ML20155D527

From kanterella
Jump to navigation Jump to search
Ack Receipt of Util Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-440/87-25 & Requests Addl Info Re Listed Actions within 30 Days of Ltr Date
ML20155D527
Person / Time
Site: Perry 
Issue date: 05/20/1988
From: Miller H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Kaplan A
CLEVELAND ELECTRIC ILLUMINATING CO.
References
NUDOCS 8806150233
Download: ML20155D527 (3)


See also: IR 05000440/1987025

Text

.

_

..

.

-

a-

.

.

.

MAY 2 01988

Docket No. 50-440

The Cleveland Electric Illuminating

Company

ATTN: Mr. Alvin Kaplan

Vice President

Nuclear Group

10 Center Road

Perry, OH 44081

Gentlemen:

Thank you for your letter of April 29, 1988, in response to our Inspection

Report No. 50-440/87025 for the Perry Nuclear Power Plant. After our review

of your response, and the telephone conversations between Mr. 5. Reynolds of

our staff and Mr. C. Jones of your staff on May 6,1988, it was agreed that

certain actions need to be addressed in a followup written response. These

actions are identified below along with coments to emphasize the importance

placed on the problems identified during the inspection.

A.

Violation 440/87025-038. Our concerns include:

1) nine motor operated

valves (MOVs) had inadequate lubrication; 2) repetitive tasks for those

M0Vs were last completed in 1985; and 3) those repetitive tasks had been

rescheduled well past the "late" due date.

Procedure PAP 0906 does not

provide criteria for making decisions to defer maintenance nor does the

procedure require that documented technical evaluations be made before

deferring maintenance. Discussions with responsible system engineers

indicated that effects on plant safety, operability, or reliability were

not considered before rescheduling M0V related maintenance.

As agreed with Mr. C. Jones, your supplemental response will

91ude the

actions taken to resolve our concerns about the nine MOVs

including the

effects, if any, on plant safety, operability, and reliability.

B.

Violation 440/87025-03C. Our concern is that the M0V manufacturer specified

the upper bearing be lubricated but procedure PMI-0030 did not include such

an instruction which resulted in several M0Vs not being lubricated.

As agreed with Mr. C. Jones, your supplemental response will include the

actions taken for all applicable MOVs, and to the effetts, if any, on plant

.

safety, operability and reliability.

!

!

C.

Violation 440/87025-03A. Our concern is that completed work orders do no't

!

include accurate information for maintenance history data and trending.

}

!

!

!

\\

\\

> \\l

8806150233 880520

. Q)

l

{DR ADOCK0500gj0

-_

__-____

__

.

-

r-

.

.

O

The Cleveland Electric

2

MAY 201988

Illuminating Company

As agreed with Mr. C. Jones, your supplemental response will include the

actions taken to ensure'that accurate maintenance history data is recorded,

readily available, and utilized to provide effective trending.

D.

Violation 440/87025-03D. Our concern is that problems identified during

. Audit PIO 87-12 bypassed the established corrective action process because

the problems were incorrectly identified as "observations" rather than

,

"deficiencies" which would be corrected thru Action Requests. The example

in our inspection report of untimely corrective action was an obvious,

non-subjective, violation of your QA Program and 10 CFR 50, Appendix B,

Criterion XVI and clearly should have been a "deficiency".

Even though only one example of our concern was documented in our report,

as discussed with members of your staff, there were several other observations

that should have been "deficiencies".

An objective of your audit system should be to assess the effectiveness of

the processes controlled by your QA Program.

"Performance related" means

actions that affect or have the potential to affect performance of structures,

components , or systems.

Overall, your response did not address the salient points that impact plant

system performance; instead, you emphasized corrective actions that partained

to correction of instructions and documentation.

Your supplemental response is expected within 30 days of the da2e of this letter.

Thank you for your cooperation.

l

Sincerely,

.

, DRIGINAl. SIGNED BY. HUBERT J. MILLER

Hubert J. Miller, Director

Division of Reactor Safety

Enclosure: Ltr dtd 4/29/88

See Attached Distribution

RIII 7"

RII)

RIII

RIII

RIII

RIII

Reynl olds /j k Jah'onski

gLfC 41,1//

L\\?

LL

Coopef

ttHarrison

ChAhotimos

il er

05/16/88

057;7/88

05/ N/8

05//) /88

05/q/88

5

/88

t,v)

. _ _ _

.

..

,-

- .

I

.

.

The Cleveland Electric

3

Illuminating Company

gjAY 2 01988

Distribution

cc:

F. R. Stead, Director, Perry

Plant Technical Department

M. D. Lyster, General Manager,

Perry Plant Operations Department

Ms. E. M. Buzzelli, Manager,

Licensing and Compliance Section

cc w/itr dtd 04/29/88:

DCD/DCB (RIDS)

Licensing Fee Management Branch

Resident Inspector, RIII

Harold W. Kohn, Ohio EPA

Terry J. Lodge, Esq.

James W. Harris, State of Ohio

Robert M. Quillin, Ohio

Department of Health

State of Ohio, Public

'

Utilities Conmission

Murray R. Edelman

_______

____ __ _ .

.

.

.

'

-

m -

~

3. .;, .;

< . . l l. . .1

.1 s

~

-

'o

1 \\

y3

.l : n f.

~

s ~

1

'

I

.

..a

+,..,

>1m

,a

s .

.

P.O.

BOX 97

e

PEARY, OHIO 44081

o TELEPHONE {216) 259-3737

o

ADORESS to CENTER ROAD

n

Serving The Best location in the Nation

PERRY NUCLEAR POWER PLANT

Al Kaplan

t' ICE PRESJOENT

m ow,

April 29, 1983

PY-CEI/NRR-0345 L

U.S. Nuclear Regulatory Commission

Docume nt Control Desk

Washington, D. C.

20555

Perry Nuclear Power Plant

Docket No. 50-440

Response to Notice of

Violation 50-440/37025-03

Dear Gentlemen:

This letter acknowledges receipt of the Notice of Violation contained within

Inspection Report 50-440/87025 dated March 31, 1988.

The re po rt identified

areas examined by Mr. W. Kropp and others during their inspec tion conducted

f rom January 11, 1938 through February 9,1988 of activities at the Perry

Nuclear Power Plant , Uni t 1.

Our response to Notice of Violation 50-440/87025-03 is attached. Please call

should you have any additional questions.

Very truly yours,

1M4

f

-

Al Kaplan

Vice President

Nuclear Group

AK: cab

At tac hme nt

cc:

T. Colburn

K. Connaughton

H. Miller - USNRC, Region III

-

J4["; Ol Ti

'J/n

MAY 2

1983

.

.

Attachment

PY-CEI/NRR-0845 L

.

Page 1 of 9

50-440/87025-03

Restatement of Violation

10 CFR 50, Appendix B, Criterion V, as implemented by PNPP, Operational Quality

Assurance Plan, Section 5.0, requires that activities affecting quality be

prescribed by instructions or procedures and accomplished in accordance vi:h

those instructions or procedures.

Section 5.0 further requires procedures to

include appropriate quantitative or qualitative acceptance criteria for

determining that important activities have been satisfactorily accomplished.

Contrary to the above:

Procedure PAP-0906, "Control of Haintenance Section Preventive

a.

Maintenance," Revision 1, did not include criteria to make technical

evaluations for rescheduling preventive maintenance activities. As a

result, repetitive tasks (preventive maintenance) already several months

past due, vere rescheduled for nine motor-operated valves in the residual

heat removal and liquid radvaste systems without evaluations of the

effects the delays could have on plant safety, operability, or

reliability. (440/87025-03B)

3.

The licensee failed to fully accomplish Preventive Maintenance

Instruction, PMI-0030, "Maintenance of Limitorque Valve Operat)rs,"

Revision 1, as follovs:

o

The inspector observed that valve stems for several residual heat

removal system and liquid radvaste system valves vere lubricated with

Neolube although PMI-0030 specified Nebula EPO.

o

There vas no objective evidence that two residual heat removal system

valves had been electrically and manually cycled as specified in the

post maintencnce requirements of PMI-0030.

(440/87025-03C)

C.

The licensee failed to properly implement Administrative Procedure

PAP-0905, "Vork Order Process," Revision 7, which outlined the

requirements for processing vork orders (V0) from initiation to closure as

follows:

o

V0 87-9677 - Summary description did not accurately reflect the

activity perforced;

o

VO 87-5727, 87-10390, 88-0080 - Incomplete or incorrect corrective

action indicated on VO Closing and Summary Sheet;

V0 87-6175, 87-7385, 87-8746, 87-9361, 87-9498, 87-9677, 87-10213 -

o

Incorrect or inadequate immediate failure cause identified on the Vo

Closing and Summary Sheet;

'

.

,

,

-

Attachm:nt

PY-CEI/NRR-0845 L

.

Page 2 of 9

o

VO 87-2249, 87-8746, 87-9361, 87-9677, 87-10390 - Incorrect or

incomplete VO closing codes;

o

V0 87-4825, 87-8298, 87-8597, 87-9677 - Incorrect or incomplete Master

Part List (MPL) numbers; and

o

V0 87-9361 - Inadequate closing summary on the VO Closing and Summary

Sheet.

(440/87025-03A)

D.

The licensee failed to fully accomplish Nuclear Quality Assurance

Department procedure, NOAD 1840, Revision 2, "Audit Performance," Section

6.2, which required that deficiencies noted during audits be documented on

Action Pequests.

Deficiencies identified during Audit 87-12,

"Effectiveness of Corrective Action" vere listed as observations;

therefore, the established corrective system was bypassed. One

observation pertained to continued untimely and ineffective corrective

action, which prior to Audit 87-12, had also been identified as a concern

by the licensee's OA organization and the NRC.

(440/87025-03D)

This is a Severity Level IV violation (Supplement I).

~

i

Correct ve Action Taken and Results Achieved

A.

Failure to document technical evaluations for rescheduling preventive

mair.tenance activities.

CEI egrees that PAP-0906 did not specifically include criteria to make the

technical evaluations nor require documentation of the evaluations.

However, system engineers involved in rescheduling repetitive tasks have

used engineering judgment, verbal instructions from unit leads, and/or

,

informal desk-guide type instructions when performing this activity. The

issue is net whether technical evaluations vere performed for rescheduled

repetitive tasks, but whether this evaluation was documented.

In order to

1

allov for documentation of the technical evaluation, a Preventive

'

Maintenance Deferral Evaluation / Justification Sheet has been developed and

is beiag incorporated into the appropriate repetitive task procedures.

This form provides for a documented "Justification for Reschedule" and

i

"Effect on Component / Consequences of Non-performance" for safety-related

i

repetitive tasks. Also, informal desk-guide instructions are being

'

developed which vill provide the system engineer with a list of

appropriate questions to ask when considering approval or denial for

rescheduling of a task. The form and the desk-guida instructions vill

provide consistent documented technical justification of approval or

denial for rescheduling of safety-related repetitive tasks.

1-

.

. .

.

Attcchment

.

PY-CEI/NRR-0845 L

.

Page 3 of 9

B.

Several examples vere identified of failure to fully accomplish Preventive

Maintenance in accordance with PMI-0030.

1.

The inspectors observed inconsistencies in valve stem lubrication.

CEI agrees that inconsistencies existed among the as-found conditions

as well as the procedures and instructions which control the

lubrication of these valve stems. As a result of these

inconsistencies, procedures have been revised and training has been

performed for maintenance personnel invclved in this activity. These

,

inconsistencies vere also evaluated as described below. An

engineering evaluation was performed to determine the significance of

valve stems lubricated with Neolube instead of Nebula EPO. The

conclusion was that all of the valve stems identified vere adequately

'

lubricated in accordance with vendor recommendations. Hovever,

improvements in lubrication practices should be made. The vendor of

these valves recommends Neolube as an acceptable valve stem lubricant.

Neolube is a graphite type lubricant that dries upon application to

the stem, leaving a fine dry graphite film coating.

In cases where

only Neolube exists on the valve stems, it should be recognized that

PMI-0030 did not require stem lubrication if the existing lubrication

was determined to be sufficient. Additionally, for MOVATS testing of

these valves per General Engineering Instruction (GEI)-0056, Neolube

vas utilized as the valve stem lubricant.

In cases where both Neolube

and Nebula EPO exist on the valve stem, it is possible that

lubrication with Nebula EP0 vas deemed necessary during a performance

of PMI-0030. This PHI did not require cleaning of the stem before

applying lubrication, thus potentially resulting in both Neolube and

Nebula EPO being present. An engineering evaluation of the

compatibility of the two lubricants determined that mixing of the two

lubricants vill have no deleterious effect on the valve or its

operability.

For the case where PMI-0030 did not require lubrication

of the MOV upper bearing, a review of the vendor recommendations

determined that the upper bearing should be lubricated periodically,

resulting in a change to PMI-0030 on January 29, 1988.

The following procedure changes and training have been completed.

PHI-0030 as revised January 29, 1988 and GEI-0056 vas revised January

28, 1988 to be consistent in future lubrication activities.

For

future Rockvell Hermaseal valve stem lubrication, Nebula EP0 vill be

'

used.

For future stem lubrication of rising stem gate and globe

valves, Never-Seez vill be used. Never-Seez is a lubricant that

leaves a vet film coating which does not dry upon application.

Mobilgrease 28 vill be used in limit switch gear boxes, and Nebula EP0

j

vill be used on operator main nousings and upper bearing grease

fittings. Also, the instructions nov require that when a valve stem

i

needs to be relubricated, it shall first be thoroughly cleaned and

inspected prior to relubrication. Appropriate maintenance workers

have been trained to these changes.

i

.

. ..

. _ _ . __ _

_

_ _ _, -_

_

__

__

_ o

. . ,

'

. .

Attech:snt

PY-CEI/NRR-0845 L

,

Page 4 of'9

.

.

2.

The inspectors found no objective evidence of valve cycling af ter

performance of PMI-0030. Research into the work history of the

subject RHR valves determined that the valves have been cycled since

'

the performance of the PMI. This was performed on January 9, 1988 in

accordance with the periodic Technical Specification surveillance to

verify operability .and no problems were experienced. PMI-0030 has

been revised (effective April 29, 1988). to specify that the Control

Room Unit Supervisor shall establish retest requirements. . A further,

revision to PMI-0030 vill provide for documentation of retest

completion.

l

C.

Several examples were identified of inadequate and/or incomplete

-

documentation during the review of completed V0s.

]

5

1.

VO 87-9677: Summary. description did not accurately reflect the

'

activity performed.

This VO vas performed to troubleshoot and repair a Residual Heat

-

Removal (RRR) pump not initiating on high heat exchanger level as

expected. The cause of this problem was determined to be a level

transmitter lE12-N008A being out of calibration. The corrective

actions taken with the V0 vere recalibration of the trensmitter and a

circuit loop check. The closing summary as stated on the VO Closing

and Summary Sheet vas, "Recalibrated transmitter and loop checked

]

Sat."

PAP-0905 in section 6.7, Vork Order Package Closeout, requires

'

the planner or vork supervisor to ". . .vrite a short, concise summary

statement of the work actually performed..." Ve believe the

requirement of PAP-0905 was met end the summary description did

,

-

accurately reflect the activity performed. The only enhancement that

j

could be made to the summary would be to include the transmitter MPL

number. However, this MPL number was adequately reflected on the same

1

Closing and Summary Sheet within the corrective action summary

description.

2.

VO 87-5727, 87-10390, 88-0080:

Incomplete or incorrect corrective

action indicated on VO Closing and Summary Sheet.

-

a.

VO 87-5727 is still in the planning stages; no vork has been

performed on this V0; and thus, no Closing and Summary Sheet has

been nor should have been complete for this V0.

Ve believe that

the V0 number should have been 87-5722 in your inspection report.

The VO Closing and Summary Sheet for this VO initially stated in

the corrective action summary, "All vork completed per the job

traveler; change out and H0 VATS per UR PPDS-2554". This was

deemed insufficient and was revised to "Replaced Limitorque

operator with rebuilt spare, performed MOVATS on actuator per

GEI-0056, adjusted torque switch per SCR 1-87-1576, and installed

nev limiter plate". This change has been incorporated into the

PPMIS history file for this V0.

!

.

,.

-

---

_ _ _ _ _ _ _ _

..

___. _ _

- - - - - - -

.

.

Attachment

PY-CEI/NRR-0845 L

Page 5 of 9

b.

V0 87-10390 vas performed to troubleshoot intermittent relay

'

problems in the Feedvater Control circuitry and to change three

relays as directed by Design Change Package (DCP)87-807. The V0

Closing and Summary Sheet initially stated in the corrective

action summary, "Implemented DCP 87-0807".

This was deemed

insufficient and was revised to, "Replaced existing time delay

relays with Potter-Brumfield relays per DCP 87-807.

Calibrated

relays and obtained voltage readings for operating point of PDU

output switch.

Cleaned contacts and calibrated associated relays

in control panel".

This change has been incorporated into the

PPMIS history file for this V0.

'

c.

VO 88-0080 vas performed to replace the charge for the Standby

Liquid Control squib valve per Surveillance Instruction

(SVI)-C41-T2002.

During the performance of this VO power

indication problems vere observed.

Troubleshooting of the

circuitry identified two blown fuses which vere promptly replaced.

The V0 Closing and Summary Sheet corrective action summary

initially only described the squib valve charge replacement. This

was deemed insufficient and was revised to include the circuitry

troubleshooting and replacement of identified blown fuses. This

change has been incorporated into the PPMIS history file for this

V0.

3.

VO 87-6175, 87-7385, 87-8746, 87-9361, 87-9498, 87-9677, 87-10213:

Incorrect or inadequate immediate failure cause identified on the VO

Closing and Summary Sheet.

a.

V0 87-6175 vas performed to modify the stem and manufacture a new

stem nut for valve lE12-F0024A in accordance with DCP 87 463.

The

VO Closing and Summary Sheet initially stated in the immediate

failure cause summary, "Modification of valve stem".

This was

deemed incorrect and was revised to "N/A" since the V0 vas only

implementing a design change. This change has been incorporated

into the PPMIS history file for this V0.

b.

VO 87-7385 facilitated the mechanical portion of vork required to

implement DCP 87-162A, which replaced the lE22-C0004A diesel

engine with an electric motor. The VO Closing and Summary Sheet

initially stated in the immediate failure cause summary, "Replace

diesel engine (Petter diesel) due to diesel failure". This was

deemed incorrect and was revised to "N/A" since the VO vas only

implementing a design change. This change has been incorporated

into the PPMIS history file for this V0.

c.

VO 87-8746 was performed to troubleshoot and repair the Division

II Diesel Generator due to the field not flashing.

The V0 Closing

and Summary Sheet initially stated in the immediate failure cause

summary, "Diesel vould not field flash". This was deemed

incorrect and was revised to "Unable to identify /unknovn" since

the troubleshooting failed to identify any problems. This change

has been incorporated into the PPMIS history file for this V0.

t

_ _ _ _ _ _ _ - _ - _ _ _ _ _ .

-

'

.

.

. .

Attachrant

PY-CEI/NRR-0845 L

'

Page 6 of 9

'

d.

VO 87-9361 was performed to troubleshoot and repair a leak from a

snubber located above an RHR pressure transmitter lE12-N0050B.

The VO Closing and Summary Sheet initially stated in the immediate

failure cause summary, "steam leak at snubber". This was deemed

insufficient and was revised to "Instrumentation tubing connection

leaking. Loose connection" since the problem was identified as a

loose tubing connection. This change has been incorporated into

the PPMIS history file for this V0.

e.

VO 87-9498 vas performed to troubleshoot a Division II Diesel

Generator failure to start during the performance of

SVI-R43-T1318. The VO Closing and Summary sheet initially stated

in the immediate failure cause summary, "Diesel Div. II did not

-

see pneumatic start".

This was deemed insufficient and vas

revised to "Not identified - Suspect solenoid start valves

1R43-F0037B and F0030B" since the troubleshooting failed to

pinpoint the cause. This change has been incorporated into the

PPMIS history file for this V0.

f.

VO 87-9677 vas performed to troubleshoot and repair incorrect

level indication for a RHR heat exchanger. The VO Closing and

Summary Sheet initially stated in the immediate failure cause

summary, "RHR HX A level indication is low".

This was deemed

insufficient and was revised to "Level transmitter lE12-N0008A out

of calibration" since the calibration problem is the cause which

vould be utilized in Failure Analysis trending. This change has

been incorporated into the PPMIS history file for this V0.

g.

VO 87-10213 was performed to repair bad connectors for two LPRMs

reading downscale. The VO Closing and Summary Sheet states in the

immediate failure cause summary, "Bad connectors". This was

deemed adequate since the problem was downscale LPRMs and the

immediate cause was bad connectors.

Identification of the cause

of bad connectors vould be part of the root cause evaluation as

part of the Failure Analysis program and is thus outside the scope

or requirements of PAP-0905.

4.

VO 87-2249, 87-8746, 87-9361, 87-9677, 87-10390:

Incorrect or

,

incomplete VO closing codes.

The ineffectiveness of VO closing codes was identified by CEI during

the INP0 Maintenance Self Assessment which was completed in November

of 1987. These codes were initially designed to aid in failure

analysis. However, due to recommendations provided f rom the Failure

Analysis committee and the ongoing development of the Reliability

Information Tracking System (RITS), the decision was made to eliminate

many of these PPMIS closing codes from the PAP-0905 vork order

process. The failure analysis program needs will be better supplied

,

through a centralized evaluation of the existing V0 closing summaries.

.

- -

- --

'

.

. .

.

'

Attcchocnt

PY-CEI/NRR-0845 L

a

Page 7 of 9

!

L

5.

VO 87-4825, 87-8298, 87-8597, 87-9677:

Incorrect or incomplete Master

i

l

Part List (MPL) numbers.

The concern over MPL numbers chosen during V0 initiation was

identified by CEI during a QA audit report PIO 87-12. "Effectiveness

of Corrective Action", issued July 29, 1987. PAP-0905 states that Vos

should, when practical, address only one MPL number, and that single

MPL numbers need not be addressed on V0s written to fill and vent

instrumentation, for troubleshooting, or on standing V0s.

a.

VO 87-4825 was written to determine the cause of a Reuter-Stokes

indexer failure. The MPL number utilized to open this VO vas

"N/A" since the indexer was not installed in the plant and thus

had no MPL number. This indexer was removed from the field and

replaced with a new indexer on March 26, 1987 in accordance with

VO 87-2620. The MPL number used for VO 87-2620 was 1C51-J0002C

and the failure cause was identified as "unknovn, VO 87-4825

vritten to troubleshoot failed indexer". VO 87-4825 could not

have had a MPL number assigned to a salvaged component no longer

installed in the field. However, to ensure identification of this

VO during future trending or failure analysis, the work summary

specified the MPL number of the component when it was installed in

the field and also referenced VO 87-2620 as the VO vhich

originally removed the component from the field. Therefore, ve

believe that this VO vas written properly and is not an example of

a violation.

b.

VO 87-8298 vas vritten to troubleshoot a contact failure to open

r

on relay 1E12-K42. The MPL number utilized to open this VO vas

the system HPL 1E12. The Plant Equipment Master-file System

(PEMS) which ties into PPHIS to provide equipment data based on

the HPL number input, does not contain MPL numbers for relays.

Therefore, the identification number for this relay could not have

been used as the VO initiating MPL number. However, to ensure

identification of this VO during future trending or failure

analysis, the work summary specified the problem as a relay

1E12-K42 failure to open.

Therefore, ve believe that this VO vas

written properly and is not an example of a violation,

c.

V0 87-8597 vas written to troubleshoot a lov temperature

indication for the Division I Diesel Generator lube oil.

Since

the problem had not yet been identified, the MPL number utilized

to open this VO vas the DG lube oil system HPL 1R47.

If a

specific component vere to be identified as the problem, the only

way to change the MPL number vould be to void the VO and then open

a nov VO vith that HPL number. Nonetheless, troubleshooting

failed to identify any problems.

For future trending or failure

analysis the suspected trouble components are vell documented

throughout this V0.

Therefore, ve believe that this VO vas

written properly and is not an example of a violation.

f

. _ . .

-

-

-

'

-

.

.

.

Attechacnt

PY-CEI/NRR-0845 L

Page 8 of 9

J

d.

V0 87-9677 was written to troubleshoot and repair incorrect level

indication for a RBR heat exchanger.

Since the problem was

s

suspected to be the controller 1E12-R0604A, this HPL number was

,

utilized to open this V0.

Troubleshooting identified the level

transmitter 1E12-N0008A as being out of calibration. Again, the

'

only way to change a VO initiation HPL number is to void the V0

and then open a new VO vith the nev MPL number.

Since this is not

required and extremely inefficient, this vill not be done.

However, to ensure identification of the VO during future trending

or failure analysis, the corrective action identified in the

Closing and Summary Sheet specifies the required recalibration of

level transmitter 1E12-N0008A. Therefore, ve believe that this VO

vas written properly and is not an example of a violation..

6.

VO 87-9361:

Inadequate closing summary on she VO Closing and Summary

Sheet.

l

This VO vas performed to troubleshoot and repair a leak from a snubber

located above an RHR pressure transmitter lE12-N00508. The VO Closing

and Summary Sheet initially stated in the closing summary, "No leakage

anymore". This was deemed insufi4cient and was revised to "Revorked

tubing fitting with reactor seal #5" since this was the actual work

required to correct the problem. This change has been incorporated

into the PPMIS history file for this V0.

!

D.

The concerns identified in Audit PIO 87-12 vere listed as observations

because they were subjective and related to ef fectiveness of

implementation of the corrective action programs as opposed to compliance

with the procedurer. The Quality Assurance procedure, NOADI-1840,

,

requires that each deficiency be documented on an Action Request (AR).

As indicated in your report, our audit program has become more

i

"performance related". The audit found compliance with the program to be

'

adequate but the deficiency noted was "performance related". The line

,

which separates deficiencies from improved performance is not vell defined

and is open to interpretation resulting in this deficiency being

documented as a recommendation rather than an AR.

As for your identified

-

example, the audit organization has re-evaluated the effectiveness of the

Condition Report program and noted an improvement in both number open and

mean time for closure of Condition Reports. This improvement was

partially due to actions taken as a result of the recommendraions in Audit

PIO 87-12.

Corrective Action To Avoid Further Violations

A.

The Preventive Maintenance Deferral Evaluation / Justification Sheet as

discussed previously vill be formally incorporated into IAP-0501 and

PAP-0906, for Instrumentation and Control Section and Maintenance Section

respectively, by June 30, 1988. The guidelines for performing a proper

technical evaluation for rescheduling repetitive tasks vill be provided to

the appropriate engineers by May 30, 1988.

]

l

1

-

- -

-

-

-

-

.

.

. .

-

-

- -

- - .

-

.

.

.

.

g

. , .

.

Attechacnt

PY-CEI/NRR-0845 L

'

Page 9 of 9

,

B.

1.

As discussed previously, procedure changes relative to the valve

'

lubrications were completed January 29, 1988. Training for

appropriate maintenance personnel to these procedure changes has also

been completed.

t

2.

The previously discussed revision to PMI-0030 to provide for

>

1

documentation of retest completion vill be complete by May 20, 1988.

C.

To ensure that the intent of the requirements of PAP-0905 is adequately

met, the following corrective actions have been or vill be implemented.

1.

Training is being provided to work supervisors and planners

emphasizing their VO reviev responsibilities and the importance of

providing adequate summaries on the VO Closing and Summary Sheet.

This effort vill be complete by May 31, 1988.

2.

A Reliability Information Tracking System (RITS) is being implemented

manually and vill be fully computerized by April 30, 1989. The

objective of this program is to analyze component failures, and based

on the results, recommend corrective actions to prevent recurrence.

As a result of this program, changes are being made to PAP-0905, Vork

Order Process.

a.

A Program Change Request (PCR) has been initiated to provide a

section on the VO Closing and Summary Sheet for MPL numbers of all

affected equipment. This vill ensure a greater capture percentage

when trending for failure analysis or planning a VO on a

particular component. This PCR vill be complete by

November 30, 1988.

b.

PAP-0905 vas revised (effective March 1, 1988) to eliminate the

need for the vork groups to determine "Failure Category" and

"Cause of Failure" closing codes. The RITS program vill utilize

the summaries within the VO package to consistently determine VO

closing codes for trending purposes when deemed necessary.

D.

To ensure that the interpretation between deficiency and improved

i

performance is made conservatively, QA guidelines have been revised to

clarify the threshold for issuing ARs to include not only programmatic

deficiencies or noncompliance, but also significant deficiencies which

affect the effective implementation of processes. Appropriate QA

personnel vere . ained to this change April 29, 1988.

Date of Full Compliance

Full compliance vill be achieved upon full implementation of RITS by

April 30, 1989.

'

.

,-_