ML20151Y378
| ML20151Y378 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 09/14/1998 |
| From: | Geoffrey Edwards PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| Shared Package | |
| ML20151Y381 | List: |
| References | |
| NUDOCS 9809180215 | |
| Download: ML20151Y378 (4) | |
Text
II
=
e' Station Support Depcriment
.= sir _
l PECO NUCLEAR reco e"e<ov comoeev 965 Chestertwook Boulevard i
A Unit of PECO Energy wayne. PA 19087 5691 i
September 14,1998 l
Docket Nos. 50-277
'50-278 l
License Nos. DPR-44 DPR-56 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 l
Subject:
Peach Bottom Atomic Power Station, Units 2 and 3 Submittal of Final Technical Specifications Pages for l
License Change Application ECR 97-02809
References:
- 1) Letter from G. D. Edwards (PECO Energy Company (PECO Energy)), to U. S. Nuclear Regulatory Commission (USNRC),
dated March 20,1998
August 11,1998
Dear Sir / Madam:
In the Reference 1,2 and 3 letters, PECO Energy Company (PECO Energy) providad information concerning License Change Application (LCA) ECR 97-l 02809. This proposed change will revise the Technical Specifications (TS) to incorporate an End-of-Cycle Recirculation Pump Trip (EOC-RPT) System at i
PBAPS, Units 2 and 3. In the Reference 4 letter, PECO Energy provided final TS pages for this LCA. Based on additional discussions between PECO Energy and the U. S. Nuclear Regulatory Commission (USNRC) Project Manager, the 9809180215 980914 PDR ADOCK 05000277 I
P PDR
&\\
j
(
S:pt mber.14,1998 Pags 2 final TS pages for this LCA have been renumbered. Attached are these final TS pages which supersede all pages provided in the Reference 4 letter.
If you have any questions, please do not hesitate to contact us.
Very truly yours, a!
arrett D. Edwards Director - Licensing Attachment cc:
H. J. Miller, Administrator, Region I, USNRC A. C. McMurtray, USNRC Senior Resident inspector, PBAPS R. R. Janati, Commonwealth of Pennsylvania 4
=
l i
COMMONWEALTH OF PENNSYLVANIA:
ss.
COUNTY OF YORK Joseph J. Hagan, being first duly sworn, deposes and says:
l That he is Vice President of PECO Energy Company; that he has read the foregoing letter conceming License Change Application ECR 97-02809, for Peach Bottom Facility Operating Licenses DPR-44 and DPR-56, and knows the contents thereof; and that the statements and matters set forth therein are true and correct to the best of his knowledge, information and belief.
i D
(-
Vic President Subscribed and sworn to before me this /@ day of hdm/wt, 1998.
ou l e
l Notary Public NOTARIAL SEAL JANET L WILEY, NOTARY PUBuC PEACH BOTTOM TWR, YORK COUNTY,PA WYCOMMSSION EXPIRES JUNE 17,2002 l
I
TABLE OF CONTENTS 1.0 USE AND APPLICATION 1.1-1 1.1 Defir.itions 1.1-1 1.2-
-Logical Connectors...................
1.2-1
.l.3 Completion Times....................
1.3-1 1.4 Frequency 1.4-1
!~
2.0 SAFETY LIMITS (SLs) 2.0-1 2.1.
SLs' 2.0-1 2.2' SL Violations 2.0-1 i
'3.0
' LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY....
3.0-1 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY 3.0-4 3.1 REACTIVITY CONTROL SYSTEMS...............
3.1-1 3.1.1 SHUTDOWN MARGIN (SDM) 3.1-1 3.1.2 Reactivity Anomalies................
3.1 3.1.3 Control Rod OPERABILITY 3.1-7 L
3.1.4 Control Rod Scram Times 3.1-12 L
3.1.5 Control Rod Scram Accumulators...........
3.1-15 i
L 3.1.6 Rod Pattern Control 3.1-18 3.1.7.
- Standby Liquid Control (SLC) System 3.1-20 3.1.8 Scram Discharge Volume (SDV) Vent and Drain Valves.
3.1-26 l
l 3.2 POWER DISTRIBUTION LIMITS 3.2-1 l'
.3.2.1 AVERAGE PLANAR LINEAR HEAT GENERATION RATE I
(APLHGR) 3.2-1 3.2.2 MINIMUM CRITICAL POWER RATIO (MCPR) 3.2-2 L
3.2.3 1 LINEAR HEAT GENERATION RATE (LHGR) 3.2-4 L
3.3 INSTRUMENTATION 3.3-1 3.3.1.1 Reactor Protection System (RPS) Instrumentation 3.3-1
.3.3.2.1
. Wide Range Neutron' Monitor (WRNM) Instrumentation 3.3-10 3.3.1.2 Control Rod Block Instrumentation 3.3-16 3.3.2.2 Feedwater and Main Turbine High Water' Level Trip Instrumentation.................
3.3-22 l
3.3.3.1 Post Accident Monitoring (PAM) Instrumentation...
3.3-24 L
3.3.3.2 Remote Shutdown System...............
3.3-27 3.3.4.1 Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT) Instrumentation 3.3-29
.3.3.4.2-End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation.....
3.3-31a thru 3.3-31c 3.3.5.1 Emergency Core Cooling System (ECCS) Instrumentation 3.3-32 l
3.3.5.2 Reactor Core Isolation Cooling (RCIC) System l-Instrumentation.................
3.3-44 L
'3.3.6.1 Primary Containment Isolation Instrumentation 3.3-48
.3.3.6.2 Secondary Containment Isolation Instrumentation 3.3-55 3.3.7.1' Main Control Room Emergency Ventilation (MCREV) i-System Instrumentation 3.3-59 3.3.8.1 Loss of Power (LOP) Instrumentation 3.3-61 3.3.8.2 Reactor Protection System (RPS) Electric Power Monitoring.....................
3.3-66 (continued)
'PBAPS UNIT 2 i
Amendment No.
l
,___