'Af 2NRC-6-092 Beaver Valley No. 2 Unit Project Organization Telecopy 200 Ent.160 QG. sui no August 22, 1986 Shippingport, PA 15077 United States Nuclear Regulatory Comission 631 Park Avenue King of Prussia, PA 19406 ATTENTION:
Mr. William Lazarus Executive Director for Operations g
SUBJECT:
Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 Emergency Planning Implementation Appraisal Gentlemen:
Beaver Valley Power Station Unit 2 is scheduled to receive its 5%
(
Operating License (Fuel Load) on April 30, 1987.
As a prerequisite to receiv-ing this Operating License, an Emergency Preparedness Implementation Appraisal will be conducted 60-90 days prior to Fuel Load by the NRC. Therefore, DLC is requesting this Appraisal to be scheduled for the end of January 1987.
It is also DLC's understanding that a preappraisal meeting would then occur in Decenber 1986.
If you have any questions, please call T.
J.
Zogimann at (412)643-5200 ext 232.
DUQUESNE LIGHT COMPANY
/
1 By u d.Xarey Vice President TJZ/ijr cc: Mr. P. Tam, Project Manager Mr. F. Pavlechko INPO Records Center h
NRC Document Control Desk 8611070082 860822 PDR ADOCK 05000412