Staff Presentation on Holtec Topical Report (TR) Review Process and Schedule Public Meeting on TR for Allowance of Heat Load Patterns in HI-STORM 100 and HI-STORM FW Systems Ngola Otto Office of Nuclear Reactor Regulation July 17, 2020
Agenda 2
- Holtec Topical Report
- Modified Topical Report Review Process Guidance and Overview
- Holtec Topical Report Review Schedule
Holtec Topical Report 3
- Requesting approval for a heat load patterns methodology in the TR for Allowance of Heat Load Patterns in HI-STORM 100 and HI-STORM FW Systems.
- Holtec intends to use the approved TR in future licensing actions (e.g. Certificates of Compliance amendments).
Modified TR Review Process Guidance & Overview 4
Guidance LIC-500, Topical Report Process Rev. 8 (ML19123A252).
Overview One year review schedule NRC accepts or rejects the TR - no opportunity to supplement NRC completes Draft Safety Evaluation (SE) and provides to the Applicant o
Documents Open Items (i.e., areas NRC is unable to make conclusion or find acceptable) o No Requests for Additional Information (RAIs) o Applicant provides responses to Open Items If the Applicants responses are acceptable - NRC completes Final SE If Applicants responses are not acceptable o
Open Items requiring minimal information to address; RAIs or conference call and documentation
Holtec TR Review Schedule 5
Current Proposed Review Schedule (1 Year)
Completed Actions o
Pre-submittal meeting: November 21, 2019 (ML19330E353) o Submittal: March 19, 2020 (ML20101N174) o Acceptance: May 22, 2020 (ML20141L621)
Milestones o
Public Meeting: July 17, 2020 (ML20181A436) o Audit for Understanding: September 4, 2020 o
Technical Audit: November 6, 2020 o
Draft SE with Open Items: December 31, 2020 o
Final SE: March 31, 2021 o
Office of General Counsel Congressional Review Act (CRA) Review:
After completion of Final SE o
Receive -A-Approved version of TR: 60 days after Final SE