ML20198H791

From kanterella
Jump to navigation Jump to search
Insp Repts 50-327/97-13 & 50-328/97-13 on 970725-0904. Violations Noted.Major Areas Inspected:Insp Scope,Event Synopsis & Observations & Findings
ML20198H791
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 09/11/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20198H783 List:
References
50-327-97-13, 50-328-97-13, NUDOCS 9709220190
Download: ML20198H791 (12)


See also: IR 05000327/1997013

Text

.

,

U.S. NUCLEAR REGULATORY COMMISSION

REGION 11

Docket Nos:

50-327. 50 328

License Nos:

DPR-77, DPR-79

Report Nos:

50-327/97-13, 50-328/97-13

Licensee:

Tennessee Valley Authority (TVA)

Facility:

Sequoyah Nuclear Plant, Units 1 and 2

Location:

Sequoyah Access Road

Hamilton County, TN 37379

Dates:

July 25 through September 4.1997

Inspectors:

M. Shannon. Senior Resident Inspector

D. Seymour, Resident Inspector

D. Starkey. Resident Inspector

Approved by:

M. Lesser. Chief

Projects Branch 6

Division of Reactor Projects

Enclosure

9709220190 970911

PDR

ADOCK 05000327

O

PDR

_ _ _ _ _ _ _ _ _ _ -

l

_ _ _ - _ _

.

.

,

EXECUTIVE SUMMARY

Sequoyah Nuclear Plant, Units 1 and 2

NRC Inspection Report 50-327/97-13, 50-328/97-13

This special inspection was conducted to review the events associated with the

misalignment of the #5 vital battery (spare) to the #4 vital battery board on

July 24,1997.

During the safety system raalignment, a senior reactor

operator (SRO) and an assistant unit operator (AUO) failed to properly perform

procedural steps which resulted in not properly aligning the battery to the

vital battery board. This resulted in the failure to meet the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />

technical specification (TS) action statement for returning the battery bank

to operable status. The battery bank is common to both units and was

inoperable for approximately 30.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

An apparent violation was identified for failure to meet the limiting

condition for operation (LCO) action statement of TS 3.8.2.3.b. in that

the DC vital battery channel was inoperable for approximately 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />

which exceeded the TS LC0 action statement for restoring the inoperable

battery within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in Hot Standby within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> (EEI 50-327,

328/97-13-03).

An apparent violation of TS 6.8.1 was identified with two examples of

not following procedures in that an operator (SRO) failed to close the

correct circuit breaker, and did not stop an evolution when unexpected

conditions were encountered (EEI 50-327, 328/97-13-01).

An apparent violation of 10 CFR 50 Appendix B Criterion V was identified

for the failure to ensure independent verification as appropriate to

circumstances while realigning the spare #5 vital battery to the #4

vital battery board.

Additional examples were identified by the

inspectors of failure to follow and/or inadequate procedures regarding

AU0 rounds (EEI 50-327, 328/97-13-02).

An apparent violation of 10 CFR 50 Appendix B Criterion XVI was

identified for failure to promptly identify an adverse condition (missed

out-of-tolerance battery voltage reading) (EEI 50-327. 328/97-13-04).

-

- _ _ _ - _ - _ _ _ _ _ - _ _ _ _ _

.

2

Control room operators initially performing the battery realignment, and

subsequent oncoming crews, did not identify the lack of an expected main

control room alarm,

in addition, the procedure did not highlight that a

main control board alarm was expected when realigning the spare battery.

Poor AU0 rounds practices vere identified, based on the length of time

taken to perform AUO rounds.

Based on the examples identified in this

inspection, and previous examples, the inspectors concluded that AUO

rounds and procedures are a significant weakness.

Poor rounds taking practices that contributed to the duration of event

were not addressed by the licensee, which is considered a weakness in

the event investigation.

A negative observation was noted when operators logged entry into the

wrong TS action statement when realigning the vital batteries on

July 24.

l

'

- . _ _ _ _ _ _

.

,

Reoort Details

I,

Inoperable Vital 125 Volt DC Battery

A.

Insoection Scone (71707)

The inspectors reviewed the events related to the failure of an SRO to

properly realign the spare #5 vital battery to the #4 vital battery

board while hanging a clearance on the #4125 volt DC vital battery.

B.

Event Synoosis

At 6:13 a.m., on July 24,1997, the #4125 volt DC vital battery was

removed from service in order to perform maintenance on the battery.

At

11:00 a.m. , on July 25, 1997, a training instructor with operator

trainees discovered that the supply breaker (breaker #107) from the

spare battery to the #4 vital DC board was open. At 11:33 a.m., breaker

  1. 107 was closed and at 12:36 p.m., following surveillance activities,

the spare battery and the #4 vital DC board were declared operable.

The

licensee initially briefed the inspectors of the adverse system lineup

at approximately 11:50 a.m. , on July 25.

C,

Observations and Findinas

During the review, the-inspectors determined that an AVO initially

requested assistance from an SR0 in the use of procedure 0-S0 250-1, 125

Volt DC Vital-Power System, to realign the spare #5 vital battery to the

  1. 4 vital battery board and to remove the #4 vital battery for

=

maintenance. The licensee-determined that SR0 assistance was requested

~by the AU0 due to uncertainty in performing the-procedure. Step 8.4.8

of procedure 0-S0-250-1 required the operator to close the spare battery

feeder breaker (#107) from vital battery #5 which would provide the

vital battery supply to vital ~ battery DC board #4 while the normal #4

vital battery _was undergoing preventive maintenance.

The operator

failed to close the correct breaker and in fact checked closed a

different breaker identified as #107. This is identified as one example

of an apparent violation for failure to follow procedure (EEI 50-

327,328/97-13-01).

The procedure step specifically stated " Place Distribution Panel A-S or

B-S breaker in ON position to align feed to desired Vital Battery Board.

(N/A others) (Located on wall outside Vital Battery Board Rooms. AB el

734')." A short table followed this step which contained the heading,

" Desired Battery BD Feeder From Distr Panel." The table included the

- _ _ _ _ _ - _ - - -

2

step "125V dc Vital Battery Board IV, Feeder - BKR 107." This step was

signed off as having been completed on the morning of July 24.

The

inspectors considered the procedural step to be confusing in that it did

not consistently identify the exact panel nomenclature.

Later in the

procedure, step 8.4.24 required the operator to open the normal supply

breaker from the #4 vital battery to the #4 vital battery board. This

breaker is also identified as BKR 107.

The step does not uniquely

identify the breaker with the #4 vital battery and vital board, since it

is generically written to apply to 1 of 4 DC channels and 1 of 4 circuit

breakers identified as BKR 107.

During a subsequent review, the licensee noted that five vital board 125

volt DC breakers on different boards were labeled as #107.

The breakers

were located in adjacent vital battery board rooms and the licensee's

investigation noted that the operator had gone to the wrong room and had

verified the wrong breaker as " closed" on the morning of July 24.

Although 0-50-250-1 contained enough information to correctly align the

batteries, and the panels and breakers were sufficiently labeled, the

.

inspectors concluded that the procedure did not uniquely and

consistently identify which specific breaker at which specific panel was

to be operated.

This, coupled with several breakers with the same

nomenclature, provided a confusing and unclear procedure.

This is also

supported by the fact that the AU0 requested assistance from an SR0 in

the performance of the procedure.

A.lthough the operator was required to " Place Distribution Panel A-S or

B-S breaker in ON position to align feed to desired Vital Battery Board"

(a key step in the alignment of the #5 vital battery to the #4 vital

battery board), the SRO went to the wrong distribution panel and found a

different BKR 107 already closed (the SR0 was looking at the normal

supply breaker for the #4 vital battery to the #4 vital battery board,

which is also labeled BKR 107).

The SR0 failed to notify the control

room of the potential status control issue and continued on with the

evolution.

The licensee determined that the SR0 did question the

unexpected breaker status, but then inappropriately verified that the

similarly labeled breakers in the other vital battery board rooms were

also closed.

In addition, the licensee's investigation revealed that after the SRO

initially verified that the #107 breaker (normal supply) was closed,

several steps later in the procedure, he opened the same breaker,

removing the #4 Vital Battery from the #4 Vital Battery Board.

,

__

-_

_ - - _ _

_

'

,

,

3

This failure to evaluate an unexpected as-found condition was similar to

an event noted in Inspection Report 97 03, where an operator found a

valve in an unexpected position and did not notify the control room,

resulting in the spent fuel pool cooling system being misaligned and the

spent fuel pool cooling pump being dead headed for about two hours.

Site Standard Practice (SSP) 2,51. Rules of Procedure Use, Section 3.3,G

and Section 3.3.H requires the operator to "Stop the procedure if an

unexpected response is obtained.

Notify the SOS /SR0 designee or

Cognizant Supervisor, and the SOS /ASOS or Cognizant Supervisor will

evaluate the situation and document the review and approval to continue

the procedure, if applicable, in a note."

In this case, when the SRO

encountered the unexpected breaker position, he did not stop the

manipulations in the procedure and did not inform the 50S/SR0 designee

or a cognizant cupervisor of the deficiency. Therefore the SOS /SR0

designee or cognizant supervisor did not have the opportunity to

evaluate the as-found condition and to authorize resumption of the

manipulations.

The licensee determined that the SRO considered himself

the cognizant supervisor. The failure to adhere to SSP-2.51, when

unexpected conditions were encountered, is considered to be a second

example of an apparent violation for failure to follow procedures (EEI

50-327, 328/97-13 01).

During the subsequent review, the licensee and the inspector noted that

Step 8.4.8 of procedure 0-S0-250-1 did not require independent

verification, although independent verification is required by Site

Standard Practice,-(SSP),12.6, Equipment Status Verification and

Checking Program, Revision 9, when realigning safety related systems,

Failure to ensure independent verification steps were appropriately

prescribed as delineated by SSP-12.6 is considered to be an apparent

violation (EEI 50-327, 328/97-13-02), and contributed to the licensee's

failure to identify the misaligned spare #5 vital battery.

The licensee noted an additional 0-50-250-1 procedure weakness. The

procedure did not identify or contain a note to the operators alerting

them that, when the #5 battery was placed in service, the main control

board alarm "#5 Battery In Service" would alarm / actuate. The lack of

this. alarm to be in the alarmed state should have alerted the control

room operators that the spare battery was not properly aligned to the

vital DC board, This procedural weakness contributed to the operating

crew's failure to identify the misaligned spare battery.

In addition,

the-inspectors concluded that the control room operators initially

performing the battery realignment, and subsequent cncoming crews, did

i

'

.

4

s

4

not question the lack of an expected main control room alarm and thus

missed opportunities to identify the inoperability.

The licensee's review also noted that, on July 24, during the initial

system alignment, the unit SR0 entered an inappropriate TS action

statement, when he logged that the plant was in TS 3.8.2.1.

This TS

action provided an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> LCO action statement.

However, the unit w6s

actually in TS 3.8.2.3 which provided only a 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> action statement.

The procedure was completed, albeit incorrectly, within the 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

The inspectors noted, once the breaker misalignment was discovered on

July 25, the correct action statement (TS 3.8.2,3) was entered and met.

The licensee and the inspectors determined that, with the distribution

panel breaker in the wrong position, the licensee had not been in

compliance with Technical Specification (TS) 3.8.2.3.b DC Distribution,

which requires that each of the four DC vital battery channels be

operable.

The TS further requires that a deenergized vital battery bank

be restored to an operable condition and in an energized status within

2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least hot standby within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

Following the misalignment of the DC system on the morning of July 24,

the #4 DC vital battery was inoperable from 6:13 a.m., on July 24 until

12:36 p.m. , on July 25, 1997, an approximately 30.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> time frame,

The failure to meet the requirements of TS 3.8.2.3.b is considereu to be

an apparent violation (EEI 50-327,328/97-13-03).

The licensee noted a contributing cause for this event was an

insufficient unique identification nomenclature for the components in

the 125 VDC System.

The licensee also noted that the plant 120 VAC

Vital boards. 250 VDC non-Vital boards, and 125 VDC Vital boards, had

examples where components lacked unique identifiers.

At the end of the

inspection period, the licensee identified that approximately 749 plant

breakers lacked unique identification tags.

The inspectors determined

that components can be adequately identified using the component

nomenclature in conjunction with the specific distribution board.

However, coupled with an unclear procedure and poor self-checking

techniques, the correct component to be operated was not identified.

The licensee's review documented in PER No. SQ971762PER, noted a similar

event documented by LER 50-327/95 08.

In this PER, the licensee stated

that corrective actions from the previous event would not have prevented

the July 24, 1997 event. The inspectors noted that LER 95-08 documented

a reactor trip as a result of an operator opening a wrong breaker. The

operator had opened breaker #48 on the wrong vital 120 VAC board. All

l

.'

,

V

5

four 120 VAC vital boards had breakers labeled #48. The cause of the

event was attributed to inadequate self-checking.

The inspectors

concluded that the June 1995 event was similar to the July 24, 1997

event. The lack of unique equipment identifiers was not recognized as

an issue in the earlier event.

Subsequently, the licensee identified various corrective actions, which

included:

revising the operating procedure to require independent

verification, hanging caution tags on the five #107 breakers to ensure

proper identification, plans to relabel all -125, and 250 volt DC and 120

volt AC boards, developing jcb performance measures for sparing out the

125 volt DC batteries, revising the battery procedure to identify the #5

battery in-service alarm, including the appropriate TS action statt. ment

in the battery procedure, reviewing other operations, maintenance and-

chemistry procedures to ensure proper independent verifications have

been identified, and taking disciplinary actions for the two operators.

During a subsequent review of the July 24 event, the inspectors were

concerned with the apparent failure to identify the misaligned breaker

during AVO tours / rounds of the control building area. The AVO rounds

include voltage readings on the #5 vital battery.

The AVO tour that was

in question was performed approximately 19 hours2.199074e-4 days <br />0.00528 hours <br />3.141534e-5 weeks <br />7.2295e-6 months <br /> after the #5 vital

battery was disconnected. The #5 vital battery voltage data point was

logged as normal, although the battery voltage was most likely below the

administrative limit of 132 VDC listed in the AU0 rounds.

Around 11:00

a.m., on July 25, the #5 vital battery voltage was found to be at 128

VDC due to not being on float charge (TS required minimum of 129 volts.

AUO roundsheet administrative minimum of 132 volts), The licensee

subsequently performed a test on the spare #5 vital battery which

confirmed that at 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> into the test the battery voltage had

dropped to 131.5 volts.

Although the AVO rounds would not have

prevented the event, they should have identified the adverse condition

many hcurs sooner (12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />). The failure to promptly identify an

adverse condition (the out of-tolerance battery voltage reading) is

e

considered to be an apparent violatior (EEI 50-327, 328/97-13-04).

Initial NRC review of the applicable AU0 tour noted that 52 items were

-signed off in the logs on various levels of the control building in

less than 7 minutes. The inspectors noted that many line items had

multiple items that had to be checked to determine acceptable / normal

operation and that only a cursory review of the area and equipment could

be made based on the documented AUO roundsheet.

It also appeared to the

inspectors that the duration of the AUO tour would not be reasonable

- - __ _ ____ ____ __

.

6

based on the number of activities performed. This is considered to be a

poor rounds taking practice.

The licensee had not addressed this area

which is considered to be a weakness in their event investigation.

The inspectors conducted a more detailed review of a section of the AUO

control building logs, and noted the following discrepancies:

The AUO control building rounds for the mid-watch on July 25 noted

three of four battery room temperatures above 80 degrees (86, 82

and 82 degrees) with no further comments. Although the minimum

and maximum tolerances were listed as 60 and 104 degrees, the

special instructions for this itea stated, "If temperature cannot

be maintained within the nominal range (70-80 degrees), then

notify Unit Supervisor and initiate corrective action as

appropriate." There was no evidence that the unit supervisor had

been notified or of any corrective actions that were implemented.

AUO control building rounds item #41 required the operator to

verify the #5 battery voltage between 132-149 volts, however, the

maximum acceptable voltage per the system operating procedure with

the #5 battery tied to one of the vital DC boards was 140 volts.

The unique equipment identifiers listed for the 480 volt Reactor

MOV Boards were inaccurate (for example, 1-BDC-201-GG-A versus

actual 1-BCTD-201-GG).

The inspectors consider the above examples of failure to follow

procedures and inadequate procedures to be additional examples of

apparent violation EEI 50-327,328/97-13-02.

Recent NRC inspection reports have documented problems with AUO rounds

and procedures.

IR 327,328/97-01 documented a weakness for not

obtaining routine log readings during EDG operation and for not actively

monitoring the EDG, although the EDG was being operated at 110% load and

was in alarm for high exhaust differential temperature and high governor

actuator differential.

IR 327,328/96-17 identified a weakness in that

neither operations nor engineering identified that the main steam lines

and main steam drain lines were vibrating excessively and the main steam

drain line supports were broken.

IR 327,328/96-13 identified a weakness

in that the licensee failed to identify the malfunctioning steam dump

drain tank level switch, causing the steam dump lines to not drain

properly.

The operator rounds sheet lacked adequate guidance regarding

the steam dump drain tank level controls.

I

.

.

'

,

7

'

In addition, that IR identified an additional weakness in that the AU0s

failed to identify the damaged piping supports following the reactor

trip (8.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> later), although required to monitor the steam dump

valves once per shift, in addition to normal roving tours of the

building.

Finally, a lack of clear guidance in operator rounds

regarding EDG starting air pressure was observed in

IR 327,328/96-09.

The licensee recently implemented the use of electronic hand held logs

for the AU0s.

However, based on the above examples AU0 rounds and

procedures are considered to be a significant weakness.

D.

Conclusions

An apparent violation was identified for failure to meet the required

action statement of TS 3.8.2.3 b in that the DC vital battery channel

was inoperable for approximately 30.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> which exceeded the TS LC0

action statement for restoring the inoperable battery within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or

be in Hot Standby within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> (EEI 50-327,328/97-13-03),

An apparent violation was identified with two examples of not following

procedures in that an operator (SRO) failed to close the correct circuit

breaker, and did not stop an evolution when unexpected conditions were

encountered (EEI 50-327,328/97-13-01).

An apparent violation was identified for the failure to prescribe

independent verification while realigning the spare #5 vital battery to

the #4 vital battery board. Additional examples were identified by the

inspectors of failure to follow and/or inadequate procedures regarding

AU0 rounds (EEI 50-327, 328/97-13-02)

An apparent violation was identified for failure to promptly identify an

adverse condition, related to a missed out-of-tolerance reading for the

  1. 5 vital battery (EEI 50-327, 328/97-13-04).

Control room operators initially performing the battery realignment, and

subsequent oncoming crews, did not question the lack of an expected main

control room alarm and thus missed opportunities to identify the

condition.

In addition, the procedure did not highlight that a main

control board alarm was expected when realigning the spare battery.

,. .

..

.

.

_

'

.

.

8

Poor _ AVO rounds taking practices were identified, based on the length of

time taken to-perform AVO watchstanding duties.

Based on the examples

identified in this inspection and previous examples, the inspectors

concluded that AUG rounds and, procedures are a sigriificant weakness.

The licensee did not address poor rounds taking practices during their

event investigation which is a weakness in the licensee's event

investigation.

A negative observation was noted when operators logged entry into the

wrong TS action statement when realigning the vital batteries on

July 24, 1997,

II. Exit Meeting Summary

The inspectors presented the inspection =results to members of licensee

management at the conclusion of the inspection on September 4,1997.

The licensee acknowledged the findings presented.

The inspectors asked the licensee whether any materials would be

considered proprietary.

No proprietary information was identified.

PARTIAL LIST OF PERSONS CONTACTED

Licensee

  • Bajestani, M., Site Vice President
  • Butterworth H , Operations Manager
  • Koehl, D., Assistant Plant Manager

i

  • Reynolds, J. , Operations Superintendent
  • Salas, P., Manager of Licensing and Industry Affairs

EC

  • Lesser: M.,-Chief. Division of Reactor Projects Branch 6

Seymour, D., Resident Inspector

  • Shannon, M., Senior Resident Inspector
  • Starkey, D., Resident Inspector
  • Attended exit interview

..

.

.. ..

..

.

.

___---_-_-_-_

."

'

,_

9

l

!

INSPECTION PROCEDURES USED

IP 40500:

Effectiveness of Licensee Controls In Icntifying, Resolving, &-

Preventing Problems

IP 7170/:

Plant Operations

.

ITEMS OPENED

Iype Item Number

Status

Descrintion and Reference

EEI

50-327, 328/97-13 01

Open

Two Examples of Failure to follow a

Procedure (Section C)

EEI

50-327, 328/97 13-02

Open

Failure to Perform Independent

Verification, and Failure to

Properly Perform AVO Rounds

(Section C)

EEI

50-327, 328/97-13-03

Open

Failure to Meet The TS LCO Action

Requirements Of TS 3,8,2.3,b For

Vital Battery Bank Operability

(Section C)

EEI

50-327, 328/97-13 04

Open

Failure to Promptly Identify an

Adverse Condition (Section C)

-