OPERATING DATA REPORT DOCKET NO.
50-413 DATE _02/14/86 COhlPLETED BY _ J. A. Reavis TELEPHONE 704/373-7567 OPERATING STATUS Catawba 1 Notes
- Nameplate Rating
~
U Re o t g Period: January 1. 1986-January 31. 1986 1
000 A
po e
- 3. Licensed Thermal Power (MWt):
3411 factor per Page 111,
- 4. Nameplate Rating (Gross MWe):
1205 NUREG-0020.
1145 i
- 5. Design Electrical Rating (Net MWe):
- 6. Maximum Dependable Capacity (Gross MWe):
- 7. Maximum Dependable Capacity (Net MWe):
1145
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report.Give Reasons:
None 4
- 9. Power Level To Which Restricted,if Any (Net MWe):
None
- 10. Reasons For Restrictions,if Any:
' This Month Yr. to Date Cumulative 4
- 11. Hours In Reporting Period 744.0 744.0 5 209.0
- 12. Number Of Hours Reactor Was Critical 676.7 676.7 4 289.0
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On Line 659.2 659.2 A i74.o
- 15. Unit Reserve Shutdown Hours
- 16. Gross Thermal Energy Generated (MWH) 2 052 905 2 052 ons 12 743 085 t
.17. Gross Electrical Energy Generated (MWH) 723 264 723 264 4 407 533 i
l
- 18. Net Electrical Energy Generated (MWH) 679 747 679 747 4 120 261
- 19. Unit Service Factor 88.6 88.6 80.2 88.6 88.6 80.2 l
- 30. Unit Availability Factor
- 21. Unit Capacity Factor (Using MDC Net) 79.8 79.8 69.1 79.8 79.8 69.1
- 22. Unit Capacity Factor (Using DER Net)
II
II
19*9
- 33. Unit Forced Outage Rate
- 24. Shutdowns Scheduled Over Next 6 Months (Type.Date.and Duration of Eacht:
None l
l
- 35. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIA L CRITICALITY INITIA L ELECTRICITY COMMERCIAL OPERATION l
0602210735 960214 l
PDR ADOCK 05000413 pp7; l
R PM L
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-413 UNIT catawba 1
.DATE 02 /14 /a6 COMPi.ETED'8Y J. A. Reavis TELEPHONE 704/373-7567 i
MONTH January, 1986 i
DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
(HWe-Ne t) 1 1 136 17 917 2
1 135 18 756 i
3 1 132 19 666 4
1 123 20 l
5 1 138 21 6
1 140 22 196 7
1 143 23 900 I
8 1 116 24 1 116 9
1 124 25 1 132 10 1 002 26 1 145 l
11 986 27 1 118 12 1 138 28 946 13 I 136 29 14 1 128 30 880 15 1 133 31 859 16 1 101 i
INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day 4
in the reporting month.
Compute to the nearest whole megawatt.
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-413 UNIT NAME Catawba 1 DATE 2/14/ 86 REPORT MDNTH January 1986 COMPLETED BY J.
A.
Reavis Page 1 "s_
TELEPHONE 704-373_--7567 O
o o,$
License Cause & Corrective y
cSG "c
uSE h
E Action to No.
Date
%h 8
y3 Event g
R YE 8
%Eb RE 82 H
o~
a:
Emo Report #
Prevent Recurrence mu vu 1-p 86-01-02 F
A CII PUMPXX liigh Feedwater Pump Inboard and Outboard Bearing Temp.
2-p 86-01-03 S
B CC TURBIN TAVG Reduced for Turbine Accept-ance Test- (testihg with Control Valves fully opened) 3-p 86-01-04 S
B CC VALVEX Control Valve Movement Test 4-p 86-01-08 S
B CC TURBIN Turbine Acceptance Testing 5-p 86-01-10 S
B CC TURBIN Turbine Acceptance Testing 6-p 86-01-13 F
A WA VALVEX VLV Actuator Failure on Service Water Makeup to Cooling Tower 7-p 86-01-13 F
A WA VALVEX Cooling Tower (IB) Secured to to Repair Makeup Control Valve 1
8-p 86-01-14 S
B CC TURBIN TAVG Reduced for Turbine Accept-ance Test (testing with Control Valves fully opened) 9-p 86-01-15 F
A IIF BLOWER Secured Cooling Tower 1B for Fan Repair 1
2 3
4 Reason:
Method:
Exhibit G - Instructions S Sc e led A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee i
C-Refueling 3-Autanatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NUREG-0161)
{
E-Operator Training G License Examination i
F-Adninistrative S
j G-Operational Error (Explain)
Exhibit I - Same Source II-Other (Explain)
- om)
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-413 UNIT NAME Catawba 1 DATE 2/14 / 86 REPORT MONTH January 1986 COMPLETED BY J.
A.
Reavis
_ Page 2
_ _ _ TELEPHONE 704-373-7567 E
oen$
License y
cause & Corrective c32 "c
o3E No.
Date
%b yy Event 5e 8
Action to o
gm, y,
5S E
YSo
$3
$3 5-ci ~
m z m ca Report #
mu vu Prevent Recurrence 10-p 86-01-16 F
A SG INSTRU Both Trains of Control Room Vent. Inoperable (Motor Temp.
Module Replaced) ll-p 86-01-16 F
A liF BLOWER Secured Cooling Tower IB for Fan Repair 12-p 86-01-17 S
B CC TURBIN Turbine Acceptance Testing 13-p 86-01-17 F
H ZZ ZZZZZZ Letdown Decreased While Swapping Mixed-Bed Demineralizers with Zenon Increasing 14-p 86-01-17 S
B CC TURBIN Turbine Acceptance Testing 15-p 86-01-19 S
F ZZ ZZZZZZ Notified by System Dispatcher Not to Increase Load 16-p 86-01-19 S
B CC TURBIN Turbine Acceptance Testing with Control Valve #4 Closed 1
86-01-19 F
58.47 A
3 Hli PUMPXX Reactor Trip Indirectly Due to C Heater Drain Tank PMP IC2 Trip (and TAT Alignment) 1 2
3 4
Reason:
Method:
Exhibit G - Instructions F
ced e}uled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Autmatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NUREG-0161)
E-Operator Training 6 License Examination F-Administrative 5
G-Operational Error (Explain)
Exhibit I - Same Source II-Other (Explain) o/';)
l UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-413 UNIT NAME Catawba 1 DATE 2-14-86
]
REPORT MONTH January 1986 COMPLETED BY J.
A.
Reavis j
Page 3 TELEPHONE 704-373 _7567 5
tj License y
Cause & Corrective c
22 "e
ca E
n
,5e, g
l No.
Date gg g
py Event Action to 4
5:E E
%5b R3 8B j
e-c~
a:
- c m o Report #
mo uo Prevent Recurrence 1
i 17-p 86-01-22 F
A lill VALVEX Feedwater IIeater IB2 Relief Valve f
Failure (Secured Power Inc.)
l 18-p 86-01-22 S
B CC TURBIN Main Turbine Power Load Unbalance j
Trip Test Preparations 19-p 86-01-22 P
B IB INSTRU Excore Nuclear Instrumentation Adjustment i
20-p 86-01-23 F
A Cil INSTRU liigh Feedwater 02 Content
.1 (Faulty Indication) 21-p 86-01-23 F
A Cli INSTRU Faulty 02 Meter Indicated High Feedwater 02 Content l 22-p 86-01-24 S
B CC TURBIN Turbine Acceptance Testing j 23-p 86-01-27 F
A HH VALVEX liigh Pressure Heater 1Al Normal Drain Control Valve Failure l2 86-01-28 F
26.30 A
3 HC VALVEX Low Condenser Vacuum Due to
}24-p l Cooling Tower IB Makeup Valve 86-01-30 F
A HA CKTBRK ' Main Generator Breaker 1B Repair f1 i
1 2
3 4
i Reason:
Method:
Exhibit G - Instnictions
[
A-Equipment Failure (Explain) 1-Manual for Preparation of Data C
led B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NUREG-0161)
E-Operator Training G License Examination F-Adninistrative 5
G-Operational Error (Explain)
Exhibit I - Same Source li-Other (Explain) 9/77)
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-413 UNIT NAME Catawba 1 DATE 2-14-86 REPORT MONTH January 1986 COMPLETED BY J.
A.
Reavis
._ Page j TELEPHONE 704-373-7s67 "s_
O o cny License y
Cause & Corrective c27 "c
v.5 $
5 g
No.
Date gy yy Event
,&r, gm, o
Action to 5E E
%5b EB 53 F
o-cr zmo Report #
mo av Prevent Recurrence 25-p 86-01-30 F
A IIC HTEXCII Low Main Condenser and Feedwater Pump 1A Condenser Vacuum i
26-p 86-01-31 F
B lill IITEXCli Peedwater Pump 1A Condenser i
Cleaning i
I t
i 1
2 3
4 Reason:
Method:
Exhibit G - Instructions 3
7g A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Miintenance or Test 2-Manual Scram Ent y Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NUREG-0161)
E-Operator Training 6 License Examination I
F-Adninistrative 5
G-Operational Error (Explain)
Exhibit I - Same Source II-Other (Explain) j9/77)
9 Docket No.: 50-413 Unit: Catawba 1 Date:
2/14/86 NARRATIVE SIMIARY Month: January, 1986 Catawba Unit i began the month at 100%.
Several power reductions occurred during the month due to Turbine Acceptance Testing. On January 15, the unit began reducing power because both trains of Control Room Ventilation were inoperable. One trair. was returned to service on January 16. The unit tripped January 19 during Turbine Acceptance Testing. The unit returned to service on January 22, but held at 20% power while a relief valve was repaired. The unit returned to 100% on January 24.
The unit operated at 100% until January 28, P
when vacuum on the Main condenser was lost during cooling tower screen cleaning.
The unit was back in service on January 29.
The unit finished the month at 90%
while cleaning cooling tower screens.
l
[
t
MONTHLY REFUELING INFORMATION REQUEST 1.
Facility name: Catawba Unit 1 2.
Scheduled next refueling shutdown: August, 1986 3.
Scheduled restart following refueling: October, 1986 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment? Yes If yes, what will these be? Technical Specification Revision If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions? N/A 5.
Scheduled date(s) for submitting proposed licensing action and supporting information:
N/A 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7.
Number of fuel assemblies (a) in the core: 193 (b) in the spent fuel pools 8.
Present licensed fuel pool capacity: 1418 Size of requested or planned increase:
9.
Projected date of last refueling which can be accommodated by present licensed capacity: August, 2008 DUKE POWER COMPANY DATE: February 15, 1986 Name of
Contact:
J. A.
Reavis Phones 704-373-7567
' CATAWBA NUCLEAR STATION Monthly Operating Status Report 1.
Personnel Exposure For the month of December, no individual (s) exceeded 10 percent of their allowable annual radiation dose limit.
2.
The total station liquid release for December has be compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
The total station gaseous release for December has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.