Responds to IE Bulletin 85-003, Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings. Listing of Valves Affected by Bulletin Encl
ML20197J656
Person / Time
Site: Washington Public Power Supply System
Issue date: 05/12/1986
From: Holmberg B
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
G1-86-65, GO1-86-0065, GO1-86-65, IEB-85-003, IEB-85-3, NUDOCS 8605200123
Download: ML20197J656 (4)


Text

.

p.
  • Washington Public Power Supply System P.O. Box 968 3000Geor0eWashingtonWay Richland, Washington 99352 (509)372-5000 b

, May 12, 1986 5 m G01-86-0065  :

S, -

B

.$.G

~q Q

? :S Mr. John B. Martin Regional Administrator f

Nuclear Regulatory Commission, Region V in 1450 Maria Lane, Suite 210 Walnut Creek, California 94596

Subject:

NUCLEAR PROJECT NO.1 DOCKET N0. 50-460 IE BULLETIN 85-03

Reference:

IE Bulletin 85-03, Motor Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings, dated November 15, 1985.

IE Bulletin 85-03 is based on various recent events and historical issues related to motor operators. Specifically, the Bulletin addresses the motor operated valves in the high pressure coolant injection / core spray and-emergency feedwater systems that are required to be tested for operational readiness in accordance with 10CFR50.55a(g).

The Bulletin specifically requests that the utility develop and implement a program to ensure that the valve operator switches are selected, set and maintained properly. A summary of the components this program should include are as follows:

a) Review and doctrnent the pertinent design basis for each valve.

b) Based on the results of Item a) above, establish the correct switch settings, i.e. torque, torque bypass, position limit, and overload for each velve operation.

c) Revise individual valve settings, as appropriate, to those estab-lished in Item b) above. Perform testing, as appropriate, at the maximum differential pressure to assure proper operation.

d) Prepare or revise procedures to ensure that correct switch settings are determined and maintained throughout the life of the plant.

e) Results of Item a) were to be submitted to the NRC within 180 days, along with a program and schedule for completing Items b) through d) prior to receiving an Operating License.

8605200123 860512 PDR ADOCK 05000460 i \

G PDR f5 ll

Mr. John B. Martin Page Two May 12, 1986 G01-86-0065 WNP-1 is currently in an Extended Construction Delay mode. The construction restart date is uncertain and the scheduled date of Operating License issuance is not known. Although some design work is still in process, the Project is experiencing further manpower reductions in this area. For these reasons, the Supply System response to this Bulletin is limited to the attached listing of valves that are affected by the Bulletin.

WNP-1 pl ans to implement a program and provide the complete response to IE Bulletin 85-03 after receiving a construction restart notice. This will provide ample time to complete our investigations and provide a final response to the Bulletin prior to receiving an Operating License.

If there are any questions, please advise.

-} Au B. A. Holmberg WNP-1 Program Director (821)

BAH /LC0:pd Attachment cc: G. Haren, UE&C (895)

V. Mani, UE&C (897)

NRC Docuaent Control Desk, Washington D. C.

e

o STATE OF WASHINGTON)

)

COUNTY OF BENTON )

B. A. HOLMBERG, being first duly sworn, deposes and says: That he is the Program Director, WNP-1, for the WASHINGTON PUBLIC POWER SUPPLY SYSTEM, the applicant herein; that he is authorized to submit the foregoing on behalf of said applicant; that he has read the foregoing and knows the contents thereof; and believes the same to be true to the best of his knowledge.

DATED f 1 o , ) 7- , 1986

(

$7dArklw I

B. A. HOLMBERG On this day personally appeared before me B. A. HOLMBERG to me known to be the individual who executed the foregoing instrument and acknowledged that he =

signed the same as his free act' and deed for the uses and purposes therein mentioned.

GIVEN under my hand and seal this day of [ hat, , 1986

./ tilfilipffa NotaryPu'blidinandfortheStateofWashington

?

Residing at ( ._ A fr,((/o t

y __

Attachmer.t List of motor operated valves required to be tested for operational readiness in accordance with 10CFR50.55a(g) in MUS, DHR, CFS and FWA Systems System Designation Valve Number High Pressure Injection and Vl-A V208-8 Makeup System V2-B V237 V3-A V238 V4 -A V239 V5-B V240 V81 V279-A V136-A V280-A V137-B V281 -A V141-B V282-A V144-A V283-B V174-A V360-A V179-A V380-A V184-B V381-B V185-B V465-B Vl98-A V685-A Vl99-B V686-B Decay Heat Removal (DHR) Vl-A V32-B V2-B V63-A V7-A V64-B V8-B V71-A V23-A V72-B V24-B V73-A V25-A V74-B V26-B V308-A V31-A V309-B Core Flood System (CFS) V31 -A V32-B Auxiliary Feedwater System (FWA) V14-A V20-B V31 -B V37-A