ML20154L396

From kanterella
Jump to navigation Jump to search
Insp Rept 50-341/86-07 on 860224-28.No Violation or Deviation Noted.Major Areas Inspected:Response to IE Bulletin 84-03, Refueling Cavity Water Seal, Inservice Testing Program Implementation & Instrumentation
ML20154L396
Person / Time
Site: Fermi 
Issue date: 03/05/1986
From: Eng P, Guldemond W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20151H314 List:
References
50-341-86-07, 50-341-86-7, IEB-84-03, IEB-84-3, NUDOCS 8603110464
Download: ML20154L396 (6)


See also: IR 05000341/1986007

Text

e

.

,

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-341/86007(DRS)

Docket No. 50-341

Licensee:

Detroit Edison Company

2000 Second Avenue

Detroit, MI 48226

' Facility Name:

Fermi 2

Inspection At: Fermi Site, Newport MI

Inspection Conducted:

February 24-28, 1986

'

Inspector:

atrici

L. Eng

8

f(<_

"

Qe,,

5

Approved By:

W.

' den,

d, Chief

.

Operational Programs Section

Date

Inspection Summary

Inspection on Februa_ry,i_2,4__28,_1986_(Rep' ort No. 5_0-341/860,07]p_R,S)) ion o

Areas Inspected: Rout ne, unannounced inspectTon orTicensee act

previous inspection findings; review of licensee response to IE Bulletin 84-03;

. inservice testing program implementation and inservice testing instrumentation.

The inspection involved a total of 40 inspector-hours onsita oy one NRC

inspector. During this inspection, Inspection Procedures 61700, 92701 and

92703 were used.

Resul ts: Of the areas inspected, no violations or deviations were identified.

B603110464 860305

PDR

ADOCK 05000341

G

PDR

L

. . -

.

.

DETAILS

1.

Persons Contacted

  • R. S. Lenart, ?lant Manager
  • G. R. Overbeck, Superintendent, Operations

A. J. Banek, I and C Technician

  • J. E. Conen, Licensing Engineer

R. C. Drouillard, Nuclear Fuel Handling Supervisor

R. J. Filipek, Acting I and C Engineer

R.

'. Mack, Plant Support Engineer

D. D. Merriman, Metrology Lab Specialist

B. J. Sheffel, ISI Programs Engineer

K. Speicher, Consultant NSS

  • Denotes those who attended the exit meeting on February 28, 1986.

The inspector also interviewed others of the licensee's staff during the

course of the inspection.

2.

Licensee Action On Previous Inspection Findings

(Closed) Open Item (341/84046-02(DRS)) Determination of maximum allowed

leak rates for category "A" and "A/C" valves.

The inspector reviewed the

licensee's Inservice Testing program for valves as well as selected valve

leak test procedures and determined that valve specific maximum allowable

leak rates had been set. This item is closed.

'

No violations or deviations were identified.

3.

Review of Licensee Response __to_ IE Bu_1_lp_t_in__8_4 _03

On August ?4, 1984, the NRC issued IE Bulletin 04-03, " Refueling Cavity

Water Seal", to all power reactor facilities. The IEB, which described

the events surrounding a refueling cavity water seL1 failure at the Haddam

Neck facility, required licensees to evaluate the potential for and

consequences of a seal failure and submit a sumary report supporting

their conclusions.

The inspector reviewed the licensee's response to IE Bulletin 84-03

as provided by letter dated, November 3,1984, pertinent drawings and both

normal and abnormal fuel handling procedures.

It was concluded that the

Fermi cavity seal does not contain active components, is permanently

installed and, therefore not susceptible to the type of failure described

in the bulletin.

During the inspection the inspector noted the following:

a.

The licensee does not use inflatable seals to retain water in the

reactor refueling cavity. A pern.anently installed bellows seal is

used which, on total failure, will result in a small leak rate limited

by a backup flexible plate seal. Leakage from the seal area is

directed to an alarmed flow meter which is verified operable and

calibrated periodically.

2

.

,

b.

The relative elevations of the spent fuel pool, the reactor core, and

the seal are such that with a seal failure and associated draindown,

'

only fuel suspended from the bridge crane and the two fuel

preparation machines could be uncovered. All remaining active fuel

would remain covered. Assuming both the loss of normal makeup

supplies and a cavity seal failure, ample time is available to place

fuel in a safe condition.

c.

Procedures are in place requiring that fuel in transit be placed

in a safe condition if leakage is indicated and makeup is

insufficient. These actions can be completed before damage occurs or

radiation levels become excessive,

d.

The spent fuel pool does not have any drains, and potential siphon

paths are defeated by installed vacuum breakers such that inadvertent

valve opening or pipe failure can not result in draining the spent

fuel pool below the level of the active fuel,

e.

Two fuel pool level alarms, the flow rate alarms mentioned in

paragraph 3.a. area radiation monitors and periodic visual inspection

are available to initiate mitigating actions on a loss of pool

inventory. Abnormal operating procedures are in place addressing

safe placement of fuel, inventory makeup and evacuation of high

radiation areas.

Based on the above, it is concluded that system design renders the

prcbability of catastrophic seal failure acceptably low.

In the event

that such a failure occurs, fuel damage is not anticipated based on

existing fuel handling procedural requirements and sufficient time to

implement such requirements.

It is, therefore, concluded that the

licensee has adequately resolved the issues identified in IEB 84-03, and

the IEB is considered closed.

A review of other potential mechanisms for loss of water was also

conducted. Short of structural failure, no credible nechanism for loss of

spent fuel pool inventory was identified.

Evaluation of other potential

leak paths fo'r the reactor cavity such as instrument installations or

access covers would result in a leak rate less than that associated with

seal failure or would be discovered prior to removal of the reactor vessel

head.

In the event of such a leak through access covers with the reactor

vessel head rerroved, personnel manning requirements assure sufficient

time to place fuel in a safe condition.

Discussions with the Nuclear Fuel Hardling Supervisor indicated that

no training or procedures are currently in place to address movement of

fuel should a loss of off site power occur. Discussions with operators

previously trained for fuel handling activities indicated that they were

aware that non-powered fuel movement could be acccmplished; however, the

details of how to conduct such operations were not clear. A training

request was promptly initiated to incorporate appropriate actions upon

loss of off site power while moving fuel into fuel handlers' training.

Verification of training conpletion and procedure revision to address

3

-

-

-

. --

. - - _ _

. . . _ . . - - - -

_ - .

__ ..

.

.

, - - - -

i

'

.

,

,

!

l

?

placement of fuel in a safe condition with a loss of off-site power prior

to the first refueling outage is considered an open item

(50-341/86007-01(DRS)), and will be followed up in an inspection prior to

the first refueling outage.

No violations or deviations were identified.

Inservice Testing _P_rogr_am , Implementation

4.

o

The licensee's inservice testing (IST) program has been reviewed and

approved by the Conmission in the facility Safety Evaluation Report.

During the course of the inspection, the licensee requested copies of

various memos which provide guidance related to interpretations of the

ASME Code requirements for inservice testing. Copies of the pertinent

memos are attached to this report.

The inspector reviewed the licensee's relief requests from the ASME Code

requirements and initial program implenentation, making the following

observations

,

a.

Subsection IWV-3300 of Section XI of the American Society of

Mechanical Engineers' Boiler and Pressure Vessel Code (ASME Code)

requires that those valves with remote position indicators be

observed at least cnce every 2 years to verify that valve operation

is accurately indicated. Discussions with the ISI Engineer revealed

that a program ensuring such was in place; however, valves which were

indicated on plant remote shutdown panels had not yet been checked.

The licensee agreed to initiate verification of remote position

indicators on the remote shutdown panels and to complete such

verifications within the ASME Code stipulations. Completion of

position verifications will be tracked as an open item

(50-341/86007-02(DRS)).

b.

As stated in the approved IST program, the licensee is allowed to

satisfy the vibration measurement requirements of the ASME Code by

obtaining vibration data in terms of velocity rather than amplitude.

It was noted that the licensee established a single vibration

acceptance criteria for all IST vibration measurements.

Review of

the High Pressure Core Injection (HPCI) surveillance procedure and'

initial test data revealed that past vibration test data were

unacceptably high. The licensee stated that upon completion of the

surveillance test on the HPCI pump, major maintenance was performed

on the pump, and that new reference values for HPCI pump vibration

measurements as well as associated acceptance criteria wculd be

formulated when sufficient steam was available to run the pump.

In

addition, the licensee stated that the decision whether to

permanently install the vibration transducers or to use hand held

instruments had not yet been made. Establishnent of the method

of vibration testing and appropriate acceptance criteria, and marking

of the data points on the pump will be tracked as an open item

(50-341/86007-03(DRS)).

4

a,NwT'-WMT

-

-

.p+-

_

e

_

ww

.

.

c.

The inspector noted that, in most cases, maximum valve stroke times

had been set based on an evaluation of valve data provided by the

manufacturer, the design engineer and plant test data. Review of the

IST program revealed that a relatively small number of valves have

the system response time defined as their maximum allowed stroke

time. The licensee agreed with the inspector's observations and

stated that valve stroke times would be reviewed and revised to

reflect individual valve characteristics and test results. The

definition of specific maximum valve stroke times which are more

indicative of component degradation, is considered to be an open item

(50-341/86007-04(DRS)). The licensee agreed to complete this effort

by the first refueling outage,

d.

A number of administrative procedures addressing the IST requirements

delineated in the ASME Code were in place. The inspector reviewed

the procedures for adequacy and consistency.

The inspector

determined that Code requirements were appropriately and clearly

addressed.

No violations or deviations were identified.

5.

Inservice Testing Instruments

A review of the adequacy of instruments used to obtain inservice testing

data against established requirements was performed by the licensee prior

to program implementation. The inspector evaluated a number of

instruments and discovered that the equipment history file for the HPCI

permanently installed tachometer defined the instrument as non-seismic and

Quality Assurance (QA) level 3; however, the Master Instrument List (MIL)

identified the same instrument as seismic category 1 and QA level 1.

The

licensee stated that this discrepancy was probably due to the fact that at

the time of purchase, it was not clear as to how the tachemeter would be

used.

The loop calibration procedure for the tachometer was not located

during the course of the inspection; however, the inspector reviewed the

calibration procedure for the tachometer sensor and noted that a one point

calibration was performed. The licensee stated that a multi-point

calibration for the loop was probably performed. The inspector also noted

that the tachcmeter was overdue for scheduled calibration. Discussions

with the licensee revealed that the tachometer had been used to obtain

initial reference data for the HPCI pump; however, due to extensive punp

mcdifications and the need to establish vibration acceptance criteria as

discussed in paragraph 3 above, new reference values would have to be

taken.

In effect, data taken with the tachometer had not been used to

verify pump operability under the auspices of the IST prcgram.

The

licensee was unable to identify any other data taken with the tachometer.

Resolution of the calibration status and requirements, and classification,

both seismic and QA level, for the tachometer, as well as evaluation of

the validity of any data taken using the tachometer, is considered an

unresolved item (50-341/86007-05(0RS)).

No violations or deviations were identified.

5

.

.

6.

Oyen Items

Open items are matters which have been discussed with the licensee, which

will be reviewed further by the inspector, and which involve some action

on the part of the NRC or licensee or both.

Open items disclosed during

the inspection are discussed in Paragraph 3 and 4.

7.

Unresolved It_ ems,

Unresolved itemt. are matters abcut which more information is required in

order to ascertain whether they are acceptable items, open items,

deviations, or violations. Unresolved items disclosed during the

inspection are discussed in Paragraph 5.

8.

Exit Interview

The inspectors met with licensee representatives (denoted in Paragraph 1)

on February 28, 1986, to discuss the scope and findings of the

inspection.

The licensee acknowledged the statements made by the

inspectors with respect to items discussed in the report. The inspector

also discussed the likely informational content of the inspection report

with regard to documents or processes reviewed by the inspectors during

the inspection. The licensee did not identify any such documents /

processes as proprietary.

6

_.

_

_

  • ,y,

Ql y

~ .._)

p

j

R ; L:Mit:;'.

_y

?)

$[ (

.:

I

-

>

AIIAEEBLEIs

.

u

O

'

sh

w

NAR 171980

.

S S!!:S ilo. 6025

,3,

.y

HEM)RANDUM FOR:

R. C. Lewis, Acting Chief. RO&tS tranch, Region II

FROM:

Smuel E. Bryan, A/D for Field Coordination DR0!, IE

SUSJECT:

OPERASILITY REQUIRE'TNTS FOR PUMPS (AITS NO. F02-700028-N07)

As we understand then, the questions in your February 1 memo are:

.

1.

Do the Technical Specification ACTION stat m ent time perios run

consecutive or concurrently with the data evaluation time (96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br />)

given in IW-3220 cf Section XI of the ASK So11er and Pressure Vessel

l

Code, l'374 Edition with Addenda thru the Sweer 1975, and

2.

When should the test results be reviewed and, if out-of-specification,

the associated pay declared inoperable?

The answer to the first goestion is the Technical Specification ACTION state-

.~ent tim period starts after the detamination is made that the pay is

inoperable as defined inWlon XI. WP-3230fc). If the data is within the

l'equired Action Rance of Table IW-3100-2 and it is de;;1ded to recalibrate

the ir.strtr.ents and rerun the test, as provided for in IWP-3230(b), the

Technical Specification ACTION statement time starts when the determination

is cade that the data is within the Required Action Range. The reasoning

behind the preceeding statement is that once the detennination is r.ade that

the data is within the Required Action Range the pure must be declered

inoperabic. The provisions in IW-3230 to recalibrate and rerun the test to

show the ptr9 is still capable of fulfilling its function are interpreted by

us as an alternative to replacement or repair, not an additional action that

can be taken before declaring the pump inoperable.

The answer to the second question is that'as soon as the data is recognized

as being within the Required Action Range the pump must be declared inoperable.

Section XI. WP-6230, ' Inservice Test Plans", stateNst the test plan shall

include 'The reference values ' Table IW-3100-1)Is Subsection." limits of Pg and Tb (Tab

IwP-3100-2), and any other values required by th

This statement

'

g w>G S ,c r Q T S M

C0'iTACT:

J. C. Stone, IE

f 402.; r,t n i

......I,

.......

l

..

-

. . ..

l

-

_ _ .

,

..

.

O

q

R. C. Lewis

2

MAR 171980

then requires the acceptance criteria to be included in the test plan.

With that indomation available, the shift supervisor should be able to

make the detemination as to whether or not the data meets the requirements.

The important point is that once the data becomes available that shows the

pop cannot meet the inservice inspection requirements and by dedinition

cannot fulfill its function then the pomp must be declared inoperable.

'

._

We have discussed the abon interpretations with 00R personnel and the

'

.

Standard Technical Specification Group and they agree. If you have any

-

further questions, please call.

Samuel E. Bryan

-

Assistant Director

.

for Field Coordination

Division of Reactor

Operations Inspection. IE

cc:

81. C. Moseley. IE

J. 5. Wetmore. STS

G. Johnson. E8

J. C. Stone. IE

-

F. J. Nolan IE

J. I. Riesland. IE

B. R. Messitt, RI!

E. J. Brunner. RI

3

R. F. Heishman, R!!!

G. L. Madsen RIV

J. L. Crews, RV

,

l

>

l

.

,

.W

f~

,

'

FC:R0!:!E h ADFC:ROI , j 00R :E,B['f, , , , ' "

. . .

JC5 tone:LD.

SE8ryan

ef/ I

..

..

3/13/80

3/l'7/80

3/{/80

.,

....

_

,.

--

.

_

. _ _ _

_ _ _ _

._

._

.

-

_ - - _ _ _ - -

l

.

..

.

.

'*

/pa M t.v, 'o.

UNITED STATES

.

'

E , . . 'h

NUCLEAR REGULATORY COMMISSION

i p "'( gy

WASWNGTON, D. C. 20555

s?.

sa

gv.....f

n

.

Docket No.: STN 50-483

1

MEMORANDUM 'OR: Richard L. Spessard, Dir(ctor

F

Division of Reactor Safety

Region III

FROM:

Hugh L. Thompson, Jr., Director

Division of Licensing

Office of Nuclear Reactor Regulation

-

SUBJECT:

CLOSURE VERIFICATION OF NORMALLY CLOSED CHECK VALVES

DURING PREOPERATION TESTING AT CALLAWAY (TIA 83-117)

REFERENCE:

Letter from R. L. Spessard to D. G. Eisenhut on the

above subject, dated November 8, 1983.

The referenced letter requested the staff position regarding testing of

normally closed check vpives for closure capability during preoperational

testing and during plant life.

The staff position is that normally closed

check valves, that have a safety function in the closed position, should

have the closure function verified both during preoperational testing and

periodically throughout the plant life.

In addition, the staff verifies

that closure verification testing is specified in their normal review of

the IST program, and if not, measures are taken to see that the program

is revised.

l

In an attempt to have the ASME clarify ambiguities within Section XI of the

ASME Code regarding valve categorization and leak testing, the staff submitted

an inquiry to the society. The response time from the society (approximately

^

one year) was a major factor in the delay of this response to you.

Enclosed

is a more detailed staff evaluation of the subject.

h ttdk'.

UG

L --

]\\/Hugh L.

hompso

Jr., Director

Division of Licensing

Office of Nuclear Reactor Regulation

Enclosure: As stated

cc:

T. Martin

P. Bemis

R. Denise

T. Bishop

P. Wohld

, P. Pelke

.

. L'

%~ittle, Resi. dent' Inspector

i8

~.

- _ _ . .

.