Informs of Sample Plan Selected for Use During Refueling Outage RFO6 Scheduled to Begin in May 1998
ML20198J387
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 01/06/1998
From: Conway J
NIAGARA MOHAWK POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NMP2L-1743, NUDOCS 9801140117
Download: ML20198J387 (2)


Text

_.

NIAGARA MOHAWK-G E N E R ATIO N NME WLE POWT NUCLEAR STAflON/ LAKE FtOAD. P.O. 00X 63. LYCOMING. NEW YORK 13093/ TELEPHONE (315) 349-4213 BUSINESS GROUP

"('5)3*?*5 JOHN T. CoNWAY

$d** %g January 6,1998 NMP2L 1743 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 RE:

Nine Mile Point Unit 2 Docket No. 50-410 NPF-69

Subject:

Technical Specification 3/4.7.5, Snubbers Gentlemen:

Nine Mile Point Unit 2 (NMP2) Technical Specification (TS) Surveillance Requirement 4.7.5.e, Functional Tests, requires that each type of snubber be tested every 18 months using one of the sample plans described in the TSs. The sample plan is required to be selected before the test period and cannot be changed during the test period. Also, TS 4.7.5.e requires that the NRC Regional Administrator be notified in writing of the sample plan selected before the test period or that the sample plan used in the previous test period be implemented. The purpose of this letter is to infonn you of the sample plan selected for use during NMP2's refueling outage RFO6 scheduled to begin in May 1998.

As discussed in our letter dated August 23,1996, our previous sample plan (i.e., our sample plan for RFO5) was based on a snubber populatian made up entirely of mechanical srMbers.

The "37 Plan" per TS 4.7.5.e.2 was selected resulting in functional testing of 37 snubbers.

During RTO5, all 21 of the mechanical snubbers on the Reactor Recirculation System were replaced with hydraulic snubbers.

>l O

,,Q 1

9001140117 990106 "

PDR ADOCK 05000410' P

PDR

ma ll 1.1! ll!.Il.I 1.111.1.1

4 Page 2, During refueling outage RFO6, the remaining mechanical snubbcrs will continue to be functionally tested using the "37 Plan" per TS 4.7.5.e.2. The Reactor Recirculation System hydraulic snubbers will be tested using the "10% Plan" per TS 4.7.5.e.l.

Very truly yours, I

John T. Conway Vice President Nuclear Engineering JTC/JMT/cmk xc: