NRC Staff Presentation - Public Meeting for Holtec TR Review-7-17-20
ML20198M440
Person / Time
Issue date: 07/17/2020
From: Ngola Otto
Licensing Processes Branch
To:
Holtec
Otto N, NRR/DORL/LLPB, 415-6695
References
Download: ML20198M440 (5)


Text

Staff Presentation on Holtec Topical Report (TR) Review Process and Schedule Public Meeting on TR for Allowance of Heat Load Patterns in HI-STORM 100 and HI-STORM FW Systems Ngola Otto Office of Nuclear Reactor Regulation July 17, 2020

Agenda 2

  • Holtec Topical Report
  • Modified Topical Report Review Process Guidance and Overview
  • Holtec Topical Report Review Schedule

Holtec Topical Report 3

  • Requesting approval for a heat load patterns methodology in the TR for Allowance of Heat Load Patterns in HI-STORM 100 and HI-STORM FW Systems.
  • Holtec intends to use the approved TR in future licensing actions (e.g. Certificates of Compliance amendments).

Modified TR Review Process Guidance & Overview 4

Guidance LIC-500, Topical Report Process Rev. 8 (ML19123A252).

Overview One year review schedule NRC accepts or rejects the TR - no opportunity to supplement NRC completes Draft Safety Evaluation (SE) and provides to the Applicant o

Documents Open Items (i.e., areas NRC is unable to make conclusion or find acceptable) o No Requests for Additional Information (RAIs) o Applicant provides responses to Open Items If the Applicants responses are acceptable - NRC completes Final SE If Applicants responses are not acceptable o

Open Items requiring minimal information to address; RAIs or conference call and documentation

Holtec TR Review Schedule 5

Current Proposed Review Schedule (1 Year)

Completed Actions o

Pre-submittal meeting: November 21, 2019 (ML19330E353) o Submittal: March 19, 2020 (ML20101N174) o Acceptance: May 22, 2020 (ML20141L621)

Milestones o

Public Meeting: July 17, 2020 (ML20181A436) o Audit for Understanding: September 4, 2020 o

Technical Audit: November 6, 2020 o

Draft SE with Open Items: December 31, 2020 o

Final SE: March 31, 2021 o

Office of General Counsel Congressional Review Act (CRA) Review:

After completion of Final SE o

Receive -A-Approved version of TR: 60 days after Final SE