noted that if a preoperational test is deferred into the Initial

Startup (ISU) program, which commences after_ initial fueling, the

completed results data would be reviewed by the Station Operations

Review Committee (SORC) in lieu of the JTG. The version of the FSAR

in effect at the time of the inspection did not provide for this shift

in review responsibility; i.e., the FSAR stated that the JTG is

responsible for reviewing preoperational test data. Deferring,this

testing to another time frame, or incorporating the deferred

preoperational tests in ISU procedures, did not in itself relieve the

JTG of this responsibility.

The action required by Supplement to Safety Evaluation Report (SSER)

No. 7 and accordingly the commitment in.ISAP No. III.a.2 was to revise

the FSAR. During the followup inspection, the NRC inspector verified

that the FSAR had been revised (see Amendment 54,'Section 14.2) to.

clarify the division of responsibility between the JTG and the SORC.

The FSAR now supports station procedures which prescribe the method of

deferral of preoperational tests from the preoperational test program,

which is the responsibility of the JTG, to the ISU program, which is

the responsibility of the SORC, a similarly qualified group. _ This

issue is closed.

~

No NRC violations or deviations were identified,

e.

Technical Specifications for Deferred Tests (ISAP No. III.a.3)

During the TRT inspection of test programs in the preoperational test

area, the NRC Operations resident inspectors expressed concern that

the orderly progress of ISU testing may be hampered by Technical

Specification (TS) limiting conditions for operation, due to the

nature and extent of the preoperational tests which had been deferred.-

In order to achieve the plant conditions (i.e., hot plant at normal

pressure and temperature) to conduct the deferred preoperational

' tests, the TS requires some of the systems being tested to be operable.:

However, operability cannot be verified until preoperational' testing

is completed. Since then, the applicant conducted another hot' testing

'

.

10

,

sequence in November and December 1984, at which time most of the

deferred tests were completed.

In a letter dated January 24, 1985,

the NRC closed this issue and thus the concern did not appear in

SSER No. 7.

~

There is no followup inspection required. This item is closed.

f.

Preoperational Testing (ISAP No. III.d)

'

During the TRT inspection of the preoperational testing program,

conclusions were reached indicating that none of the related allega-

tions and findings had either safety significance or generic implica-

tions, except that past document control system problems may have

affected the testing program.

Details of these conclusions and

findings are in SSER No. 7.

The primary concern was that past

preoperational testing may not have been conducted using fully updated

procedures because of the difficulties system test engineers (STEs)

had in obtaining design document updates.

In response to the TRT's concerns over possible past document control

impacts on testing, the applicant committed to actions that establish

measures to provide greater assurance that current design data was

utilized in testing, and to determine whether or not past document

control system problems did not adversely affect the testing program.

In the ISAP, this is broken down into three action categories:

4.1.1

Assessments, administrative procedural changes, and training

to ensure an adequate program is in place to maintain test

procedures current.

4.1.2

Detailed record reviews to determine the effect of Document

Control Center (DCC) problems on the testing program.

4.1.3

Determinationofrootcause(s)andevaluationofthe

potential for generic implications.

The NRC followup inspection of actions taken in accordance

with this ISAP commenced with 4.1.1 during this inspection

period and will continue during subsequent periods.

For

the sake of clarity and tracking, the ISAP No. III.d

paragraph numbers are indicated below.

4.1.1.1

The applicant comitted to revise CP-SAP-21, " Conduct of

Testing," to include instructions for STEs to review test

procedures approximately two weeks prior to the scheduled

test date to help facilitate timely updates and thus

eliminate last-minute complex reviews. The NRC inspector

verified Section 4.9.3 of CP-SAP-21 (Revision 3) as having

this requirement as of January 11, 1985.

- -

- -

.

11

4.1.1.2

The applicant committed to instruct STEs on the new

requirements of CP-SAP-21.

This was verified to be complete

by the NRC followup inspector by review of documented

evidence that the training had been completed by January 14,

1985.

Sections 4.1.1.3 and 4.1.1.4 of ISAP No. III.d involve a review

of the CPSES document control program and interviews of STEs to

help assess the adequacy of existing procedures and methods.

When the NRC followup inspector attempted to review related

documentation, there were only a few rough, hand written notes

showing evidence of STE interviews, but no results or actions

from the review and interviews were available.

The applicant

,

explained that the final results report would address this,

'

therefore this part of the followup will be conducted later.

For tracking purposes, this is an open item (445/8516-0-11).

No NRC violations or deviations were identified.

g.

Plug Welds (ISAP No. V.d)

Status of CPRT Activity

Reinspection of the new random sample of 57 ASME Code,Section III

supports by ERC has been completed.

No unauthorized plug welds were

identified.

This new random sample was required as a result of the

.

NRC identifying that the original sample of supports included

f

unauthorized non-ASME Code,Section III supports.

Status of NRC Inspection Activity

'

(1) The NRC inspector has witnessed a total of 13 ERC reinspections

from the new random sample, of which the following 5 were

performed during this report period:

Component Support No.

Unit No.

SF-X-002-021-F43S

Common

SI-2-105-404-052K

2

CC-2-204-421-C53R

2

CC-1-065-007-533R

1

MS-2-RB-004-2

2

4

During the above reinspections, ERC did not identify any

conditions to the NRC inspector as subject to evaluation as

potential deviations.

The NRC inspector also witnessed the

macroetching of four component support base plates which

exhibited indications that suggested the possible existence of

plug welds.

Two of these base plates were identified during the

October inspection period.

The macroetching confirmed that plug

welds did not exist.

No NRC violations or deviations were identified.

i

'

.

12

(2) A total of four independent inspections has been conducted by

the NRC inspector, of which the following three occurred during

this report period:

Component Support No.

Unit No.

CS-2-AB-067-013-3

2

CC-2-050-700-A43K

2

CS-2-564-701-A33R

2

No NRC violations or deviations were identified.

(3) Documentation packages for the 13 reinspected and 4 independently

inspected supports were reviewed.

No discrepancies or missing

documents were identified.

No NRC violations or deviations were identified,

b.

Installation of Main Steam Pipes (ISAP No. V.e)

Status of CPRT Activity

The status of CPRT activity has not changed from the last reporting

period.

The results report is being reviewed by CPRT.

Status of NRC Inspection Activity

The preservice inspection documentation; i.e., UT and magnetic

particle examination reports are currently being reviewed.

In

addition, the results of the four UTs performed on the highest

stressed areas of loops 1 and 4 will be reviewed.

No NRC violations or deviations were identified.

i.

Nonconformance and Corrective Action Systems (ISAP No. VII.a.2)

Status of CPRT Activity

A review of current and historical procedures that controlled the

processing and documenting of deficiencies has been completed.

This

review was made to determine if programmatic deficiencies existed in

these procedures.

Sub populations of nonconformances have been

selected from the various systems used to document deficiencies.

These sub populations were based on-type of documentation, method of

processing, and time of occurrence in plant construction.

Addition-

ally, ASME and non-ASME related deficiencies were divided.

Random

samples have been generated for each sub population.

Review of the documentation is complete for approximately 360 NCRs.

Review of the remaining sub populations is ongoing.

If programmatic

deficiencies are found, root cause and generic implication will be

determined.

s

.

13

Status of NRC Inspection Activity

Checklists used by ERC to evaluate nonconformances were reviewed by

the NRC inspector.

It was noted that no evaluation of the dispositions

for adequacy was made on the checklists.

This omission may be resolved

by an ERC proposed review of dispositions for technical adequacy.

This is an open item (445/8516-0-12, 446/8513-0-08).

No NRC violations or deviations were identified.

j.

Audit Program and Auditor Qualifications (ISAP No. VII.a.4)

Status of CPRT Activity

The draft of the results report for this ISAP has been written and is

undergoing review and revision.

Status of NRC Inspection Activity

The NRC inspector reviewed background data for verification during a

future NRC audit of the corporate audit files.

No NRC violations or deviations were identified.

'

k.

Pipe Support Inspections (ISAP No. VII,b.3)

Status of CPRT Activity

The reinspections being performed under ISAP No. VII.b.3 deal with

pipe supports located in Room 77N and the 42 pipe supports previously

inspected by the TRT. All other pipe support populations and their

samples are being reinspected under ISAP No. VII.c, " Construction

Reinspection / Documentation Review Plan."

(1) Room 77N Pipe Supports

Reinspection of the 178 pipe supports in Room 77N, identified as

being nonconforming by TRT, has been completed. Of the 238 devi-

ations identified, 234 have been evaluated with 229 determined to

be valid.

(2) TRT Issues - 42 Pipe Supports

Of the 42 pipe supports identified by TRT as being nonconforming,

17 have been reinspected by ERC.

Physical reinspections _ are

being accomplished using QI-058, Revision 0.

Twenty-six

deviations have been issued with 22 processed as being valid.

_

'

.

14

.

Status of NRC Inspection Activity

(1) Room 77N Pipe Supports

(a) The NRC inspector has reviewed QI-037, Revision 0.

To date,

seven reinspections have been witnessed.

The following

seven independent inspections were performed by the NRC

inspector during this report period:

Verification Package No.

Support No.

Unit No.

I-S-PS7N-190

SI-1-039-044-S42R

1

I-S-PS7N-031

CC-1-131-010-S43R

1

I-S-PS7N-038

CC-1-155-011-S43R

1

I-S-PS7N-039

CC-1-155-012-543R

1

I-S-PS7N-095

CS-1-158-033-542R

1-

I-S-PS7N-129

PS-1-SB-006-004-2

1

I-S-PS7N-143

SI-1-SB-043-008-2

1

(b) During the above independent inspections, the NRC inspector

identified the following conditions:

I-S-PS7N-031:

The welds joining a wide flange (item 8) to

a plate (item 9) consisted of a fillet weld on both sides

of the wide flange of approximately 22 inches in length.

Approximately 20 inches of the welds were undersize by a

minimum of 1/16 inch with respect to the 1/4-inch _ fillet

required by Drawing CC-1-131-010-543R, Revision 4, and a

consecutive 2-inch segment was 1/8-inch undersize.

The

vertical welds on the outside of the wide flange joining two

plates (items 9 and 10) were also undersize by a minimum of

1/16 inch for more than 25% of the weld length.

Paragraphs 5.1.2 and 5.3 of B&R Procedure CP-NDEP-200 require-

plate and piping welds to be inspected'for size.

Review of

the applicable operation traveler, CC-1-131.010-S43R, and

associated weld data cards showed that the welds had been

previously inspected and accepted.

As a result of this

condition being identified, B&R-initiated NCR XI-708.

The failure to identify undersize welds is'a violation

(445/8516-V-13).

I-S-PS7N-190:

The NRC inspector measured a center-to-center

spacing of 10 1/2 inches.between a 1 1/4-inch Hilti bolt and

a 1-inch Hilti bolt on adjacent fixtures of support

SI-1-039-044-542R.

It was ascertained that this installation

had been inspected and accepted on December 21, 1981.

'However, review of Attachment l'in Revision 7 of B&R-

Procedure CEI-20 revealed that a minimum center-to-center-

spacing of 11 1/4 inches is required between 1 1/4-inch and

i

1-inch Hilti bolts.

This procedure further stated that this

~ inimum spacing applies to Hilti bolts detailed on separate

'

m

!

-_

_ - - - _ -

.

. - .

--. .

.,.

. -

- . .

. . .

-

._

'

.

15

.

adjacent fixtures and that violation of_ minimum spacing must

be approved by issuance of design change documents by the

applicable Comanche Peak Project Engineering design groups.

There was no evidence of any design change documents

approving this minimum spacing violation.

This failure to verify conformance to procedure requirements

,

is a violation (445/8516-V-14).

<

'

(2) TRT Issues - 42 Pipe Supports

(a) The NRC inspector reviewed QI-058, Revision 0, and QI-061,

Revision 0.

To date, three reinspections have been

witnessed with the following two performed during this

inspection period:

Verification Package No.

Support No.

Unit No.

I-S-PS42-25

CT-1-013-011-S22R

1

I-S-PS42-41

RH-1-020-003-522K

1

(b) During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-S-PS42-25:

(i) No lock nuts were present on clamp balts,

and (ii) location of bolt hole in relation to base plate

edge was incorrect.

I-S-PS42-41:

(i) Paint was observed on a spherical hearing,

and (ii) material was incorrectly identified.

Dispositions of the above findings are open items

,

(445/8516-0-15 and 445/8516-0-16).

No NRC violations or deviations were identified.

(c) The following five independent inspections were performed by

the NRC inspector during this report period:

Verification Package No.

Equipment No.

Unit No.

I-S-PS42-06

AF-1-035-029-S33A

1

I-S-PS42-024

CT-1-013-010-522K

l'

I-S-PS42-034

RC-1-052-016-C41K

1

I-S-PS42-033

RC-1-035-700-C41R

1

I-S-PS42-08

AF-1-059-003-S33R

1

(d) During the above independent inspections, the NRC inspector.

identified the following conditions:

_

_

_

.

1

16

I-S-PS42-06: The NRC inspector observed that three 1 1/4-inch

Hilti kwik bolts (from a total of eight), that were used to

attach two base plates of support AF-1-035-029-S33A to the

wall, had been installed through an embed plate.

It was

noted that this ir.stallation was inspected and accepted on

IR No. 15042 dated March 30, 1981.

B&R construction Procedure CEI-20, applicable to this

installation, was reviewed. Attachment 3 of CEI-20 allows

Hilti bolts to be placed as close as practical to the edge

of an embedded plate, without damaging the plate, as long as

there are no attachments to the plate within a minimum of

12 inches on both sides of the proposed Hilti bolt location.

Subsequent to this report period, applicant personnel

showed the NRC inspector that insertion of Hilti kwik

bolts through the embed plate had been authorized by DCA.

The adequacy of the engineering basis for the DCA is

considered an unresolved item pending NRC review (445/8516-

U-55).

7.

ISAP No. VII.c

a.

Electrical Cable

Status of_ CPRT Activity

>

ERC has completed 87 reinspections and 88 documentation reviews of

sampled electrical cable as of November 25, 1985.

Status of NRC Inspection Activity

(1) NRC inspectors have, as of November 25, 1985, witnessed 21 ERC

reinspections and performed independent reviews of 10 documenta-

tion packages. The following three independent reinspections of

sampled electrical cable were performed in this report period:

Verification Package No.

Cable No.

Unit No.

I-E-CABL-014

ER140509Z

1

I-E-CABL-063

E9123380

1

I-E-CABL-102

EG139517

1

(2) During the above independent reinspections, the following

condition was identified:

-

I-E-CABL-102:

Reinspection revealed that ERC inspectors did not

identify the disagreement of the physical routing with the cable

and raceway schedule, as required by Section 5.6 of QI-014,

Revision 0, dated July 18, 1985. The cable physically routes

into tray T13GCCP80 and then tray T13GCCP81. The cable schedule

routes this cable into T13GCCP81 and then T13GCCP80. This is an

NRCdeviation(445/8516-D-17).

.

_

-

.

17

..

i

b.

Cable Trays

j

Status of CPRT Activity

ERC has completed 89 reinspections and 83 documentation reviews of

sampled cable trays as of November 25, 1985.

Status of NRC Inspection Activity

i

(1) NRC inspectors have,'as of November 25,19C, witnessed 11 ERC

reinspections, performed independent reviews of 7 documentation

packages, and performed 6 independent ieinspections of sampled

cable trays. The following independent reinspection was

performed in this report period:

,

Verification Package No.

Cable Tray No.

Unit No.

I-E-CATY-077

T14BREC28

1

(2) During the above independent reinspection, the NRC inspector

identified that F.RC inspectors did not identify a missing bolt

and locking device on the splice plate joining tray section

',

T14BREC28 to T14BREC27 as required by Section 5.3.6 of QI-016,

Revision 1.

This is an NRC deviation (445/8516-D-18).

c.

Electrical Conduit

Status of CPRT Activity

ERC has completed 80 reinspections and 80 documentation reviews of

sampled electrical conduit as of November 25, 1985.

Status of NRC Inspection Activity

(1) NRC inspectors have, as of November 25, 1985, witnessed 14 ERC

reinspections, performed independent reviews of 15 documentation

'

packages and performed 5 independent reinspections of sampled

electrical conduit.

(2) The following two independent reinspections of sampled electrical

conduit were performed in this report period:

Verification Package No.

Conduit No.

Unit No.

I-E-CDUT-036

C12909546

1

I-E-CDUT-048

C16WO9519

1

No NRC violations or deviations were identified.

'

,

-

.

.

,

.

..

-.

.

-

'

.

18

4

(3) The following documentation review was performed for an

electrical separation inspection in this report perfod:

,

Conduit No.

Room No.

Un_it No.

C12G03270

100

1

During the above review, it was identified that the electrical

inspector who signed the " Electrical Separation Punchlist" and

" Electrical Separation Deficiency Report," which were attached

to IR E-1-0013528, had been certified for "All QI-QP11.3" as a

level II inspector, despite having failed the written examination

for QI-QP-11.3-29.

This condition was ascertained to have been

previously identified by the TUGC0 Audit Group (TAG) cnd is being

evaluated by SET. Thi's is an open item pending review of the SET

9

evaluationandaction(445/8516-0-19).

No NRC violations or deviations were identified.

,

d.

Electrical Equipmegt Installation

l

Status of CPRT Activity

ERC has completed 59 reinspections and 20 documentation review packages

of sampled electrical equipment installations as of November 25, 1985.

,

Status of NRC Inspection Activity

(1) NRC inspectors have, as of November 25, 1985, witnessed 11 ERC

reinspections, perforned independent reviews of 10 documentation

packages and performed 3 independent reinspections of sampled

electrical equipment ir.stallations.

.

,

I

(2) The following ERC reinspection of sampled electrical equipment

installation was witnessed during this report period:

,

Verification Package No.

Equipment No.

Unit _No.

'

I-E-EEIN-062

1E35

1

During the above reinspection, ERC identified the following

i

condition as subject to evaluation as a potential deviation:

Nuts on the studs for the penetration were not engaged flush with

!

top of stud threads.

,

Disposition of the above finding is an open item (445/8516-0-20).

No NRC violations or deviations were identified.

.

I

,

.

.

. .

.

. -

.

.

.

'

.<

1

19

(3) The following independent 'teinspections of electrical equipment

installations were parformed during this rep 6rt period:

Verification, Package Na.

Equipment No.

Unit No.

I-E-EEIN+050

CPX-ELDPEC-06

1

I-E-EEIN-055

CPI-ELOPEC-10

1

No NRC violations or deviations were identified.

-

'.

(4) Independent documentati4n reviews were performed of nine

verification packages during this . report period.

The results of

these reviews are open items per. ding comparison with ERC findings

when they become available (445/8516-0-11 through 445/8516-0-29),

e.

Instrumentation Equipment _ Installation

Status of CPRT Activity

ERC has completed 80 reinspections and 97 documentation reviews of

!

sampled instrumentation equipment installations as of November :25,1985.

Status of NRC Insnection Activity

.

(1) NRC fr.spectors nave, as of November 25, 1985, witnessed eight ERC

reinspections, performed independent reviews of five documentation

packages and performed six ir, dependent reinspections of sampled

instrumentation equipment installations.

,

(2) Of the six Independent NRC inspections performed, to date, the

'

"

following four occurred during this report period:

Verification _ Package No._

Eguipment No.

Unit No.

I-E-ININ-051

1- LT-932

.1

I-E-ININ-041

1-LT-930

1

I-E-ININ-049

1-FT-425

1

1-E-ININ-059

1-PT-124

1

During the above reirspections, the following conditions were

identified by the NRC inspector:

I-E-ININ 051:

The ERC inspector failed to identify and inspect

the required mininum bend radius for Bend No. 5.

This berd was

accessible for inspection.

I-E-ININ-041:

Bend No. 5 which was identified by the ERC

inspector as being inaccessible for measurement was found to be

accessible and inspectable.

!

l

.

-

,

..

.

_.

'

.

20

'

.

.

1-E-lNIN 059:

'(a) A swagelck fitting rear support C-24-04-51 was

observed to be touching the wall, thus violating the air gap

requirement; and (b) an air gap violation was identified between

'

tee tubing arid the wall penetration at the inside face of the

excess letdesn heat exchanger orifice room.

I-E-ININ 049:

(a) Installation identification tag for the low

pressure root valve was incorrectly marked with respect to

appitchble instrument identity, i.e., the tag on val e 1-RC-80618

which was assctiated with 01strument 1-FTe425, showed instrument

1-FT-424; (b) less than the required 1/84f nch air gap existed

between the high pressure sensing line and a steel member adjacent

'

to the isolation valve location; and (c) a loose bolt was observed

at the lov pressur6 sensing line flange attachment to the

differential pressure type instrument.

The above failures to inspect required attributes and identify

non-onfor' ming conditions constitute a deviation (445/8516-D-20h

00 ring the abote inspection, the ERC inspector additionally noted

that tags on immediat'ely adjacent lay pressure root valves were

also incorrectly marltd with retpect to applicable instrument

identity.

Tlie tag on valve 1-8C-80598, which was associated with

-

instrument 1-FT-424, showad instrument 1-FT-426.

The tag on

'

valve 1-RC-8060B, which was associated with instrumsnt 1-FT*426,

'

showed instrumeht 1-FT-425.

~

,

(3) irdependept documentation reviers were performed on three

'

verification packages during this report period,

The l'esults of

these rev$ews are open itehis pending comparison with ERC firdings

when they becone available (445/85M-0*31 through 445/8516'0-33).

f-

pipi.ig Syr*.em Bolted Joir.ts/.Materialp

Statys of CFET Activity

ERC has completed 72 reinspectlons of piping system bolted

joints / materials as of November 23,19Q5, from a total random aird

engineered sample size of 73.

Seyeo valid deviation repoFts (DRs)

were g'anerated as a result cf the above reinspections.

ERC has also cQmpleted 65 docm.ent revien on these packages.

Eight

valid ors have been generated as a result of the above documentation

reviews.

Status of NRC Inspection Acti_vity

i

(1) The NRC inspector has performed five independent inspections, to

date, of which the following occurred during this report period:

j

Verification Package No.

Drawing No,

Flange No.

UMt

-1

I-M-PBOM-035

BRP-D0-2-0G-056

5

?

i

No NRC violations or deviaticns were ident.ified.

+

.

.

.

.

.-..

'

.

21

(2) The NRC inspector performed independent document reviews of the

following packages during this report period:

Verification Package No.

Drawing No.

Flange No.

Unit

R-M-PBOM-018

BRP-SW-1-SB-003

1

1

R-M-PB0M-031

BRP-CS-1-AB-001

1

1

R-M-PB0M-042

BRP-SI-1-SB-012

1

1

No NRC violations or deviations were identified.

(3) The following independent NRC inspections were performed during

September 1985, but were not specifically identified in NRC

Inspection Report 50-445/85-13; 50-446/85-09:

Verification Package No.

Drawing No.

Flange No.

Unit

I-M-PBOM-003

BRP-CC-1-RB-038

4

1

I-H-PB0M-054

BRP-CC-1-RB-056

1

1

No NRC violations or deviations were identified,

g.

Small_ Bore Piping and Instrumentation Tube Welds / Material

Status of CPRT Activity

Reinspection of a random sample of 60 small bore pipe and

instrumentation tube welds and material from Units 1, 2, and common is

in progress.

To date, 45 small bore piping welds have been rein wected

by ERC. No deviations havo been identified.

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed seven reinspections performed.

by ERC, none of which occurred during this report period.

The

following two independent inspections were conducted in this report

period:

Verification Package No.

Pipe and Weld No__._

Unit No.

I-M-SBWM-004

WP-X-073-151R3, 3

Common

I-M-SBWM-005

MS-1-221-1303-2, 16

1

No NRC violations or deviations were identified.

h.

Large Bore Piping Welds / Material

Status of CPRT Activity

Visual reinspection of a random sample of 60 ASME Code,Section III

large bore piping welds hnd material from Units 1 and 2 is in progress.

-

-

-

-

.

.

._.

. _ -

.

._

'

,

22

To date, 45 large bore piping welds have been reinspected with one

deviation being identified. The deviattor,was evaluatcd as being

valid; however, it was determined to r.ot have safety significance.

Status of NRC Inspection Activity

To date, the NRC it.spectcr has w'itnessed eight reinspections by ERC,

none of which occurred during this report period. Tne following

independent inspection was conducted in this report period:

Verification Package No.

Pipe & Weld No.

Unit No.

,

I-M-LBWM-073

CS-X-010-151R3, ISA

Comon

No NRC violations or deviations were identift.ed.

1.

Large Bore _ pipe Supports - Rigid

Status of CP_RT Activity

j

Reinspection / verification of pipe support installations by ERC is in

' rocess with approximately 96% of the population sar.ple completed. A

p

,

total of 164 deviations have been identified of which 136, to date,

'

have been determined to be valid. ERC has determined that 70 of the

-

valid DRs are not safety significant, while the reminder are currently

being reviewed for safety significance.

Status of NRC Inspection Activity

(1) To date, five ERC reinspections have been witnessed to assure

compliance with QI-027, with the following being witnessed

'

during this report period:

'

Verification Package No.

Pipa Support No.

Unit _No.

.

!

j

I-S-LBSR-217

CC-1-197-008-C52R

1

'

During the reinspection, ERC identified the following to the NRC

'

inspector as subject to evaluation as potential deviations:

(a) clearances between the pipe -and the support were out-of-

tolerance, (b) undersize welds were present, and (c) component

n: ember lengths were not shown or) the design drawing.

Dispositionsoftheabovefindingsareanopenitem(445/2516-0-24).

No NRC violations or deviations were identified.

i

.

E-

..

-

.

-

'

.

23

(2) Five independent inspections of pipe support installations have

been performed, with the following three inspections performed

during this report period:

Verification Package No.

Pipe Support No.

Unit No.

I-S-LBSR-006

CC-1-146-008-S43R

1

I-S-LBSR-013

DD-1-016-016-S33R

1

I-S-LBSR-041

CC-1-126-702-F43R

1

,

During independent review of ERC Verification Package

No. I-S-LBSR-041 and the original installation documentation

package for pipe support Mark No. CC-1-126-702-F43R, a deviation

,

from commitment (445/8516-D-35) was identified. Section 5.6.1.A

'

of QI-027, Revision 0, states, " Verify welds are located as shown

on design drawings. Record any welds that are in addition to

those specified on the drawings (attachment 6.6)."

ERC did not

identify or document the existence of two additional field welds

which were not specified on the drawings, but were identified by

the issuance of " Vendor Supplied Component Modification Records"

that documented the performance of field welding.

,

J.

Large Bore Pipe Supports - Non-Rigid

Status of CPRT Activity

Reinspection / verification of pipe support installations by ERC is in

process with approximately 83% of the population sample completed. A

total of 234 ceviations have been identified of which 187, to date,

have been determined to be valid.

ERC has detennined that 72 of the

,

valid DRs are not safety significant, while the remainder are currently

.

being reviewed for safety significance.

,

Status of NRC Inspection Activity

(1) To date, six ERC reinspections of pipe support installations

have been witnessed to assure compliance with QI-029, with the

'

following being witnessed during this report period:

Verification Package No.

Pipe Support No.

Unit No.

I-S-LBSN-043

MS-1-150-033-C52K

1

1-S-LBSN-240

CC-1-040-019-E33S

1

(2) During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-S-LBSN-043:

(a) Component member length and location were

out-of-tolerance, (b) locking devices were missing, (c) spherical

,

.

-e.

-

m

. _

..

.-.

-

.-

- ..

i

.

,

24

I

bearing gap was out-of-tolerance, (d) safety lockwire on snubber

capscrew was broken, (e) paint.was present on spherical bearings,

(f) welder identification was not visible on pressure boundary

r

welds,and(g)snubberinterferencewithinsulationwasobserved.

I-S-LBSN-240:

(a) Component member identification was incorrect,

(b) bill of material items were not within fabrication tolerances,

(c) component member location was out-of-tolerance, (d) shear lug

to pipe clamp clearances were out-of-tolerance, (e) pipe clamp

bolts did not have full thread engagement, (f) locking devices

were missing, and (g) one Hilti bolt violated requirements for

perpendicularity,

Dispositions of the above findings are open items (445/8516-0-36

l

and 445/8516-0-37).

!

No NRC violations or deviations were identified.

(3) To date, five independent inspections of pipe support

installations have been perfomed. During this report period,

the following inspection was performed to assess the adequacy of

i

ERC reinspections:

i

Verification Package No.

Pipe Support No.

Unit No.

1

j

I-S-LBSN-003

SI-1-008-003-S42S

1

This effort revealed that ERC had perfomed the reinspection in

accordance with the requirements of QI-029.

No NRC violations or deviations were identified.

i

k.

HVAC Duct Supports

4

Status of CFRT Activity

~

A total of 89 HVAC duct supports were randomly selected from a

population of 2580 supports representing Units 1, 2, and common. To

i

date, ERC has reinspected 55 supports and initiated 142 DRs, primarily

in the areas of undersize welds and configuration discrepancies. Of

l

the 142 DRs,106 have, to date, been established as being valid.

'

Status of NRC Inspection Activity

(1) To date, the No.C inspector has witnessed seven ERC reinspections,

I

with the following four being performed during this report period:

(

Verification Package No.

Duct Support No.

Unit No.-

!

l

I-S-HVDS-029

SG-785-1H-RIF

1

[

I-S-HVDS-089

CB-810-IN-2BB

1

I-S-HVDS-103

CB-810-1N-2BD

1

r

l

I-S-HVDS-109

CB-854-2N-C30/C30-1

2

i

.

. . _ . -

-_

_,

_

-

,

,

.

.

25

(2) During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-S-HVDS-029:

(a) Weld symbols and weld locations were incorrect,

(b) welds were undersized, and (c) a Hilti Kwik Bolt violated

required embedment length.

l

I-S-HVDS-089:

(a) Member dimensions were incorrect, (b) welding

configuration was incorrect, (c) weld sizes were incorrect,

(d) incomplete fusion was noted in welds, and (e) weld undercut

4

was observed.

~

I-S-HVDS-103:

(a) Dimension violations, (b) duct dimension was

incorrect, (c) incorrect orientation was observed, (d) welds were

'

undersized, and (e) an unsatisfactory weld profile was noted.

I-S-HVDS-109:

(a) Weld location was_ incorrect, (b) welds were

undersize, (c) welding was not performed per weld symbol, and

(d) minimum thread engagement was unsatisfactory.

Subsequent to the inspection, DRs were initiated for the above

conditions.

Dispositions of the abc/e findings are open items (445/8516-0-38

through 445/8516-0-40 and 446/8513-0-09).

(3) During the witnessing of ERC's reinspection of support

CB-854-2N-C30/C30-1, the NRC inspector observed what appeared to

be significant damage to Flange Nos.-17 and 18 of Battery Room

Ventilation Exhaust Duct System EMD-3.

This observed condition

was not an attribute being reinspected by ERC at this time, and

was therefore not identified.

Further examination revealed that

this condition most likely was caused during installation, in

that the bolted flanges were force bent upwards approximately 30

degrees in order to preclude interference with an adjacent

concrete wall.

The force bending created a gasket gap of 1/4 inch

in the trough of the bend which is in excess of the maximum

'

allowable gap of 5/32 inch. A sealant type material was used to

fill in the excessive gap.

Review of the original installation

and inspection documentation revealed that this field modification

was neither reported nor documented on a Bahnson Installation

Interference Report or a Bahnson Deficiency & Disposition Report.

Further, the Bahnson QC IR dated April 1, 1983, which required

ductwork inspection for visual damage, reported that joints 1

through 18 of Duct System BRVE-EMD-3 had been inspected and

accepted. This failure to document field modifications and

identify nonconforming conditions is a violation (446/8513-V-10).

'

1

.-

.

_

_ _

d

'

.

'

26

.

~

(4) The NRC inspector conducted the-following five independent

~.

inspections during this inspection period:

VerificationiPackage No.

Duct Suppor.t No.

Unit No.

I-S-HVDS-010

AB-886-1L-WP2

1

I-S-HVDS-066

SG-773-2H-WP5

2

I-S-HVDS-057

SG-852-1J-1E

1

I-S-HVDS-065

CB-830-2N-1CV

-2

I-S-HVDS-122

DG-810-2K-PS1

2

i

No NRC violations or deviations were identified.

1.

Reinspection of Containment Liner and Tank Stainless Steel Liner

Status of CPRT Activity

~

A tank stainless steel liner was 100% reinspected representing 29 weld

seam packages.

Sixty-two weld seams were randomly selected from

Units 1 and 2 containment liners incloding both dome and cylindrical

liners.

ERC reinspections and document revie'ws are 100% complete.

However, changes to QI-031, Revision 0,.are contemplated and may

require additional reinspection.

Eighty-two valid deviations have been identified by ERC which are

currently being reviewed for safety significance.

Status of NRC Inspection Activity

.

(1) The NRC inspector had previously witnessed 9 reinspections

representing approximately 10% of the random sample of 91.

The

NRC inspector independently reinspected the following three

containment liner and tank stainless steel liner weld seams

during this report period

Verification Package No.

Joint No.

Unit No.

-

I-S-LINR-08

8D

1

3

I-S-LINR-12

P88

-

2

I-S-LINR-61

PS2

2

/

(2) During the independent reinspections, the NRC inspector noted the

following conditions:

I-S-LINR-61:

Excessive reinforcement up to 7/32 inch was

identified for approximately 80% of the weld length.

This weld

seam is between the 3/8-inch cylindrical liner plate and a pipe

penetration with a 3 to 1 taper.

QI-031, Revision 0, does not

provide specific instructions for the measuring of reinforcement

,

of welds connecting a tapered item to a uniform thickness item.

However, Section 5.1. A3c states, .in p' art, " Verify that the height

4.

-

.

,

27

of the reinforcement on each face of the seam does not exceed

3/32-inch." All NRC measurements were taken from the liner plate

to the center of the weld seam.

The ERC inspector accepted this

attribute without comment or obtaining special instructions.

This is an NRC deviation (446/8513-D-11).

I-S-LINR-08:

The NRC inspector rejected attribute A.1.d of the

checklist regarding contour measured from a 10-foot straight edge.

Section 5.1.Al of QI-031, Revision 0, states, in part, with

respect to attribute A.1.d, "The following local contour devia-

tions are to be verified: . . . A maximum of 3/4 inch deviation

from a 10 foot straight edge placed in the vertical direction

between the horizontal weld seams." The NRC inspector measured a

1 1/4-inch deviation from the straight edge. The liner plate-in

this location is apparently somewhat convex near the center of a

vertical cross section.

The NRC inspector measured the 1 1/4-inch

deviation by placing the 10-foot straight edge in contact with

the liner plate for approximately the top 30% of the vertical

cross section and measuring at the bottom of the cross section

just above the lower horizontal weld seam.

The ERC inspector

stated that he measured the deviation from the 10-foot straight

edge by placing the straight edge in contact with the greatest

inward vertical deviation and adjusting the position of the

straight edge until equal maximum deviations exist for the upper

and lower portion of the vertical cross section.

The ERC

inspector measured a maximum deviation of 3/4 inch using this

method and accepted the attribute.

Values of measurements

'

obtained by these methods are not precise and in this case varied

by as much as a factor of two.

QI-031, Revision 0, fails to

provide concise instructions for the measuring of this attribute,

This is an NRC deviation (445/8516-D-41).

,

I-S-LINR-08, -12, and -61:

It was noted with respect to the base

material local contour attributes for cylindrical liner verifica-

tion packages that the ERC inspector had entered "N/A" (not

applicable) and " dome only" on the checklists.

Section 5.1.A.1

in Revision 0 of QI-031 states, in part, "The following local

contour deviations are to be verified:

A maximum of 1-inch gap

between the cylindrical liner or dome shell plate and a 6 feet

long template curved to the required radius . . . ." Thus, the

local contour attribute is applicable and does apply to the

cylindrical liner.

The failure to inspect the required attribute

is an NRC deviation (445/8516-D-42).

The NRC inspector noted that attribute A.1.b was not applicable.

Paragraph 5.1.A.1 of QI-031, Revision 0, states, in part, with

respect to attribute A.1.b, "The following local contour

deviations are to be verified:

. . . A maximum 1 1/2-inch gap

when the 6 feet long template is placed across 'the dome weld

l

seams when measuring horizontally or vertically." Therefore,

l

attribute A.1.b applies only to the dome weld seams.

Review of

the completed checklists revealed that the ERC inspector had

!

_-

_ -

__

._.

.

._

_

. . _ _

__

_ _ _ . . _ .

__

_

.

I

28

4

accepted this attribute for these three verification packages

which are weld seams on the cylindrical _ liner. The.NRC inspector

'

then reviewed the ERC Description Memorandum QA/QC-RT-293 which

lists Gibbs and Hill (G&H) Containment Liner Specification

2323-SS-14, Revision 4, dated January 10, 1979, as a reference

for developing QI-031 Revision 0.

Paragraph 8.2.2.1.2.b in G&H

Specification 2323-SS-14, Revision 4, states, in part, "The -

i

following deviations are acceptable: . . . A 1 1/2 inch gap when

the template above is placed across one or more welded seams,"

and applies to both the cylindrical liner and the dome liner.

This conflict between the G&H specification and attribute A.1.b

.of QI-031, Revision 0, is an NRC deviation (445/8516-D-41).

i

m.

Structural Steel

!

Status of CPRT Activity

$

Reinspection of the first random sample of 60 structural steel members

is approximately 25% complete.

Twenty-five valid deviations have been

identified. The second sample, which is related to safe shutdown

l

systems, has not yet been selected.- Documentation review procedures

!

have not been issued.

Status of NRC Inspection Activity

(1) Seven reinspections have been partially witnessed (welding

-

inspection is not complete), representing approximately 12% of

the first random sample. The following four ERC reinspections

were witnessed by the NRC inspector during this report period:

.

Verification Package No.

Equipment No.

Unit'No.

I-S-STEL-059

AFCO-MK-F180-1-RB

1-

I-S-STEL-007

liK-12

1

,

I-S-STEL-066

DCA 16019 MK-10

Common

I-S-STEL-010

AFC0-C70-3-SA

1-

I

(2) During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:-

[

I-S-STEL-059:

Numerous attributes _were rejected including bolt

hole coverage and edge distance, bolt size, and weld location..

'

-Paint removal was requested to allow for adequate surface

inspection of the weld

4

-

I-S-STEL-007: An extra bolt hole, not identified in the field

- '

performed alterations, was~noted.

Bolt contact was also. rejected.

~

,

. Verification Package No. I-S-STEL-007 involves the reinspection

i

i

of a sump screen in the Unit 1 reactor building. The screen is a

~

vendor assembled frame bolted to a -structural steel framework.

-

!

The screen is-included in_the ERC Population Description under

.

.

. -

. -

_

-.

-

.

29

" Vendor assembled frames and bents," but is not actually a

- structural member. The validity of the structural steel

population is being evaluated.

I-S-STEL-066:

Hilti bolt size and field installed associated

details (size of components) were rejected.

I-S-STEL-010:

Numerous attributes were rejected including bolt

spacing, configuration and edge distance, connection orientation

and location, limit of alterations, and location of member.

This

package is a monorail support member that is installed at an

angle of approximately 60 degrees between the monorail and the

support member. The drawings indicate an installation angle of

90 degrees.

Dispositions of the above findings are open items (445/8516-0-43

through 445/8516-0-46).

No NRC violations or deviations were identified.

n.

Concrete Placement

Status of CPRT Activity

Reinspection of the first random sample of 60 concrete placement

packages is approximately 98% complete.

Reinspection of the second

sample related to safe shutdown systems is approximately 40% complete.

Thirty-one deviations have been identified related primarily to

unfilled holes, voids, and debris in the concrete surface.

Of the

28 deviations which have been evaluated, 25 were identified as valid.

These are currently being reviewed for safety significance.

,

Documentation review procedures have not yet been issued.

Status of NRC Inspection Activity

'

(1) The NRC inspector has witnessed a total of 12 reinspections' to

date. The following three ERC reinspections were witnessed by

the NRC inspector during this report period:

Verification Package No.

Concrete Placement No.

Unit No.

I-S-CONC-079

IRCN-CPC-201-4822-007

2

I-S-CONC-076

IRCN-CPC-201-6885-010

2

I-S-CONC-069

IRCN-CPC-101-8805-001

1

(2) During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation _as.

,

potential deviations:

I-S-CONC-079: The locations and sizes of installed concrete

cast-in place Richmond inserts were out-of-tolerance.

Embedded

plates were installed too close to cast-in place inserts.

'

.

30

I-S-CONC-076:

The locations of installed concrete cast-in place

Richmond inserts were out-of-tolerance.

Dispositions of the above findings are open items (446/8513-0-12

and 446/8513-0-13).

No NRC violations or deviations were identified.

(3) The NRC inspector independently reinspected the following five

concrrte placements during this report period, representing

approximately 5% of the first and second samples:

Verification Package No.

Concrete Placement

Unit No.

I-S-CONC-017

IRCN-CPC-003-4860-023

Common

I-S-CONC-003

IRCN-CPC-002-5852-025

Common

I-S-CONC-016

IRCN-CPC-205-6810-010

2

I-S-CONC-015

IRCN-CPC-002-4790-040

Common

I-S-CONC-057

IRCN-CPC-002-E852-370

Common

(4) During the above independent reinspections, the NRC inspector

identified the following conditions:

I-S-CONC-015:

During review of the ERC inspection checklist

subsequent to the NRC inspection, the NRC inspector observed that

attribute 3.A of the checklist (surface inspection of walls, etc.)

was not signed off.

Therefore, it could not be established

whether or not ERC had performed the required reinspection of

this attribute.

Section 5.2.4 of ERC Procedure CPP-009,

Revision 1, requires the lead inspector (Level III) and the lead

discipline engineer to ". . . ensure that reinspection /

documentation review results are clear, accurate, and complete."

The incomplete checklist for Verification Package No. I-S-CONC-015

had been approved by both the lead inspector and the lead

discipline engineer.

This is an NRC deviation (445/8516-D-47).

I-S-CONC-057:

The NRC inspector identified dirt in the

construction joint and a void with a depth of at least 11/2

inches.

The void and dirt were not identified by the ERC

inspector.

Further review of the inspection checklist revealed

that the ERC inspector had entered "N/A" (not accessible) and

" coated" with respect to attribute 3.A.

Section 5.3.A of QI-043,

Revision 1, states with respect to concrete surface inspection,

" Inspect all accessible surfaces for honeycombing and voids.

(Inaccessible surfaces are those cast against earth, backfilled,

or coated)." The NRC inspector observed the concrete placement

associated with this verification package and found that it was

not coated on any surface and was accessible.

This is an NRC

deviation (445/8516-D-48).

.

31

o.

Small Bore Pipe Supports

Status of CPRT Activity

Reinspection of the first and second samples of small bore pipe

supports is approximately 97% complete.

A total of 67 valid deviations

have been identified related primarily to Hilti bolt embedment, hole

spacing and edge distance in base plates, and pipe clearances.

Documentation review is approximately 99% complete with 31 valid

deviations identified.

Status of NRC Inspection Activity

Six reinspections were previously witnessed by the NRC inspector.

There was no NRC inspection activity during this report period.

p.

Pipe Whip Restraints

Status of CPRT Activity

ERC has completed 28 reinspections of pipe whip restraints out of the

planned sample size of 110.

Nine valid ors have been identified.

Status of NRC Inspection Activity

(1) The NRC inspector has witnessed four ERC reinspections, to date,

of which the following occurred during this report period:

Verification Package No.

Support Identification Unit No.

I-S-PWRE-057

-M40-S1-0588

1

I-S-PWRE-053

FW-1-018-906-C67W

1

(2) During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-S-PWRE-053:

(a) Gaps existed between the plate and the top of

the washer (0.164 inches) and between the bottom of the washer

and the nut (0.140 inches) on the upper right anchor bolt of the

reactor side plate, (b) a gap of 0.122 inches existed between the

washer and the top of the nut on the middle left anchor bolt on

the reactor side plate, and (c) the capture plate on the reactor

side was 1/16 inch out of location from drawing requirements.

Dispositions of the above findings are an open item

(445/8516-0-49).

No NRC violations or deviations were identified.

.

.

-

sr

_

_ _ _ _ _

-

.

32

q.

Instrument Pipe / Tube Supports

Status of CPRT Activity

ERC has completed 46 out of the planned 102 reinspections of

instrument pipe / tube supports. Twenty-eight DRs have been validated

from a current total of 29 that have been reviewed by the population

engineer. Two hundred and sixty-three deviations have not yet been

reviewed for validity.

Status of NRC Inspection Activity

The NRC inspector has performed, to date, four independent inspections

of which the following occurred during this report period:

Verification Package No.

Instrument Tag No.

Unit No.

I-S-INSP-010

1-PI-4770

1

I-S-INSP-033

1-LT-462

1

While performing the above independent reinspections, it was observed

and noted with respect to support 33A, that the serrated grooves on

the spring nuts did not align with the channel clamping ridge as

required by attribute 4.5 of QI-055.

However, the ERC inspector

signed off the attribute as being acceptable. This is an NRC

deviation (445/8516-D-50).

r.

Category I Conduit Supports

Status of CPRT Activity

A total of 110 Category I conduit supports were randomly selected from

a population of 5500. The number of supports inspected, to date, is 71.

Physical reinspections are being accomplished using QI-053, Revision 0,

and are approximately 64% complete.

Nineteen deviations have been

identified and are being reviewed t,y ERC for validity and safety

significance. Two have been processed and were found to be not valid.

'

Status of NRC Inspection Activity

(1) The NRC inspector reviewed QI-053, Revision 0, and QI-054,

Revision 0, and witnessed the following three reinspections

during this report period:

Verification Package No.

Equipment No.

Unit No.

I-S-COSP-046

C03609956-04

1

I-S-COSP-073

C-140-06419-01

1

I-S-COSP-071

C-14W-13102-05

1

(2) During the reinspections, ERC identified the following conditions

to the NRC inspector as subject to evaluation as potential

deviations:

_

,, s

,

33

I-S-COSP-046:

A 3/8-inch Hilti, on south end, had a 1/8-inch gap

'

between unistrut and wall.

I-S-COSP-071:

(a) Plate size was incorrect, and (b) a nut was

. bottomed out on Hilti bolt threads.

Dispositions of the above findings are open items (445/8516-0-51

and 445/8516-0-52).

No NRC violations or deviations were identified.

s.

Documentation Review of Fill and Backfill Placement

Status of CPRT Activity

Documentation review of the sample of 120 fill and backfill placements

is approximately 92% complete.

A total of 254 deviations have been

identified and are being evaluated for validity.

No physical

reinspections are planned.

Status of NRC Inspection Activity

The NRC inspector reviewed Revision 3 of QI-057.

No independent

document reviews have yet been performed.

No NRC violations or deviations were identified.

t.

Field Fabricated Tanks

Status of CPRT Activity

The population consists of eight tanks which were fabricated on site,

four of which are inaccessible.

Reinspection by ERC is in process

and is approximately 60% complete.

A total of 54 deviations have

been identified which are being reviewed by ERC for validity and

safety significance.

a

Status of NRC Inspection Activity

(1) The NRC inspector reviewed QI-041 for accuracy and adequacy, and

witnessed 10% of the ERC reinspection effort on the following

four tanks:

l

Verification Package No.

Unit No.

I-M-FFTA-01

Common (1)

l

!

I-M-FFTA-02

Common (1)

I-M-FFTA-03

Common (1)

I-M-FFTA-04

Common (1)

,

1

l

. . .

.

, . . -

34

(2) During the above reinspections, ERC identified the following

conditions to the NRC inspector as subject to evaluation as

potential deviations:

I-M-FFTA-01:

(a) A stitch weld was used where a full length

weld is required, (b) weld size was indeterminate on lap joints,

(c) a 3/8-inch fillet weld was specified on 1/4-inch thick

material, (d) Bill of Material item 6 to 11 fillet weld had an

'

insufficient weld throat size,.(e) seismic restralit gussets had

!

insufficient weld throat size, and (f) anchor bolt ring chairs

had undersize welds.

I-M-FFTA-02:

(a) A stitch weld was used where a full length weld

,

'

is required, (b) weld size was indeterminate on lap joints,

(c) undersize fillet weld was present at nozzle locations No. 1

and 15, (d) Bill of Material item 11 to tank shell had an

undersize fillet weld, (d) Bill of Material item 11 to item 6

fillet weld had an undersize throat, (f)-fillet welding on the

davit bracket was undersize, and (g) anchor bolt ring chairs had

undersize welds.

Dispositions of the above findings are open items (445/8516-0-53

and 445/8516-0-54).

No NRC violations or deviations were identified.

,

(3) Due to the small population, the NRC inspector performed

independent inspections of approximately 15% of the defined

{

attributes on the four accessible tanks.

This effort revealed

that reinspections were performed in accordance with the

1

requirements of QI-041.

No NRC violations or deviations were identified.

8.

Exit Interview

An exit interview was conducted on Dec0nber 4,1985, with the applicant

representatives denoted in paragraph 1 of this appendix. During this

interview, the NRC inspectors summarized the scope and findings of the

inspection.

The applicant acknowledged the findings.

1

1

1

(

f

i

i

l

,

-