ML20155B054

From kanterella
Jump to navigation Jump to search
Insp Rept 50-285/88-15 on 880406-0513.No Violations Noted. Major Areas Inspected:Followup on Status of Instrument Air Accumulator Assemblies & Followup on Onsite Event
ML20155B054
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 06/01/1988
From: Harrell P, Reis T, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20155B040 List:
References
50-285-88-15, NUDOCS 8806130065
Download: ML20155B054 (26)


See also: IR 05000285/1988015

Text

__-___ __- __-

_ - _ _ _ _ _ .- _ -

_ _ _ _

. __ __ - -

- _______

_ _ __ __________ _ _-_____ ____ _ ___ ____ _ __

,

..

',

,.

-

.

.

,

APPENDIX A

,

'

U. S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report:

50-285/88-15

Operating License:

DPR-40

Docket: -50-285

Licensee: Omaha Public Power District (0 PPD)

1623 Harney Street

Omaha, Nebraska 68102

Facility Name:

Fort Calhoun Station (FCS)

Inspection At:

FCS, Blair, Nebraska

Inspection Conducted: April 6 - May 13, 1988

Inspectors:

.

d

$[1[N

'

'

P. H. Harrell, Senior Resident Reactor

Date

Inspector

bflfff

'

-

.

T. Reis, Resident Reactor Inspector

Date

A

Approved:

6[

T. F. Westerman, Chief, Reactor project

Date

Section B

Inspection Summary

Inspection Conducted April 6-27, 1988 (Report 50-285/88-15)

Areas Inspected:

Routine, unannounced inspection incicding followup on the

status of the instrument air accumulator assemblies and followup on an onsite

event.

Results: Within the two areas inspected, two potential violations (failure to

meet the established design criteria for the instrument air system,

paragraph 3; and the apparent failure to maintain containment integrity,

paragraph 4) were identified.

8806130065 880601

ADOCK0500g5

PDR

0

, , , - ,

. ,

.. .

..-

- , _ . . _ .

.__-.

,- .-_ - .

. - . - - ..

. _ . _ _ -

._______- _____.

'

-,

,,

'

. .

,

.

.

'

,

DETAILS

1.

Persons Contacted

  • R. Andrews, Division Manager, Nuclear Production
  • W. Gates, Plant Manager
  • M. Core, Supervisor, Maintenance
  • J. Fisicaro, Supervisor, Nuclear Regulatory and Industry Affairs
  • J. Gasper, Manager, Administrative and Training Services
  • R. Jaworski, Section Manager, Technical Services
  • R. Kellog, Acting Manager, Technical Support
  • T. Patterson, Supervisor, Technical
  • S. Swearngin, System Engineer, Instrument Air System
  • C. Simmons, Plant Licensing Engineer
  • S. Trausch, Supervisor, Operations

[

  • K. Morris, Division Manager, Quality Assurance and Regulatory Affairs

p

  • J. O'Connor, Plant Engineer

l

  • A. Richard, Manager, Quality Assurance

l

  • R. Scofield, Supervisor, Outage Projects
  • Denotes attendance at the monthly exit interview.

The NRC inspector also contacted other plant personnel, including

operators, technicians, and administrative personnel.

2.

Plant Status

The reactor was operating at 100 percent power during this inspection

period. The next refueling outage is sched;1ed for September 1988.

3.

Followup'on the Status of the Instrument Air Accumulator Assemblies

This inspection was performed to follow-up on licensee activities for

testing of accumulator assemblies for air-operated, safety-related valves.

This inspection was focused to review the status of the accumulator

assemblies for valves required to function by changing position during

various design basis accidents (e.g., locs-of-coolant accident, seismic

event, er steam generator tube rupture) that require plant shutdown.

Each accumulator assembly is comprised of a check valve, accumulator,

valve operator, and interconnecting tubing.

The valve operator is

normally repositioned by using air pressure from the instrument air

system.

The instrument air system is a nonseismically installed system

supplied by three nonvital air compressors.

The accumulator assemblies

were designed and installed to provide an air pressure storage system to

reposition the valves in the event the normal air supply is lost. The

accumulator assemblies are safety grade installations designed to fulfill

their intended safety function following a design basis accident (DBA).

In the recent past, NRC inspectors have reviewed the installation of the

accumulator assemblies to verify that the assemblies were designed and

installed in accordance with the appropriate regulatory requirements.

l

l

-

.

_

=_-

_ ______._________- - __ ______ - ___________-_ _ _

-

.

.

..

'

.

, .

.,

.

.

2

-

.

Each of the inspections and reviews performed by NRC personnel is

discussed below:

a.

-During a safety system outage modification inspection (SSOMI)

performed by NRC Headquarters personnel in September and October

1985, the SS0MI team ,dentified an apparent deficiency related to the

accumulator assemblies for the component cooling water supply to the

reactor coolant pump containment isolation valves, HCV-4388 and

HCV-4380. The details of the deficiency are documented as

Deficiency 2.2-1 in NRC Inspection Report 50-285/85-22, issued on

January 21, 1986.

The deficiency noted that the licensee had altered the hardware

installation so Valves HCV-438B and HCV-438D were changed from a fail

closed to a fail open mode.

Because the "failed" position was

changed, the licensee relied on the air pressure in the accumulator

assembly to shut the valves in the event containment isolation was

required. The SSOMI team noted that the calculation associated with

Modification MR-FC-81-218, the design document that changed HCV-438B

and HCV-4380 frcm fail closed to fail open valves, assumed zero

leakage from the accumulator assen;bly, and therefore concluded that

the size of the accumulator was sufficient to hold HCV-438B and

HCV-438D shut until an operations individual could manually shut the

valves. The SSOMI team disagreed with the no-leakage assumption made

in the calculation because the licensee had not performed any testing

to determine the actual leakage from the accumulator assembly.

On April 15, 1986, the licensee provided a response to

Deficiency 2.2-1.

The response stated that, "although the system

leakage was not quantified in the original calculation, the amount of

allowable leakage can be inferred from the margin between the minimum

pressure required and the system pressure following actuation of the

,

!

valve. The amount of margin in the original calculation was such

that system leakage was a moot point.

The revised preliminary

calculation, using the correct parameters, indicates that the margin

is approximately 40 percent." The response also stated that a new

revised calculation would be completed and placed in the file.

On August 7, 1986, a working meeting was held in the Region IV

offices between the NRC and the licensee. At this meeting, the

l

correutive action programs provided by the licensee in the response

dated April 15, 1986, were discussed and it was determined that the

response to Deficiency 2.2-1 was inadequate. As a result of the

,

l

discussions, the licensee agreed to submit a revised response to the

l

deficiency.

i

On April 10, 1987, the licensee submitted a revised response.

The

revised response stated that the licensee had initiated a program to

l

l

l

l

u

.

..

'.

'

l

l

3

l

..

,

provide comprehensive evaluation of systems which depend on

accumulator assemblies for proper functioning during an accident

event. The revised response stated that the program would include

the following elements.

Identify CQE (safety-related) valve operators that are equipped

.

with air accumulators.

Determine the operating criteria of the valve during each

.

applicable postulated accident.

This will include parameters

such as operating pressure and temperature, time duration after

-

an initiating event when valve operation will commence, and the

length of time that the valve operator must function.

Develop criteria for functional testing each valve operator

.

which was identified according to the above criteria.

Develop appropriate surveillance testing to ensure that tne

.

systems continue to function as required.

The revised response stated that at the comp'.etion of the evaluation

described above, a systematic program would be initiated to perform

testing of the installed accumulator assemblies to verify that the

equipment could reliably perform the required accident function. The

revised response also noted that a schedule for completing air

accumulator testing would be provided by August 1987.

On December 23, 1987, the licensee submitted an update of the

previous response for the items identified by the SS0MI team.

In

this updated response, the licensee stated that because of the

unforeseen requirement to perform more extensive evaluations with

respect to the corrective actions, the date for providing the

schedule for completing air accumulator testing has been extended to

July 1988.

Consequently, at the time of this inspection, the

licensee still has yet to submit a schedule for testing the

accumulators.

This item remains open pending submission of the

required schedule as committed by the licensee in its April 10, 1987,

revised response.

(285/8815-01)

Also, in response to Deficiency 2.2-1 identified by the SSOMI team,

'

the licensee issued Operations Support Analysis Report (OSliR) 87-10

dated April 6, 1988, to determine the following:

The valves serviced by an accumulator assembly that are

.

essential to ensure a safe plant shutdown or to mitigate the

consequences of a DBA coincident with the loss of offsite power.

Describe the function of the essential valves and accumulator

.

assembly following a DBA.

_

._

!

.*

.

..

,

,

4

,

-

4

j

.

Evaluate the need to reposition the essential valves following a

.

DBA.

Determine the postaccident oper iting conditions for the

.

essential valves and ensure tnat the conditions are within the

design basis for the facility.

Establish the maximum time interval the essential valves' must be

.

repositioned and/or the number of times the essential valves

require recycling.

Develop criteria for functionally testing the essential valves

.

to verify the valves will perform their intended safety

function.

Based on the results of OSAR 87-10, the l'censee determined that

various actions would be required to ensure that essential valves

would comply witn their design basis and would be able to perform

their intended safety function. A detailed discussion of the status

of each essential valve is provided later in this inspe +tsn report.

b.

On September 26, 1983, the licensee submitted a 10 year inservice

inspection (ISI) plan for the period of 1983 to 1993. Based'on

concerns identified by NRC personnel in the licensee's submittal, an

onsite meeting was held in October 1987 to resolve the concerns. One

of the areas of concern involved the licensee's inservice

testing (IST) program for the check valves installed in accumulator

assemblies. At tne meeting, the licensee agreed to submit a revision

to the IST program to include the accumulator check valves and on

December 16, 1987, the IST program revision was submitted by the

licensee for NRC review and approval.

This revision has not yet been

approved by the NRC.

Subsequent to the submission of the revised IST program, the licansee

determined, based on the results of the analysis performed by

OSAR 87-10, that additional accumulator check valves should be

included in the IST program.

However, the licensee has not yet

submitted a proposed revision to include the newly identified check

valves in the IST program.

The licensee stated that a new revision

would be made prior to the end of the 1938 refueling outags. This

item remains open pending a submission of a revised program by the

licensee and review and approval by the NRC.

(285/8815-02)

A detailed discussion is provided later in this inspection report

that identifies the valves that have been included in the IST program

and also identifies which valves need to be included in the program.

c.

On July 6,1987, the licensee experienced an event where water from

the fire water system entered the instrument air system. As a result

,

.

.

_

. . .

. . -

-

. .

,

5

-

.

of this event, Emergency Diesel Generator 2 failed to start on demand

during the performance of a surveillance test on September 23, 1987.

The details of the event are provided in NRC Inspection

Report 50-285/87-27.

As a result of the followup inspections performed by NRC inspectors

on the water intrusion event, a Notice of Violation and Proposed

Imposition of Civil Penalty was issued on February 22, 1988.

Subsequent to the issuance of the Notice, a meeting was held at the

NRC Headquarters Office on November 13, 1987. At the enforcement

conference, the licensee made numerous commitments to address the

concerns identified by the NRC inspectors. One concern addressed by

the licensee was the testing of the check valves installed in

accumulator assemblies.

The commitments made by the licensee during

the enforcement conference for testing of check valves were submitted

to the NRC in a letter dated November 20, 1987.

In the letter, the

licensee stated that the accumulator check valves would be tested and

that the IST program would be revised to ensure periodic testing of

the check valves in the future (the status of the IST program was

discussed in paragraph 2.b above and the status of the testing of the

check valves is discussed later in this inspection report. The

status provides a detailed description of which valves have been

tested and the results of the testing).

In addition to the testing of the accumulator check valves, the NRC

identified concerns related to the seismic installation of the

accumulator assembly components that include the accumulator, tubing,

valve operator, and check valve.

In response to this concern, the

licensee submitted a letter, dated November 20, 1987, that provided

the seismic calculations completed by the licensee.

The NRC is

currently reviewing the calculations submitted by the licensee to

verify the adequacy of the calculations (the status of the seismic

qualification for each valve accumulator assembly is provided in a

detailed discussion later in this inspection report).

This item

remains open pending a review of the seismic calculations by NRC

personnel.

(285/8815-03)

The licensee submitted a response to the notice of violation and

proposed imposition of civil penalty, dated April 27, 1988, to the

violations identified in NRC Inspection Report 50-285/87-27.

(At the

time this inspqction was concluded, the response was under review by

the NRC Region IV office.)

l

d.

On April 18, 1988, the licensee issued a Safety Analysis for

l

Operability (SA0).

The licensee issued the SA0 to address conditions

related to specific essential valves for verification that the plant

l

could continue to operate safely. The SA0 issued on April 18, 1988,

was a revision to previous SA0s that had been issued by the licensee.

,

'

The revised SA0 considered all data related to the operability of

l

essential valves that was available at the time, and applies to the

!

valves discussed below.

l

. - .

,

tj;

,

..

.

.

.

,

.

6

.

.

A detailed discussion of the status of each accumulator assembly

installed with essential valves is provided below. The discussion

for each valve includes: (a) a description of the valve and the

function of the accumulator assembly, (b) actions performed to verify

accumulator size, (c) function testing performed on the accumulator

assembly, (d) IST program status for the accumulator assembly check

valve, and (e) seismic qualification status of the accumulator

assembly.

For each essential valve discussed below, a review was performed to

verify that the currently existing conditions did not require entry

into a limiting condition for operability (LCO) as defined by the

Technical Specifications (TS).

This review was performed based on

the current information available with respect to the present status

of each essential valve. Based on this review, it appeared that none

of the conditions of the essential valves described below require

entry into an LCO.

(1) Safety injection and refueling water tank (SIRWT) level control

bubblers (A/FIC-383, B/FIC-383, C/FIC-383, D/FIC-383)

(a) These bubblers are used to detect the level in the SIRWT.

In the event of a loss-of-coolant accident (LOCA) and

safety injection is initiated, the safety-injection pumps

will transfer water from the SIRWT into the react e coolant

system. When the level in the SIRWT reaches approXmately

16 inches, as detected by the level bubblers. a

recirculation actuation signal (RAS) is initiated.

.\\ RAS

will shut the SIRWT outlet valves, open the containmect

sump isolation valves, shut the safety injection and

containment spray pumps recirculation valve to the SIRWT,

and stop the low pressure safety-injection (LPSI) pumps.

The purpose of the RAS is to switch suction of the

high pressure safety-injection (HPSI) and containment spray

(CS) from the SIRWT to the containment sump.

If air system

pressure is lost to the bubblers, the accumulator

assemblies maintain pressure for bubbler operation to

prevent premature initiation of a RAS.

(b) A preliminary calculation has been completed by the

licensee to verify that the accumulators are of sufficient

size to provide a backup source of air pressure in the

event the normal instrument air pressure is lost.

The

results of the preliminary calculation indicate that the

accumulator size is adequate and the licensee is in the

process of issuing a formal calculation to verify the size

of the accumulators is adequate.

This item remains

unresolved pending the issuance of a formal calculation by

the licensee and a review of the calculation by the NRC.

l

(285/8515-04)

lc

.

-

___ _. _ _..

.

,

..

.

.

.

7

.

.

(c) A functional test of the accumulator assembly was performed

in April 1988 to verify that the check valves would

maintain sufficient pressure in the accumulator for a

period of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to ensure proper operation of the

bubblers.

The 12-hour operational period for the

accumulators was established by the analysis done in

OSAR 87-10. When the installed check valves were tested,

the licensee determined that the check valves would not

maintain accumulator pressure for the required 12-hour

period. Upon discovery of the inadequacy of the installed

check valves, the licensee replaced the check valves with

new check valves that had been bench tested and verified to

have zero leakage.

The April 18, 1988, SA0 addressed the

operability of the SIRWT level detectors. The evaluation

concluded.that the detectors were operational based on the

fact that the installed check valves had been replaced with

new check valves and that the prelimina y calculation

inaicated that the accumulators were properly sized. Based

on the conclusions contained in the SAO, the licensee

stated that no action was required at that time. However, a

test to verify that the accumulator assembly will function

for a period of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> has not been performed by the

licensee for any of the SIRWT level detectors. The

licensee stated that the functional test would be completed

during the 1988 r efueling outage. This item remains open

pending a satisfactory functional test to verify the

accumulator assembly will provide a 12-hour supply of air

pressure to the bubblers.

(285/8815-05)

The significance of this issue is that when the licensee

tested the originally installed check valves, it was

determined that the check valves leaked excessively.

The

check valves had not been previously tested.

Based on the

results of the tests, it appeared that the accumulator

assemblies could not perform their intended safety function

in the event that a LOCA occurred in conjunction with the

loss of instrument air pressure.

The worst case scenario

would occur if two or more level detectors lost air

pressure, causing a premature initiation of a RAS.

If a

premature initiation of RAS was initiated, the suction of

the HPSI and CS pumps would be switched from the SIRWT to

,

!

the containment sump.

If the sump did not contain

sufficient water to provide adequate flow through the

pumps, the HPSI pumps would self-destruct due to

overheating.

The loss of the HPSI and CS pumps would

significantly impact the ability to maintain sufficient

core cooling flow to prevent gross fuel damage.

The loss

l

of the CS pumps would impact the ability to lower the

l

containment pressure during a post-LOCA event.

l

I

l

l

l

.--

_

-.

_

.-

,

..

'

a

,

.

8

-

Section 9.12.5 of the Updated Safety Analysis Report (USAR)

establishes the design criteria for the performance of the

SIRWT bubblers and provides an evaluation of the

established design.

Section 9.12.5 of the USAR states, in

cart, that the level controller in the SIRWT requires a

supply of air to function properly. These cortrollers are

required to transfer the suction of the HPSI and CS pumps

to the containment sump after the water supply in the SIRWT

reaches the low-level setpoint.

To make these instruments

independent of the instrument air system during the

accident, each is equipped with an air storage tank which

tioats on the instrument air system.

If the pressure'in

the instrument air system drops, a check valve in the line

to the air storage tank closes which isolates the tank from

the system and prcvides a supply of air to the controller .

,

However, in this case, the accumulator assemblies for the

SIRWT level controllers fe'1ed to meet the established

design criteria in that testing performed on the

accumulator assembly check valves indicated that the valve

leaked excessively and would not perform its intended

design function.

This is one example of a potential

violation of the failure to meet plant design criteria

(285/8815-06).

(This condition was identified and reported

to the NRC as 10 CFR 50.72 report on April 15,1988.)

The NRC inspectors consider this matter potentially

significant, even though the probability of experiencing a

LOCA concurrent with the loss of instrument air is

extremely. low. Systems and components must be installed

and maintained to ensure that they can continue to fulfill

the established design criteria.

(d) The check valves associated with the SIRWT bubbler

accumulators were included in the revised IST program

submitted by the licensee on December 16, 1987.

Inclusion

of these check valves in the IST program will ensure that

the valves are verified to be functional each quarter.

(e) The licensee performed a calculation to verify that the

accumula,or assembly was seismically qualified. The

licensee submitted the calculation to the NRC for review on

November 10, 1987.

(2) Component cooling water to the reactor coolant pumps'

containment isolation valves (HCV-438B and HCV-4380)

(a) Valves HCV-4388 and HCV-4380 are designed to shut to

isolate containment in tha event containment isolation is

required in conjunction with a loss of pressure in the

component-cooling water (CCW) system.

Valves HCV-438B and

-

.

.

'

>

..

,

.-

.

.

,

.

9

.

HCV-4380 fail open on a loss of air pressure and rely on

taeir individual accumulator assemblies to hold the valve

shut, if required, when containment isolation is required.

(b) In response to a deficiency identified by the SSOMI team,

the licensee performed a calculation to verify that the

accumulator was properly sized to perform its intended

safety function.

The SSOMI team subsequently reviewed the

calculation performed by the licensee and determined that

'

the calculation was not adequate to establish that the

accumulator was sufficiently sized.

Based on this rev'ew,

the licensee performed an SA0 to verify that the plant

could continue to operate safely.

The results of the SAO concluded that the valves, as

currently installed, do not represent a significant

degradation of plant safety. The basis for this conclusion

was that the pressure in the CCW system would always be

greater than containment pressure during a LOCA.

If CCW

system pressure is lost concurrent with a LOCA,

Valves HCV-438B and HCV-4380 would be held shut by the

accumulator assemblies for 30 minutes.

(The valves were

tested during the 198/ outage and verified to be operable

for 30 minutes.) When CCW system pressure is lost, the raw

water (RW) system, the backup cooling water source for CCW,

will automatically initiate to provide cooling to the

components normally supplied by the CCW system.

However, in the event of a CCW line break inside

containment Valves HCV-4388 and HCV-4380 would shut for

30 minutes, as verified by the licensee's tests, and would

then potentially reoper due to the unverified adequacy of

the accumulator assembifes.

Further, if a line break

occurred, the valves car.not be manually shut due to the

high radiation levels at the valve location during a LOCA.

If Valves HCV-4388 and HCV-4380 reopened, RW would be

pumped into containment, causing the boric acid solution in

the containment sump to become diluted. The diluted boric

acid solution could potentially cause the reactor to become

critical when pumped into the vessel by HPSI pumps

When questioned by the NRC inspectors, the licensee stated

that the original design basis for the plant did not

require that an analysis be performed for a LOCA concurrent

with a CCW line rupture in containment. This matter will

be discussed with NRR to verify that such an analysis is

not required.

Therefore, this item remains unresolved

(285/8815-07).

(This condition was identified and reported

by the licensee as a 10 CFR 50.72 report on April 6, 1988.)

.--

- . . - . . _ .

_.,

_

l

-

,

,,

.

.

10

-

(c) During the 1987 refueling outage, the accumulator

assemblies for Valves HCV-4388 and HCV-438D were

functionally tested and verified to be operable for

30 minutes.

Subsequent to the testing, the licensee

established, during preparation of OSAR 87-10, that the

design criteria for the accumulators required that

Valves HCV-4388 and HCV-438D be held shut for a period of

1000 hours0.0116 days <br />0.278 hours <br />0.00165 weeks <br />3.805e-4 months <br />.

The licensee could not verify that the

accumulator assemblies could meet this new design criteria,

so an SA0 was issued. The discussion provided above

references the results of the SA0 evaluation, and the NRC

inspector's concerns.

(d) The check valves associated with Valves HCV-438B and

.

HCV-438D were not included in the revised IST program

submitted by the licensee on December 16, 1987.

These

check valves will be included in a revision to the IST

program which the licensee stated will be completed prior

to the end of the 1988 refueling outage.

(e) The licensee performed a calculation to verify that the

accumulator assembly was seismically qualified.

The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

(3) Loop injection valves from the discharge of the charging pumps

(HCV-238 and HCV-239)

(a) Valves HCV-238 and HCV-239 are normally open valves that

provide a path for continuous makeup water flow from the

volume control tank to the reactor coolant system via the

charging pumps.

The valves are required to be shut in the

event a LOCA occurs and hot-leg injection is required. The

valves are shut to divert flow from the charging pump

through the pressurizer auxiliary spray line. The valves

fail open on a loss of air pressure and are required to be

held in the shut position by the accumulators in the event

hot-leg injection is initiated.

(b) The licensee has not performed any calculations to verify

that the accumulators are properly sized to perform their

intended safety function.

An SA0 has been issued to

address the indeterminate status of the size of the

accumulators. A discussion of the SA0 is provided below.

(c) The licensee performed functional testing of the

accumulator assemblies during the 1987 refueling outage.

The test performed by the licensee verified that the

accumulator assemblies would perform their design functions

for a period of 25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br />.

However, during the preparation

of OSAR 87-10, the licensee established a design criteria

. - - - - - - - -

-

- . -

-

-

,- - ,

. - ,

--

_ _ _ .

_

'

v

..

<

.

11

that required the accumulator assemblies to operate

indefinitely. Based on the newly established criteria, the

licensee determined that the accumulator assemblies could

not be considered operable.

(This condition was identified

and reported by the licensee as a 10 CFR 50.72 report on

April 6, 1988.)

The licensee issued an SA0 to address the inoperability of

Valves HCV-238 and HCV-239. The conclusions of the SA0

indicate that Valves HCV-238 and HCV-239 cannot-meet the

established design basis. Therefore, the licensee has

established an alternate means of establishing hot-leg

injection by using the path through SI-186, HCV-347, and

HCV-348.

Valve SI-186 is a normally closed, locked manual

valve.

Valves HCV-347 and HCV-348 are motor-operated

valves. The licensee has established interim measures to

ensure that hot-leg injection is established as soon as a

LOCA occurs by having the auxiliary. building operator open

Valve SI-186. An operations memorandum was issued to

instruct the operator to open Valve SI-186 as soon as

possible because the valve is inaccessible in a post-LOCA

situation due to high radiation levels.

(d) The check valves associated with tho accumulator assemblies

were included in the revised IST program submitted by the

licensee on December 16, 1987.

In the revised IST program,

the licensee proposed that the check valves would be tested

quarterly.

However, the check valves are located inside

the bioshield inside containment, so it is not apparent how

the licensee intends to test the check valves quarterly

when the plant is at 100 percent power.

This item remains

-open pending a review of this apparent discrepancy in the

licensee's IST program submittal.

(285/8815-08)

(e) The licensee has not performed calculations to verify the

accumulator assemblies are seismically qualified.

For this

reason, an SA0 was issued, as described above, to address

the inoperability of the valves. The licensee stated that

calculations would be performed during the next refueling

outage to seismically cualify the accumulator assemblies.

This item remains onc., pending completion of the

calculations and a review of the calculations by the NRC,

(285/8815-09)

(4) Auxiliary spray isolation valve (HCV-240)

(a) Valve HCV-240 is used to provide a hot-leg injection path

into the reactor coolant system via the auxiliary spray

line for the pressurizer.

Valve HCV-240 is normally shut

5

. .

..

..s

12

and fails shut on the loss of air pressure.

The

accumulator assembly was installed to hold the valve open

during hot-leg injection.

(This condition was identified

and reported as a 50.72 report on April 6,1988.)

(b) The licensee has not performed a calculation to verify that

the size of the accumulator is. adequate.

For this reason,

the licensee issued an SA0 to address the inoperability of

the valve. A discussion of the SA0 is provided below.

(c) The licensee performed functional testing of the

accumulator assembly during the 1987 refueling outage and

verified the accumulator assembly would function for a

period of 25 hcurs. However, during the preparation of

OSAR 87-10, the licensee established a design criteria that

required the accumulator assembly to operate indefinitely.

Based on the newly established criteria, Valve HCV-240 was

declared inoperable. The licensee issued an SA0 to address

the inoperability of the valve. The conclusions of the SA0

are the same as those discussed above for Valves HCV-23P

and HCV-239.

In addition to the conclusions made by the

SA0 for HCV-238 and HCV-239, a solenoid-operated valve,

HCV-249, is installed in parallel with Valve HCV-240.

Valve HCV-249 can be used to provide hot-leg injection.

(This condition was identified and reported as a 50.72

report on April 6, 1988.)

(d) The check valve associated with the accumulator assembly

was included in the revised IST program submitted by the

licensee on December 16, 1987.

Inclusion of the check

valve in the IST program will ensure that the valve is

i

verified to be functional each time the plant is placed in

the cold shutdown mode.

(e) The licensee has not performed a calculation to verify that

the accumulator assembly was seismically qua~ified.

The

accumulator assembly was seismically qualified based on

'

engineering judgement.

The licensee stated that a

calculation would be performed during the next refueling

outage to verify that the accumulator assembly is

seismically installed.

This item remains open pendin0 the

preparation of a seismic calculation for the accumulator

assembly and a review of the calculation by the NRC.

(285/8815-10)

(5) SIRWT cutlet valves (LCV-383-1 and LCV-383-2)

(a) Valves LCV-383-1 and LCV-383-2 are used to isolate the

SIRWT from the safety-injection and containment spray pumps

suction header when pump suction is switched from the SIRWT

to the containment sump upon receipt of a RAS. These

, , . - -

__ ,__

_

._

. . '

,

s

-

.

,

13

valves shut to minimize the possibility of contaminated

'

water in the containment sump from entering the SIRWT.

The

valves fail open on a loss of air pressure and are held

shut by the-accumulator assemblies.

s .

(b) The licensee has not performed a calculation to verify that

the accumulator size is adequate to operate

Valves LCV-383-1 and LCV-383-2.

In this case, both valves

share a common accumulator.

Section 6.2.5 of the USAR states, in part, th:t the

safety-injection system has been designed to meet the

single-failure critarion. However, the accumulator

assembly for Valves LCV-383-1 and LCV-383-2 does not meet

the single failure criterion'in that one accumulator

supplies backup air pressure for both valves. This is

another example of a potential violation of the failure to

install a component that complies with the established

design criteria.

(285/8815-06)

The NRC inspectors noted that the licensee identified the

need to install an additional accumulator during the

preparation of OSAR 87-10, and that the licensee is

currently planning to install the additional accumulator in

the near future.

(c) The licensee did not functionally test the accumulator

assembly for Valves LCV-383-1 and LCV-383-2. Although the

licensee had not previously established a duration criteria

for accumulator assembly operation during the preparation

of OSAR 87-10, the licensee determined that the design

criteria for the accumulator assembly was to hold

Valves LCV-383-1 and LCV-383-2 shut for a period of

1000 hours0.0116 days <br />0.278 hours <br />0.00165 weeks <br />3.805e-4 months <br />. When the licensee determined that design

criteria, a modification was installed to provide a

nitrogen supply system to the valve operators to supplement

the accumulator assembly.

When the nitrogen system was installed, new check valves

that had been bench tested and verified to have zero

leakage were installed in the accumulator assembly.

The

nitrogen bottles were located within the plant such that

the bottles would be accessible during a LOCA.

By placing

the bottles in this location, operations personnel could

always replace depleted bottles to ensure that a continuous

source of pressure is available to hold Valves LCV-383-1

and LCV-383-2 shut for 1000 hours0.0116 days <br />0.278 hours <br />0.00165 weeks <br />3.805e-4 months <br />.

By installing the nitrogen supply system, the licensee had

established a method for ensuring that Valves LCV-383-1 and

LCV-383-2 met the newly established design criteria.

(This

..

.

t

.

.>.

'

. .

j

14

-

LCV-383-2 met the newly established design criteria.

(This

7-

condition was identified and reported as 10 CFR 50.72

report on April 6, 1988.)

(d) The check valves associated with the accumulator assembly

were included in the revised IST program submitted by the

licensee on D.cember 16, 1987.

Inclusion of these check

valves in the IST program will ensure that the valves are

verified to be functional each quarter.

(e) The licensee performed a calculation to verify that the

accumulator assembly was seismically qualified. The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

(6) Safety-injection and containment spray pumps' recirculation

isalation valves to the SIRWT (HCV-385 and HCV-386)

(a) Valves HCV-385 and HCV-386 are normally open to allow water

being pumped by the safety-injection and containment spray

pumps to recirculate back to the SIRWT to prevent

deadheading the pumps. When a RAS is generated, the valves

shut to prevent the contaminated water in the containment

sump from being pumped into the SIRWT.

The accumulator

assemblies installed on these valves are intended to hold

the valves shut during the containment recirculation mode

of operation of the safety-injection system.

(b)

In response to Deficiency 2.2-1 identified by the SSOMI

team, the licensee evaluated the accumulator installation

for Valves HCV-344 and 345.

During the evaluation, the

-

licensee noted that both valves shared a common

accumulator.

Because the installation did not meet the

design requirement to satisfy the single-failure criteria,

another accumulator was installed.

The modification

provided one accumulator for each valve. After the

modification was completed, the licensee performed a

calculation to verify the size of the accumulators for the

valves was adequate. The csiculation verified that

sufficient accumulator capacity existed.

(The modification

completed by the licensee is detailed in Licensee Event

Report (LER)87-018, dated August 28,1987.)

(c) A functional test was performed on the accumulator

.

assemblies during the 1987 refueling outage.

The test

verified that the accumulator assemblies would function for

'

a period of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

However, during the preparation of

OSAR 87-10, the licensee established that the accumulator

assemblies are required to maintain prersure for a period

of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, then shut the valves and hold them shut for a

period of one hour.

The one hour period was established to

allow the auxiliary building operator sufficient time to

-

( ~,

.

.

,

15

manually shut the valves.

To ensure that operations

personnel are aware of the need to shut the valves, a

change was-made to Procedure E0P-20, "Functional Recovery

Procedure." This change directs operations personnel to

shut the valve as soon as a RAS is initiated.

By manually

shutting t.he valve, the licensee meets the design criteria

that states the valves must be held shut for a period of

1000 hours0.0116 days <br />0.278 hours <br />0.00165 weeks <br />3.805e-4 months <br /> following the initiation of a RAS.

(d) The check valves associated with the accumulator assemblies

were included in the revised IST program submitted by the

licensee on December 16, 1987.

Inclusion of these check

valves in the IST program will ensure that the valves are

verified to be functional each quarter.

(e) The licensee performed a calculation to verify that the

accumulator assembly was seismically qualified. The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

(7) Radiator exhaust dampers for the emergency diesel generators

(YCV-871E and YCV-871F)

(a) Dampers YCV-871E and YCV-871F are normally shut to prevent

outside air from entering the emergency diesel generator

(EDG) rooms. When the EDGs are started and reach 100 rpm,

"

the air-operated motors open the dampers to provide air

flow across the radiator.

The air flow provides cooling

for the EDGs. Once the dampers are open, they will remain

open without the presence of air pressure. On a loss of

air pressure, the dampers will remain in the normally

closed position. The accumulator assemblies were installed

to provide a backup source of air pressure to ensure that

the dampers are opened when the EDGs are started.

If the

dampers did not open, the EDGs would overheat and could

potentially cause damage to the engines.

(b) The accumulators were supplied by the manufacturer of the

air-operated motors and were sized by the manufacturer to

ensure that a sufficient volume of air was available to

l

operate the motors.

The licensee has performed a

calculation to verify that the accumulator size is adequate

to open the dampers.

(

(c) Repairs and a functional test of the accumulator assemblies

was performed by the licensee when a damper failed to open

l

during a routine surveillance test performed on September

j

23, 1987. The subsequent functional test indicated that

the accumulator assemblies were capable of performing their

l

l

l

l

l

7

$.

' .>

,

,

,

16

intended design function.

(The failure of the damper to

open was previously reported in LER 87-25, dated

November 30, 1987.)

(d) The check valves associated with the accumulater assemblies

were in-luded in the revised IST program submitted by the

licensee on December 16, 1987.

Inclusion of these check

valves in the IST program will ensure that the valves are

verified to be functional each quarter.

(e) The licensee performed a calculation to verify : hat the

accumulator assembly was seismically qualified. The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

(8) HPSI header isolation valve used for initiation of long-term

core cooling (HCV-2987)

(a) Valve HCV-2987 is used to divert a portion of HPSI flow

from the cold leg, when the valve is open, to the charging

pump header for hot-leg injection, when the valve is shut.

The valve is normally open and will fail as-is on a loss of

air pressure. Air pressure is required to open and to shut

,

the valve.

The opening and shutting of the valve is

accomplished by the use of an air accumulator.

(b) A calculation to verify the size of the accumulator has not

been performed. The accumulator was supplied by the valve

manufacturer and was specifically designed for use with

this valve type.

(c) Functional testing of the accumulator assembly has not been

performed. During performance of a test to verify

accumulator assembly adequacy, the licensee identified a

problem with the air intensifier installed in the

accumulator assembly. The air intansifier is a mechanism

that boosts the instrument air pressure from approximately

90 psig to 300 psig for valve operation. Since no spare

parts were available to repair the intensifier, the

licensee disconnected the instrument air supply line to the

accumulator assembly and connected a temporary nitrogen

supply system. The nitrogen system supplies the 300 psig

motive force to the valve actuator. This temporary

modification will ensure that the valve can perform its

intended safety function. During the next refueling

outage, the licensee intends to return the valve to its

normal configuration and perform tests to verify valve

operability (the details of the problems with HCV-2987 and

the actions taken by the licensee are provided in LER

88-002, dated February 5, 1988.)

o

,

,

-

.

17

(d) The check valve associated with the accumulator assembly

was included in the revised IST program submitted by the

licensee on December 16, 1987.

Inclusion of the check

,

valve in the IST program will ensure that the valve is

verified to be functional each time the plant is placed in

e cold shutdown mode.

(c) TFe licensee performed a calculation to verify that the

accumulator assembly was seismically qualified.

The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

(9) HPSI heac'er isolation valves (HCV-304, HCV-305, HCV-306, and

HCV-307)

(a) These valves are used to establish hot-leg injection flow

to the reactor coolant system (RCS).

By shutting or

throttling the valves, flow is diverted into the RCS

hot-leg.

The valves are normally open ard require air

pressure for operation.

On a loss ofJair pressure, the

accurrulator assembly will open the valve, if the valve is

shut. Once the valve is open, the position cannot be

changed by the accumulator assembly.

These valves are not

accessible for manual operation during a LOCA due to the

high radiation levels.

When aeviewing the status of the accumulator asserblies for

these valves, the licensee identified that, in the current

design configuration, the valves cannot be shut by the

accumulator assemblies once air system pressure is lost.

Without the capability to shut the valves, no assurance can

be provided that the proper amount of hot-leg injection

flow can be obtained. The valves are required to be shut

only if one diesel generator fails to operate or,1f one

loop motor-operated injection valve fails to shut.

(Details of this matter are provided in OSAR 87-10.)

The nuclear steam supplier, Combustion Engineering,

recommended in 1978 that the licensee provide a remote

manual means of operation for the valves to ensure that the

valves can be operateci, if required.

However, these

modifications have not been pursued by the licensee. The

licensee is now in the process of obtaining an evaluation

from Combustion Engineering to determine whether or not

hot-leg injection can be achieved with the currently

installed system configuration. This item remains

unresolved pending the completion of the evaluation by

Combustion Engineering and the completion of licensee

actions identified in the evaluation.

(285/8815-11)

i

.

J

L

- , _ _

_

_

_

..

,-t

,

8 '

.

,

18

(b) A calculation to verify that the accumulator has sufficient

capacity has not been performed by the licensee.

However,

a functional test has been successfully performed, and

based on the results of the test, the licensee stated that

the accumulators could perform their intended safety

function.

(c) The licensee performed a functional test of the accumulator

assemblies during the 1987 refueling-outage to verify that

the assemblies operated properly.

The test confirmed that

the assemblies were fully operable.

(d) The check valves associated with the accumulator assemblies

were included in the revised IST program submitted by the

licensee on December 16,_1987.

Inclusion of these check

valves in the IST program will ensure that the valves are

verified to be functional each time the plant is placed in

the cold shutdown mode.

(e) The licensee performed a calculation to verify that each

'

accumulator assembly was seismically qualified.

The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

j

(

eupply valves to the turbine-driven auxiliary feedwater

l

u.., s.CV-1045A and YCV-10458)

(a) Valves YCV-1045A and YCV-1045B are installed to provide

steam to the turbine-driven auxiliary feedwater pump from

Steam Generators A and B, respectively.

The valves are

normally shut and fail open on a loss of air pressure.

The

'

accumulator assemblies were installed to shut the valves in

the event of a loss of air pressure concurrent with a steam

generator tube rupture to prevent the release of

radioactive material to the environment.

(b) The licensee performed a calculation on accumulator sizing

in response to a deficiency identified by the SS0MI team.

The calculation indicated that the accumulator sizing was

adequate.

Subsequent to the performance of the

calculation, the SSOMI team reviewed the results and

determined that the calculation was inadequate.

The

licensee revised the calculation to incorporate the

comments noted by the SSOMI team.

Currently, the

accumulators are considered to be adequately sized to

perform their intended safety function.

(c) Functional testing of the accumulator assemblies was

performed during the 1985 refueling outage. During this

testing, the licensee determined that the accumulator

assemblies could hold Valves HCV-1045A and HCV-1045B shut

'

.

'

-

..

19

for 30 minutes. The design criteria states that the valves

should be held shut indefinitely.

To ensure the valves

stay shut, the licensee has provided instructions in

E0P-04, "Steam Generator Tube Rupture," to direct

operations personnel to manually shut the valve within

30 minutes of the initiation of a steam generator tube

rupture.

(d) The check valves associated with the accumulator assemblies

were included in the revised IST program' submitted by the

licensee on December 16, 1987.

Inclusion of these check

valves in the IST program will ensure that the valves are

verified to be functional each quarter.

(e) The licensee performed a calculation to verify that the

accumulator assembly was seismically qualified.

The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

(11) CCW isolation valves to the containment air cooling and

filtering units (HCV-400A, B, C, and 0; HCV-401A, B, C, and D;

HCV-402A, B, C, and D; and HCV-403A, B, C, D)

(a) These are isolation valves for CCW flow to the containment

air cooling and filtering units.

Valves HCV-400A and C,

HCV-401A and C, HCV-402A and C, and HCV-403A and C also

func+. ion as containment isolation valves.

The valves can be normally open or normally shut, depending

on the containment cooling requirements. lne valves

require air pressure for operation. The accumulator

assemblies were provided;to ensure that all valves open in

the event that a containment isolation actuation signal is

initiated concurrent with a loss of air system pressure.

(b) The licensee has not completed calculations to verify that

the accumulators are properly sized. A functional test has

been performed, as described below, that verified the

accumulator sizing was adequate.

(c)

Functional testing on the accumulator a.,sembly for each

valve has been completed.

The testing verified that the

accumulator assembly would move the valve to the open

position.

Based on the testing, the licensee determined

that the accumulator assemblies were operational.

The licensee has not performed functional testing to verify

that the valves can be shut in the event containment

isolation is required. A discussion of whether or not an

analysis is required to be performed to address a CCW line

rupture in containment concurrent with a LOCA was provided

.-

--

_

_

e

.,

,.

,

.

,

a-

y

i .

20

in paragraph 3.d of this inspection report.

The status of

these valves will be revie.wed by NRC when the review is

performed for Valves HCV-438B and HCV-4380. Accordingly,

the review of these valves will be tracked under the

unresolved item (285/8815-07) issued to track the review of

HCV-4388 and HCV-4380.

(d) The check valves associated with the accumulator assemblies

were included in the reri sed IST program submitted by the

licensee on December lo, 1987

Inclusion of these check

valves in the IST program will ensure that the valves are

verified to be functional each time the plant is in the

cold shutdown mode.

(e) The licensee performed a calculation to verify that the

accumulator assembly was seismically qualified.

The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

(12) Spent fuel pool charcoal filter bypass valve (HCV-712A)

(a) Valve HCV-712A is normally open to bypass the charcoal

filter during normal plant operations. Whenever spent fuel

'

movement is performed at the spent fuel pool,

Valve HCV-712A is shut so that the ventilation air flow

passes through the charcoal filter to prevent contamination

from being released to the environment. The valve fails

!

as-is on a loss of air system pressure. The accumulator

assembly *s designed to provide motive force to shut the

valve if the valve is in the open position. Once the valve

.

has been shut, it will remain in the shut position.

'

(b) The licensee has not performed a calculation to verify that

the sizing of the accumulator is adequate. A functional

test was performed, as described below, which verified the

adequacy of the accumulator size.

(c) During the 1987 refueling outage, the licensee performed a

functional test of the accumulator assembly.

The test

'

involved shutting Valve HCV-712A under full-flow conditions

and verifying that the valve remained closed for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

Based on the results of the testing, the licensee

established the operability of the accumulator assembly.

(d) The check valve associated with the accumulator assembly

was included in the revised IST program submitted by the

licensee on December 16, 1987.

Inclusion of this check

valve in the IST program will ensure that the valve is

!

verified to be functional each quarter.

-

l

_

.g

,

,

-

.

21

(e) The licensee performed a calculation to verify that the

accumulator assembly was seismically qualified.

The

licensee submitted the calculation to the NRC for review on

November 20, 1987.

The SA0 issued by the licensee for these specific essential valves

has been forwarded to the NRC for review.

In addition, the seismic

calculations submitted on November 10 and 20, 1987, to verify that

the specific accumulator assemblies described above were seismically

qualified are under review by the NRC.

Therefore, these matters will

be considered an open item pending completion of the review by the

NRC.

(285/8815-11)

4.

Followup on an Onsite Event

On April 19, 1988, the licensee identified a situation that represented a

loss of containment integrity. At the time of discovery, the plant was at

100 percent power and had been operating at power since the last refueling

outage that ended June 6, 1987.

During a walkdown being performed by a maintenance engineer to verify the

adequacy of Procedure ST-CONT-3, "Containment Isolation Valves Leakage

Rate Test-Type C," the engineer noted that a tubing cap was not installed.

The cap should have been installed on one leg of the test tee for Pressure

Transmitter PC-743, a pressure transmitter used to annunciate a

containment high pressure condition in the control room.

PC-743 is

connected to containment penetration M-38 via a 1-inch line which is

reduced to 3/8-inch tubing for connection of the transmitter.

The

engineer identified the problem while performing a walkdown in response to

Violation 285/8710-07 cited by the NRC resident inspector in NRC

Inspection Report 50-285/87-10, issued in May 1987. The violation was

related to Procedure ST-CONT-3 not accurately reflecting the as-built

installation of the piping and valves connected to containment

penetrations.

Procedure ST-CONT-3 provides instructions for the local

leak rate testing of mechanical penetrations.

Without the cap installed on the test tee, containment integrity was

violated in that the 3/8-inch tubing connecting PC-743 and

Penetration M-38 provided an unrestricted path from inside to outside

containment. The licensee performed a preliminary calculation to

determine the leak rate through the 3/8-inch tubing, at a containment

pressure of 52 psig, the maximum containment pressure experienced in a

post-LOCA event. The leak rate was determined to be approximately

4.1 cubic feet per minute (cfm). The leak rate calculation was performed

based on a mixture of air water, and steam. This is the mixture that

would be expected after a loss-of-coolant accident occurred.

The licensee also performed a preliminary calculation to determine whether

or not the radiation levels at the site boundary would exceed the levels

established by 10 CFR Part 100 at a calculated leak rate of 4.1 cfm.

The

results of the preliminary calculat;on indicated that the radiation levels

ll

.

.

22

would not exceed the established Part 100 limits. The preliminary

calculation indicated the thyroid dose over a 2-hour period would be

258.6 Rem. The Part 100 limit is 300 Rem. The preliminary calculation

also indicated that the whole body dose would be 6.4 Rem over a 2-hour

period.

The Part 100 limit is 25 Rem.

Based on the results of the

preliminary calculation, it appears that the radiation levels would not

exceed the established Part 100 limits.

The licensee stated that the

preliminary calculation would be formally issued in the near future. This

item remains open pending completion of the calculation and a review of

the calculation by NRC personnel to verify its adequacy.

(285/8815-13)

The licensee performed a calculation to determine the value of the leak

rate through the test tee to determine whether or not containment

integrity was violated as defined by the TS. The flow rate calculation

was performed based on the leakage of dry air from containment, through

the piping and tubing, and out the test tee.

Dry air was used because the

TS limit for La, where La is defined as the design basis leakage rate of

0.1 percent weight of the containment atmosphere per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> at a

pressure of 60 psig, is based cn the leakage of dry air. The licensee's

calculati'n of the leakage via the instrument line indicates the TS limits

for B&C +,pe leakage was exceeded by a factor of approximately seven

(418,000 standard cubic centimeter (SCCM) calculated as compared to TS

limits of 62,451 SCCM). This item represents a potential violation of the

containment integrity requirement of TS LCO 2.6. (285/8815-14)

Upon discovery of this problem by the licensee, the test tee cap was

immediately reinstalled. The licensee immediately instituted a walkdown

of all other penetrations to verify that no other problems existed. No

other problems were identified. The licensee reported the loss of

containment integrity to the NRC Headquarters duty officer on April 19,

1988, via the emergency notification' system in accordance with the

requirements of 10 CFR Part 50.72. The licensee also immediately notified

.the NRC resident inspector.

Licensee management stated that a licensee

event report would be submitted within 30 days of the discovery of the

event in accordance with 10 CFR Part 50.73.

In followup to this event, the licensee also determined that additional

plant instrumentation was affected by the failure to install the test tee

cap.

Three other pressure instruments are also connected to

penetration M-38 via the common piping that connects to PC-743. The

licensee determined that the three instruments were also inoperable

because the open-ended tubing would prevent a pressure increase in the

piping and thus would prevent the three pressure instruments from sensing

a pressure increase in containment.

Two of the instruments, A/PC-742-1

and A/PC-742-2, are used to initiate safety injection, containment

isolation, and steam generator isolation signals in the event of a high

pressure condition in containment.

The two instruments provide redundant

initiation for one of the four channels installed to detect a containment

high pressure event. There are an additional six pressure instruments

which perform the same function as A/PC-742-1 and A/PC-742-2. A third

instrument, A/PC-765, is used to initiate a reactor trip via the reactor

ls

-

,

.

23

protection system in the event of a high containment pressure. An

additional three instruments are provided at other containment

penetrations to initiate the same reactor trip signal.

Because additional

instrumentation remained functional to initiate automatic response to a

j

containment high pressure condition, the required redundancy for the three

inoperable instruments connected to Penetration M-38 was maintained as

defined by the TS.

To establish when the cap may have been removed, the licensee performed a

documentation search. The results of the search indicated that the local

leak rate test was perf;rmed on Penetration M-33 in March 1987 in

accordance with Procedure ST-CONT-3 and that no other work had been

performed on the pressure transmitter since then.

The search also

revealed that Maintenance Order (MO) 872526 had been issued in May 1987 to

verify that all caps associated with local leak rate testing activities

had been reinstalled. MO 872526 was issued for verification of cap

installation as a result of a loss of containment integrity identified by

the licensee in September 1974.

(The licensee submitted Licensee Event

Report (LER) 50-285/74-14 to provide details of the loss of containment

ntegrity.)

followup inspection was performed by the NRC inspectors to review the

actions taken by the licensee and to verify that the actions were

completed. The NRC inspectors noted that the program established by the

licensee to verify that all penetration assemblies were returned to normal

prior to exiting the cold shutdown mods was not a commitment made in

LER 50-285/74-14, but instead was a program established by licensee

self-initiative. However, the cap that was found not to be installed had

not been included on the M0 as an item for verification.

Therefore, based

on the documentation review performed by the licensee, it appeared that

the cap had not been reinstalled when the local leak rate test was

performed in March 1987.

The NRC inspectors then performed a followup of this event.

The followup

included a tour of the plant to verify that selected penetrations were

properly sealed to prevent a loss of containment integrity, a review of

Procedure ST-CONT-3 to verify that appropriate instructions had been

provided for testing of Penetration M-38, and a review of M0 872526 that

provided instructions for a verification that all test caps were

installed.

During this review, the NRC inspectors noted that the selected

penetrations inspected during the plant tour were in an acceptable

condition.

A review of Procedure ST-CONT-3 indicated that the instructions provided

to the technicians were inadequate in that Procedure ST-CONT-3 requires

that the cap on the test tee be removed prior to performance of the leak

rate test; however, no instructions are provided to the technician ta

ensure the cap is replaced. A review of MO 872526 indicated that the

technicians were instructed to verify that the test fitting used inside

containment to perform the local leak rate test had been removed; however,

no instructions were provided for verification that the normally installed

i

,

- ,,

..

_

"

r

  • . ,;.

24

test caps had been replaced. The licensee could not determine why a

verification of cap installation had not_ been provided on M0 872526.

Since Violation 285/8710-07 has already been issued to address the

inadequacies of Procedure ST-CONT-3, no additional violation will be

issued to cite the specific problems associated with the instructions

provided for testing of Penetration M-38.

Licensee management stated, in

response to Violation 285/8710-07, that Procedure ST-CONT-3 would be

upgraded prior to the next refueling outage.

It is expected that the

upgrade of Procedure ST-CONT-3 will include revision of the instructions

for testing Penetration M-38.

Further, licensee management stated that an

in-depth raview would be performed to ensure that the instructions

provided for verification of normal penetration assembly status prior to

startup from a refueling outage would be performed.

In addition, during a review of this event, the NRC inspector noted that

the containment isolation valve, A/HCV-742, for Penetration M-38 was an

air-operated valve and that the valve did not have an accumulator assembly

installed.

In an event where containment isolation of Penetration M-38 is

required, concurrent with the loss of instrument air pressure, it is not

evident how Valve A/HCV-742 could be shut, considering the valve fails

open on a loss of air pressure. The licensee stated that the NRC had

previously approved the installation and failure mode of Valve A/HCV-742.

The NRC inspector will forward the information discussed above to

personnel in NRC Headquarters for review to verify that the installation

and failure mode complies with established design criteria appropriate to

the Fort Calhoun Station. This item remains' unresolved pending a review

i

by NRR. (285/8815-15)

4.

Exit Interview

The NRC inspectors met with Mr. R. Andrews, Division Manager, Nuclear

Production, and othee members of the licensee's staff on April 22, 1988,

and obtained supplemental information until May 13, 1988, at the end of

this inspection. At this meeting, the NRC inspectors summarized the scope

of the inspection and the findings.

l

l

l

[

t

1

)

2:; Ofr;

.

's:~

,- ,

!=

APPENDIX B

- PROPOSED ENFORCEMENT CONFERENCE AGENDA

~

CMAHA PUBLIC POWER DISTRICT-

'

June 8, 1988

, L

I.

Introduction and Purpose of Meeting

L. J. Callan

Adequacy of Accumulator Assemblies and

Associate Analysis-Justifying

Continued Plant Operation

Containment Integrity

.II.

Licensee Presentation

OPPD Staff

-III. NRC Comments

L. J. Callan

IV.

Licensee Response-

OPPD Staff

V.

Closing Comments

L. J. Callan

L

i

f

.

I

e

+-v

i ,.

s.