ML20154S834

From kanterella
Jump to navigation Jump to search
Safety Insp Repts 50-456/86-06 & 50-457/86-05 on 860127-0329.No Violation or Deviation Noted.Major Areas Inspected:Licensee Actions on Previous Insp Findings,Plant Tours,Pipe Supports,Essential Svc Water & Contractor Audit
ML20154S834
Person / Time
Site: Braidwood  
Issue date: 04/03/1986
From: Gardner R, Kropp W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20154S826 List:
References
50-456-86-06, 50-456-86-6, 50-457-86-05, 50-457-86-5, NUDOCS 8604080169
Download: ML20154S834 (7)


See also: IR 05000456/1986006

Text

.,

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-456/86006(DRP); 50-457/8600S(ORP)

Docket Nos.- 50-456; 50-457

Licenses No. CPPR-132; CPPR-133

'

Licensee:

Commonwealth Edison Company

Post Office Box 767

Chicago, IL 60690

Facility Name:

Braidwood Station, Units 1 and 2

'

Inspection At: Braidwood Site, Braidwood, IL

Inspection Conducted:

January 27, 1986 through March 29, 1986

,

hb"

/dg

Inspector: Wayne J. Kropp

Date

h-

A/85

Approved By:

Ronald N. Gardner, Chief

Reactor Projects 3A

Date

Inspection Summary

Inspection on January 27, 1986 through March 29, 1986 (Reports

No. 50-456/86006(0RP); 50-457/86005(0RP))

Areas Inspected:

Routine, unannounced safety inspection of activities with

regard to licensee action on previous inspection findings, plant tours, pipe

supports, essential service water, and the mechanical contractor audit

program. The inspection consisted of 128 inspector-hours onsite by one NRC

inspector including 5 inspector-hours onsite during off-shifts.

Results:

No violations or deviations were identified.

MA' M S N J'

O

-

..

.

'

DETAILS

1.

Persons Contacted

Commonwealth Edison Company (CECc)

  • M. J. Wallace, Project Mansger

C, W. Schroeder, Services Superintecdent

D. L. Shamblin, Project Construction Superintendent

  • G. E. Groth, Assistant Construction Superintendent
  • E. E. Fitzpatrick, Station Manager
  • G. Marcus, Assistant Manager Quality Assurance
  • T. E. Quaka, Site Quality Assurence Superintendent

W. Yahle, Engineering Manager

J. W. Gieseker, Engineer

M. Gorski, Engineer

$0. Boone, Project Construction Field Engineer

  • E. Wondorf, Engineer
  • P. Barnes, Regulatory Assurance Supervi'scr
  • L. E. Davis, Assistant Superintendent Technical Services
  • D. Pan,uette, Maintenance Assistaat Superintendent
  • R. Kyrouac, Station Quality Assurance Supervisor
  • 0. E. O'Brien, Operations Assistant Superintendent
  • C. J. Tomashek, Project Startup Superintendent
  • 0. L. Cecchett, Regulatory Assurance
  • A. J. D' Antonio, Regulatory Assurance
  • T. Miosi, Nuclear Licensing Administrator - G.O.
  • T. Simpkin, kegulatory Assurance

The inspectors also cont 6cted other licensee and contractor personnel,

. including craftsmen, and technical and engineering staff cembers.

  • Denotes those attending the exit meeting on March 27, 1986.

2.

Licensee Action on Previous Inspection Findings

a.

Violations

(Closed) 456/83-09-02A; 457/83-09-02A:

Two drawings were not stamped

with field change request (FCR) document numbers.

Part of the

licensee's corrective action was evaluated and verified for implemen-

tation during the inspect-lon period documented in Inspection Reports

No. 456/65032; 457/85031. The licensee':s corrective action consisted

of:

Stamping drawing M-2539C-4 with FCR L-9194 and urawing

M-2542C-121 with FCR L-9988.

These drawing; were identified

in the violation as not being stamped with these FCRs as

2

.

.

required by Phillips Getschow Procedure PGCP-1.1, " Control of

Engineering Change Notices and Field Change Requests."

Drawings M-2539C-4 and M-2542C-121 were verified to be stamped

with the appropriate FCRs during the inspection period documented

in Inspection Reports No. 456/85032; 457/85031.

Intensifying and increasing training in document control

activities.

The inspector verified that training was conducted

in document control activities.

This training was conducted with

production, engineering, and QC personnel in September 1983.

Conducting audits to verify that the corrective action was

acceptable.

One of the audits, Phillips Getschow Audit

No. 83-BR15, was conducted July 26, 1983, which commenced prior

to the extensive attention placed on document control by Phillips

Getschow (August 1983).

This audit did identify drawings that

were not stamped with the appropriate FCRs or Engineering Change

Notices (ECNs).

However, subsequent followup audits (September,

October, November, December, 1983 and August 1984) reviewed by

the inspector revealed no problems with document control.

The

inspector also reviewed licensee QA Surveillances No. 2981

(June 1983) and No. 3450 (February and March 1984) which were

performed to followup on deficiencies noted in document control

during the licensee site QA Audit No. 20-83-15 (March 1983) of

Phillips Getschow.

These surveillances noted no problems with

drawing control.

Based on the results of the followup audits

conducted by Phillips Getschow and the followup QA surveillances

by the licensee, the corrective action appears effective.

Since installation activities were performed to the drawings and

process documents in the production data packages, the lack of

stamping drawings located at the document control stations with the

outstanding ECNs and/or FCRs would not directly affect the

installation of components.

In addition, the review for the impact

of an ECN or FCR on installation activities is independent of the

stamping of the ECN or FCR on controlled drawing copies.

The

inspector selected several drawings which were noted in the licensee's

Audit No. 20-83-15 as not having been stamped with the appropriate

FCR/ECN and verified that the installed component was not affected.

This was accomplished by reviewing the production data packages and

inspecting the installed component.

This item is considered to be

closed.

(Closed) 456/85007-02; 457/85007-02:

The installation of the

containment spray pumps was not in accordance with design drawings.

The corrective action consisted of the piping contractor, Phillips

Getschow, issuing a Nonconformance Report (NCR) 3963 to document the

'

deficiency in the installation of the Unit 1 and Unit 2 containment

spray pumps.

The Unit 1 and Unit 2 residual heat removal (RHR) pumps,

which are of the same design as the containment spray pumps, were

examined by Phillips Getschow and similar deficiencies were identified

on each pump.

Phillips Getschow issued NCR 3961 to document the

3

.

.

deficiencies with the RHR pumps.

Both NCR 3963 and 3961 required the

pumps to be reworked in accordance with applicable design drawings.

The inspector reviewed the installation records and inspected the pumps

and noted no problems.

Both NCRs were closed January 30, 1986.

The

corrective action to avoid further noncompliance includes a Phillips

Getschow equipment installation procedure, QCP-822, and improved

equipment grouting control instituted in the last year.

The inspector

reviewed procedure QCP-B22 and the equipment grouting controls and

found them satisfactory.

To ensure other equipment does not have

deficiencies similar to the containment spray pumps and the RHR pumps,

the licensee issued NCR 6083.

This NCR provides for reviews of other

safety-related equipment pump bases and supporting documentation to

ensure correct installation, grouting and inspection.

NCR 6083 was

closed March 27, 1986.

The inspector reviewed the disposition and

closure of this NCR with no problems being noted.

This item is

considered to be closed.

(Closed) 456/85015-06:

The licensee's Quality Assurance Department

inappropriately closed Nonconformance Report (NCR) 600 and as a result

did not assure that conditions adverse to quality were corrected.

Parts of the licensee's corrective actions were evaluated and verified

for implementation during the inspection periods documented in

Inspection Reports No. 456/85032; 457/85031 and 456/85058; 457/85054.

The inspector verified that NCR 600, which was reopened, was properly

and effectively closed by the licensee's QA Department.

NCR 600 was

reclosed by Surveillance 5548, on February 26, 1986.

The pipe supports

associated with NCR 600 were inspected by the licensee's QA department

to verify compliance with the design drawings prior to reclosing NCR

600.

The inspector selected four of the 14 pipe supports inspected by

the licensee's QA department to evaluate their effectiveness.

The

results of these four inspections are documented in Paragraph 4 of

this report.

The licensee's response to this violation stated that

NCR 744 was issued to identify concerns which were noted during a

special audit conducted by Phillips Getschow.

NCR 744 was closed

March 27, 1986. The inspector reviewed the disposition and closure of

this NCR with no problems being noted.

This item is considered to be

closed.

b.

Open Items

(Closed) 456/85038-09; 457/85037-07:

The processing of site

contractor documents, which identify significant conditions adverse

to quality, was not performed in a manner commensurate with the

processing of NCRs.

The licensee has sent letters to the major site

contractors (Newberg, L. K. Comstock, Phillips Getschow, and Pullman)

which standardized the approach for processing documents identifying

significant conditions adverse to quality.

These documents are

required to be submitted to the licensee for approval of the proposed

resolution.

This item is considered to be closed.

No violations or deviations were identified.

4

_ _ _ _ _ _ _ _

.

.

3.

Plant Tours

The inspector observed work activities in progress, completed work, and

plant status during general inspections of the plant.

Observations of.

activities included:

storage of electrical raceway components for Unit 2,

structural welding, cable tray hanger installation for Unit 2, housekeening,

cable trays, junction boxes, mechanical equipment, and high strength

bolting.

During this inspection period, the licensee commenced Integrated

Hot Functional Testing (IHF).

The inspector observed various IHF activities

and monitored control room activities.

The housekeeping of Unit 1 areas

has improved since November.

However, one item was discussed with the

licensee regarding action to protect the Main Control Board (MCB) from

unnecessary exposure to dust and dirt.

The doors on the back of the MCB

were left open even though there is no work in progress.

This item was

identified by the licensee management during a tour and management agreed

that some action would be taken to ensure the doors remained closed when

work was not in progress. The inspector will monitor this area to

ascertain the effectiveness of management's action to resolve this issue.

No violations or deviations were identified.

4.

Pipe Supports

The following ASME Class 1 supports were examined to verify compliance

with design drawings and the ASME code in the areas of weld quality, weld

configuration, location and hanger configuration:

Identification

System

Type

1CV06031V

Chemical & Volume Control

Spring Hanger

1SI25004F

Safety Injection

Pipe Clamp

1RH02050R

Residual Heat Removal

Sway Strut

1SIO401?S

Safety Injection

Shock Suppressor

The inspector also reviewed the data packages which include the

installation traveler, weld issuance tickets, nondestructive examination

records, and any closed deficiency documents.

No violations or deviations were identified.

5.

Essential Service Water

The licensee informed the inspector of an error in the radiographing of two

welds in the Essential Service Water system.

During the NRC Construction

Appraisal Team (CAT) inspection documented in Inspection Reports

No. 456/84044; 457/84040, the CAT inspectors determined that the radiographs

provided by the vendor (Southwest Fabricators) for welds SX-36-1-W3 and

SX-36-1-W4 were radiographs of the same weld (W3).

Therefore, W4 was never

radiographed.

In order to determine the acceptability of the unradiographed

weld (W4), the site independent testing contractor, Pittsburgh Testing

Laboratory (PTL) was directed by the licensee to radiograph both welds.

The radiographs produced by PTL.were provided to the CAT inspectors and

5

.x

.

!

'

their review and interpretation determined that the welds were acceptable.

Subsequently, while reviewing the installed pipe spool, the site mechanical

contractor noted that field weld 8A was identified on the pipe as shop weld

W3.

A field review of the spool and radiographs by the licensee determined

that PTL had radiographed field weld 8A as shop weld W3 and shop weld W3 as

  • -

shop weld W4.

This resulted in Southwest Fabricator's shop weld W4

remaining unradiographed.

Therefore, the CAT inspectors concern pertaining

to the two identical radiographs for shop welds SX-36-1-SW3 and SX-36-1-SW4

is now identified as an unresolved item (456/86006-01; 457/86005-01).

At

this time, the involved spool is full of water due to testing and cannot be

radiographed.

The licensee has stated that all three welds (8A, W3, and W4)

will be radiographed and evaluated for final disposition when the spool is

available for radiographing.

No violations or deviations were identified.

6.

Phillips Getschow Audit Program

The inspector reviewed the following Phillips Getschow internal audits for

compliance to Phillips Getschow Procedure QAP/8R 12.1, Revision 8, " Site

Internal Audits":

Audit No.

Subject

Date

86BR8

Final Line Walk of

February 11-24, 1986

Compcnents. Supports /

Restraints

,

'

86BR12

Component Support Mater'ial

February 28 - March 4,

and Item Substitution and

1986

the Restocking of Deleted

s

or Unused Component Support

Material and Items

4

868R5

Mechanical Joint Review /

January 20-27, 1986

Retrofit Program .

I4

86BR13

Base Metal Accepta1ce and

February 1986

Repair for AISC, Category I

'

'

Steel

86BR18

Calibration by Outside

March 11-13, 1986

Source

The checklists utilized in performing these audits were reviewed by the

inspector.

The checklists identified the objective evidence evaluated by

the auditor during the audit.

The audits verified the implementation of

the procedures that were being audited.

The inspector also reviewed the

training and certification files for six lead auditors.

No violations or deviations were identiffeu.

s

6

r

.

,

7.

Unresolved Items

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable items, violations, or

deviations.

An unresolved item disclosed during the inspection is

discussed in Paragraph 5.

8.

Exit Interview

The inspector met with licensee and contractor representatives denoted in

Paragraph 1 during and at the conclusion of the inspection on March 27,

1986.

The inspector summarized the scope and results of the inspection and

discussed the likely content of this inspection report.

The licensee

acknnwledged the information and did not indicate that any of the

information disclosed during the inspection could be considered proprietary

in nature.

7

u