ML20154J887

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-321/85-32 & 50-366/85-32.Violation 1 Remains as Stated in Notice of Violation.Response to Violation 1 Requested
ML20154J887
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 03/05/1986
From: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Kelly R
GEORGIA POWER CO.
References
NUDOCS 8603110099
Download: ML20154J887 (3)


See also: IR 05000321/1985032

Text

O VC<d' ML yg

f

'

MAR 0 51986

Georgia Power Company

ATTN: Mr. R. J. Kelly

Executive Vice President

P. O. Box 4545

Atlanta, GA 30302

Gentlemen:

SUBJECT: REPORT NOS.~ 50-321/85-32 AND 50-366/85-32

Thank you for your response of January 13, 1986, to our Notice. of Violation

issued on December 12, 1985, concerning activities conducted at your Hatch

facility.

We have evaluated your response to the violations and found that

violation No. 2 of your letter meets the requirements of 10 CFR 2.201. We will

examine the implementation of your actions to correct violation No. 2 during

future inspections.

After careful consideration of the bases for your denial of violation 1, we have

concluded, for the reasons presented in the enclosure to this letter, that the

violation occurred as stated in the. Notice of Violation.

Therefore, in

accordance with 10 CFR 2.201(a), please submit to this office within 30 days of

the date of this letter a written statement describing steps which have been

taken to correct violation 1 and the results achieved, corrective steps which

will be taken to avoid further violations, and the date when full compliance

will be achieved.

The response directed by this letter is not subject to the clearance procedure

of the Office of Management and Budget issued under the Paperwork Reduction Act,

PL 96-511.

We appreciate your cooperation in this matter.

Sincerely,

Original signed by

J. N. Grace

J. Nelson Grace

Regional Administrator

Enclosure:

Staff Assessment of Licensee Response

cc w/ encl:

J. T. Beckham, Vice President and

General Manager

H. C. Nix, Site General Manager

P. E. Fornel, Site QA Supervisor

L. Gucwa, Manager, Nuclear Safety

and Licensing

bec w/ encl:

(See page 2)

~~~G&O3110099 960305-

'

PDR

ADOCK 05000321

l

G

PDR

Il

'

ygoj

---

s

.

MAR 0 51986

Georgia Power Company

2

bec w/ encl:

NRC Resident Inspector

Hugh S. Jordan, Executive Secretary

Document Control Desk

State of Georgia

RII

RII

RI

RIlpOb. /'

-

T)

\\h

(;

j

Alanatonis

VBr& nlee

GJen ns

RWalker

2/5S/86

2/.21i/86

2/

<86

f

2/ j/86

..

-

_ - _

__ _ - - _

_ _ - _ - - .

.

-

- - - _ _ _

_ .

.

.s

,

ENCLOSURE

l

Staff Assessment of Licensee Respnnse

Region II has reviewed the licensee's response of January 13, 1986, to the Notice

of Violation (N0V) issued on December 12, 1985.

After a careful review of the

Georgia Power Company response to the two violations, the staff has found the

licensee's response to violation No. 1, as presented in the NOV, to be acceptable,

but disagree with the licensee's assessment that violation No. 2 of the NOV, did

'

not occur.

There is sufficient justification that violation No. 2 of the NOV,

,

designated as violation No.1 in the licensee's January 13, 1986 letter, is an

appropriate example of noncompliance with 10 CFR 50.72(b)(2)(i) reporting

i

requirements. This violation should remain as stated for reasons stated below.

)

10 CFR 50.72(b)(2)(i) requires that a four-hour telephone notification be made of

any event found while the reactor is shutdown, and that, had it been found while

the reactor was in operation, would have resulted in the plant, including its

principal safety barriers, being seriously degraded or being in an unanalyzed

-

condition that significantly compromises plant safety.

On December 15, 1984,

with Unit 1 shut down, the licensee identified a nonisolable linear through wall

,

!

'

crack approximately 2 3/4-inches long in the 18-inch nitrogen inerting and purge

!

line by the magnetic particle inspection method.

At the time of discovery, as stated by the licensee, the shift supervisor was

,

l

notified of the finding and judged that the crack ~would not significantly compro-

mise plant safety, and hence did not make a four-hour telephone report to the

NRC.

However, subsequently a written report was submitted to the NRC per the

_

requirements of 10 CFR 50.73.

,

While the shift supervisor's assessment of the problem was eventually verified to

be correct, in that the crack would not significantly degrade primary containment

'

boundary in the event of a design basis accident, his conclusion was not sup-

,

!

ported by an engineering analysis until much later.

The results of the analysis

(

!

were presented to the NRC on November 8,1985.

Therefore, from the time of

'

' discovery to the time of completed engineering analysis, the nonisolable crack in

the nitrogen inerting and purge line was in an unanalyzed condition. The purpose

of the four-hour NRC telephone reporting requirement is for the licensee. to

promptly identify items such as cracks and breaks in piping that may signifi-

cantly compromise plant safety.

Therefore, while credit is given to the

.

licensee in making an engineering judgement of NRC reportability determination

i

under 10 CFR 50.72(b)(2)(1) criterion, the significance of this condition (i.e.

nonisolable crack) was not adequately assessed.

In this case, visual and

'

'

magnetic particle inspections were not sufficient. bases for determination of

condition significance. An engineering evaluation was also required to determine

-

safety significance.

For the aforementioned reasons, the violation remains as written.

,

I

2

I

'

i

_

.

.

_