Final ASP Analysis - Quad Cities 2 (LER 265-75-035)
ML20168A719
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 06/16/2020
From: Christopher Hunter
NRC/RES/DRA/PRB
To:
Littlejohn J (301) 415-0428
References
LER 1975-035-00
Download: ML20168A719 (4)


Text

PRECURSOR DESCRIPTION AND DATA NSIC Accession Number:

106333 Date: August 30, 1975

Title:

HPCI Found Inoperable at Quad Cities 2 The failure sequence was:

1. The RCIC system had failed for reasons unspecified.
2. A test was initiated to determine the operability of HPCI
3. This test revealed that HPCI was also inoperable due to a broken auxiliary oil pump lime.
4. Since both RCIC and HPCI were inoperable am orderly shutdowm was initiated.

Corrective action:

1. The reactor was shutdown in an orderly fashion.
2. The HPCI auxiliary oil pump line was replaced with the sarae type of line.

Design purpose of failed system or component:

1. RCIC provides for core cooling when feedwater is unavailable.
2. HPCI provides emergency cooling water-when the system pressure is above the LPCI and CS operating pressures.
3. The auxiliary oil pump provides lubrication to the HPCI turbine prior to initiation of the turbine driven lube oil pump.

Unavailability of system per WASH 1400:

  • RpCm 8.8 x 10-2 /D Unavailability of component per WASH 1400:
  • pump failure to start:

I x 10-3 /D Unavailabilities are in units of per demand D-1.

Failure rates are in units of per hour HR-1.

RCIC Surveillance testing HPCI Reactor inoperable on HPCI to prove inoperable shutdown operabilityI Potential Severe Core Damage No

-No -ADSILPCI/CS available; however, a violation if Tech. Specs.

-No

-No -ADS/LPCIICS available; however, a violation of Tecl'. Specs.

NSIC 106333 -

Actual Occurrence of HPCI Found Inoperable at Quad Cities 2

Loss of Reactor RCIC/HPCI Automatic LPCI or Long Feedwater Subcritical

Response

Depressurization CS Response Ter Flow Adequate System Operates Adequate Cor Coln Potential Severe C ore Damage Sequence No.

I No Yes 1

2 3

(F)

No Yes No Yes Yes Yes Yes 5

6 7

NSIC 106333 -

Sequence of Interest for HPCI Found Inoperable at Quad Cities 2

CATEGORIZATION OF ACCIDENT SEQUENCE PRECURSORS NSIC ACCESSION NUMBER:

106333 DATE OF LER:

September 9, 1975 DATE OF EVENT: August 31, 1975 SYSTEM INVOLVED:

HPCI COMPONENT INVOLVED:

aux lube oil pump CAUSE: broken oil line SEQUENCE OF INTEREST:

loss of feedwater flow ACTUAL OCCURRENCE:

HPCI found inoperable at Quad Cities 2 REACTOR NAME: Quad Cities 2 DOCKET NUMBER:

50-265 REACTOR TYPE:

BWR DESIGN ELECTRICAL RATING:

789 MWe REACTOR AGE:

3.4 yr VENDOR:

General Electric ARCHITECT-ENGINEERS:

Sargent & Lundy OPERATORS: Commonwealth Edison LOCATION:

20 miles NE of Moline DURATION:

360(a) hours PLANT OPERATING CONDITION:

69% power SAFETY FEATURE TYPE OF FAILURE:

(a) inadequate performance; failed to start; (c) made inoperable; (d) ____________

DISCOVERY METHOD:

surveillance testing COMMENT:

-