Informs That Submission of Surveillance Capsule Matls Test Rept Will Be Delayed Beyond 880920 Deadline,Due to Oxidation & Degradation Damage to Flux Spectrum Monitors.Rept Will Be Submitted by 871231
ML20154M007
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 09/20/1988
From: Medford M
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
NUDOCS 8809270024
Download: ML20154M007 (1)


Text

_ _ _ _ _ _

b o

9 fG Southem Califomia Edison Company P O sox 000 2244 W ALPdVT GROVE Avit4UC RO S E M E A D. C A U F OM P41 A 917 70 M O utoroRO g g g g,, ong

. ~.u. o7e;.;.. ~+ ~, ' "

September 20, 1988 U. S. Nuclear Regulatory Commission Attention: Document Control Oesk Hashington, D.C. 20555 Gentiemen:

Subject:

Docket Nos. 50-361 and 50-362 Extension for iM Surveillance Capsule Haterials Test Results Report San Onofre huclear Generating Station, Units 2 and 3 A reactor vessel material irradiation surveillance specimen was removed from the Unit 2 reactor vessel during Unit 2 Cycle 4 refueling outage on September 20, 1987, to satisfy a Technical Specification Surveillance Requirement 4.4.8, "Reactor Coolant System Pressure and Temperature Limits."

A technical summary report of the result is required by 12 months from the date of the surveillance capsule withdrawal in accordance with 10 CFR 50 Appendix H.

In order to meet this deadline, the surveillance capsule cask was shipped to the Battelle Columbus Laboratory for test and analysis on February 19, 1988.

However, during testing and analysis, Battelle Columbus Laboratory informed SCE on August 10, 1988, that flux spectrum monitors in the surveillance specimens were damaged.

The damage to the flux spectrum monitors consisted of oxidation and degradation, due to poor fabrication process, and revised procedures would he necessary for disassembly and testing.

Consequently, the submittal of the Unit 2 surveillance capsule materials test report will be delayed beyond the original deadline of September 20, 1988, as estabitshed by 10 CFR 50 Appendix H.

The completion of this materials test report is expected in November of this year.

The report will be submitted by December 31, 1988.

Very truly yours, ff'lhl?f/& "

cc:

D. E. Hickman, NRC Project Manager

/

J. B. Hartin, Regional Administrator, NRC Region V F. R. Huey, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3 MN 9909270004 880920 ip DR ADOCK 0500 g2 7

- -- ---