Docket No. 50-373
Docket No. 50-374
Commonwealth Edison Company
ATTN:
Mr. Cordell Reed
Vice President
Post Office Box 767
Chicago, IL 60690
Gentlemen:
This refers to the routine safety inspection conducted by Z. Falevits of this
office on May 6-8, 1986, of activities at LaSalle County Nuclear Station,
Units 1 and 2 authorized by NRC Facility Operating Licenses No. NPF-11 and
No NPF-18 and to the discussion of our findings with Mr. R. D. Bishop at the
conclusion of the inspection.
The enclosed copy of our inspection report identifies areas examined during
the inspection. Within these areas, the inspection consisted of a selective
examination of procedures and representative records, observations, and
interviews with personnel
During this inspection, certain of your activities appeared to be in vi'olation
of NRC reouirements, as described in the enclosed Notice.
The inspection
showed that action had been taken to correct the identified violation and
to prevent recurrence. Our understanding of your corrective actions are
described in Paragraph 2c of the enclosed inspection report.
Consequently,
no reply to the violation is required and we have no further questions
regarding this matter at this time.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of
this letter, the enclosures, and your response to this letter will be placed
in the NRC Public Document Room.
The responses directed by this letter and the accompanying Notice are not
subject to the clearance procedures of the Office of Management and Budget
as required by the Paperwork Reduction Act of 1980, PL 96-511.
S606040016 860528
ADOCK 05000373
G
/[0/,
I
i
.
Commonwealth Edison Company
2
MAY 281986
We will gladly discuss any questions you have concerning this inspection.
Sincerely,
,
j ;* 7 3 by U.'U '* D IE00
,
J. J. Harrison, Chief
Engineering Branch
Enclosures:
1.
2.
Inspection Reports
No. 50-373/86019(DRS);
No. 50-374/86018(DRS)
cc w/ enclosures:
D. L. Farrar, Director
of Nuclear Licensing
G. J. Diederich, Plant
Manager
DCS/RSB (RIDS)
Licensing Fee Management Branch
Resident Inspector, RIII
Phyllis Dunton, Attorney
General's Office, Environmental
Control Division
%td
b'/
a
Falevits/kst
Maffett
Ha rison
c.g
s/n/et
<[//(W
6 z6