Staff Presentation on Holtec Topical Report (TR) Review Process and Schedule Public Meeting on TR for Allowance of Heat Load Patterns in HI-STORM 100 and HI-STORM FW Systems Ngola Otto Office of Nuclear Reactor Regulation July 17, 2020

Agenda

  • Holtec Topical Report
  • Modified Topical Report Review Process Guidance and Overview
  • Holtec Topical Report Review Schedule 2

Holtec Topical Report

  • Requesting approval for a heat load patterns methodology in the TR for Allowance of Heat Load Patterns in HI-STORM 100 and HI-STORM FW Systems.
  • Holtec intends to use the approved TR in future licensing actions (e.g. Certificates of Compliance amendments).

3

Modified TR Review Process Guidance & Overview Guidance LIC-500, Topical Report Process Rev. 8 (ML19123A252).

Overview

  • One year review schedule
  • NRC accepts or rejects the TR - no opportunity to supplement
  • NRC completes Draft Safety Evaluation (SE) and provides to the Applicant o Documents Open Items (i.e., areas NRC is unable to make conclusion or find acceptable) o No Requests for Additional Information (RAIs) o Applicant provides responses to Open Items
  • If the Applicants responses are acceptable - NRC completes Final SE
  • If Applicants responses are not acceptable o Open Items requiring minimal information to address; RAIs or conference call and documentation 4

Holtec TR Review Schedule Current Proposed Review Schedule (1 Year)

  • Milestones o Public Meeting: July 17, 2020 (ML20181A436) o Audit for Understanding: September 4, 2020 o Technical Audit: November 6, 2020 o Draft SE with Open Items: December 31, 2020 o Final SE: March 31, 2021 o Office of General Counsel Congressional Review Act (CRA) Review:

After completion of Final SE o Receive -A- Approved version of TR: 60 days after Final SE 5