Text

. _ _

e January 21, 1998 Mr. Harold B. Ray Executive Vice President Southem California Edison Company San Onofre Nuclear Generating Station P. O. Box 128 San Clements ?9lifornia 92674-0128

[

SUBJECT:

MEQUEST FOR ADDITIONAL INFORMATION - PROPOSED STEAM GENERATOR SLEEVING TECHNICAL SPECIFICATION AMENDMENT FOR SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 (TAC NOS. M99641 AND M99642)

Dear Mr. Ray:

3 Enclosed is a request for additional information (RAl) related to Southern California Edison's September 16,1997, letter requesting NRC approval to use ASEA Brown Boveri/ Combustion Engineering !eak tight sleeving as an alternative steam generator tube repair to plugging.

Please provide your response to the RAI within 45 days from the date of this letter, so that our review of this issue can be completed before the next refueling outage. Please call me at (301) 415-3062 with any questions.

Sincerely, Original Signed By Mel B. Fields, Project Manager Project Directorate IV-2 Division of Reactor Projects Ill/IV Office of Nuclear Reactor Regulation Docket Nos. 50-361 DISTRIBUTION:

and 50-362 Docket File PUBLIC

Enclosure:

Request for Additional PDIV-2 R/F

[}

Information EAdensam WBateman cc w/ encl: See next page MFields EPeyton i

s OGC ACRS 9001300021 980121 KPerkins, RIV WCFO DR ADOCK 0500 1

p TPGwynn, RIV TSullivan DOCUMENT NAME: Sleeve /q.Itr To receive a copy of this document, indicate in the bar: "C" = Copy without enclosures "E" = Copy with enclosures "N" = No copy 0FFICE PDIV-2/PM PDIV-2/LA NAME MFdids EPeyt6rP P 7

DATE 01/2//98 Ol Gl/98 01/ /98 01/ /98 01/ /98 0FFICIAL RECORD C0t

,N

Mr. Harold B. Ray January 21, 1998 cc w/enci:

Mr. R. W. Krieger, Vice President Rei,ldent inspector / San Onofre NPS Southem Califomia Edison Company c/o U.S. Nuclear Regulatory Commission San Onofre Nuclear Generating Station Post Office Box 4329 P. O. Box 128 San Clemente, Cr.lifomia 92674 San Clemente, Califomia 92674-0128 Mayor Chairman, Board of Supervisors Chy of San Clemente County of San Dego 100 Avenida Presidio 1600 Pacific Highway, Room 335.

San Ciomente, Califomis 92672 San Diego, Calfomia 92101 Mr. Dwight E. Nunn, Vee President Alan R. Watts, F.sq.

Southem Califomia Edison Company Woodruff, Sprodlin & Smart San Onofre Nuclear Generating Station 701 S. Parker St. No. 7000 P.O. Box 128 Orange, Califomia 92668-4702 San Clemente, Califomia 92674-0128 Mr. Sherwin Harris Resource Project Manager Public Utilities Department City of Riverside 3900 Main Street -

Riverside, Califomia 92522 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavilion 611 Ryan Plaza Drive, Suite 400 Artington, Texas 76011-8064 Mr. Terry Winter Manager, Power Operations San Diego Gas & Electric Company P.O. Box 1831 San Diego, Califomia 92112-4150 Mr. Steve Hsu Radiologic Heahh Branch

' State Department of Health Services Post Office Box 942732 Sacramento,Califomia 94234

REQUEST FOR ADDITIONAL INFORMATION PROPOSED STEAM GENERATOR SLEEVING TECHNICAL SPECIFICATION AMENDMENT SAN ONOFRE NUCLEAR GENERATING STATION. UNITS 2 AND 3

~

DOCKET NOS. 50 361 AND 50-382 The following request for additional information is in reference to Southem Califomia Edison's September 16,1997, letter requesting changes to the San Onofre Nuclear Generating Station, Units 2 and 3 Technical Specifications (TS). The September 16 letter also included ABB/CE Topical Report CEN-630-P and Report No. 96-OSW-003-P.

4

- 1.

The proposed TS limit for the imperfection depth at or beyond which the steam generator tube shall be removed from service or repaired is equal to 44% of the nominal tube wall thickness. This could be less conservative from the sleeve plugging limit discussed on page 8-9 of Topical Report CEN 630 P, once allowance for NDE uncertainty (typically 10%) and flaw growth (typical!/10%) are taken into account.

Please justify the use of 44% in light of the information contained in Topical Report CEN 630-P.

2.

Topical Report CEN-030-P diacussed a VT assocated with the wald preparation process, but states that this VT is optional. The staff believes that this inspection would confirm the adequacy of the brushing step to prevent weld failures due to oxide

- inclusions. Please clarify if this VT will be performed in accordance with the topical report, if a VT will not be performed, provide the technical justification (i.e., provide details that demonstrate the high degree of cleanliriess accepted in the flald).

4