ML20151U932

From kanterella
Jump to navigation Jump to search
Insp Repts 50-445/88-20 & 50-446/88-17 on 880302-0405. Violations Noted.Major Areas Inspected:Applicant Actions on Previous Insp Findings,Followup on Violations/Deviations, General Plant Area (Tours) & Piping Sys & Supports
ML20151U932
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/22/1988
From: Livermore H
NRC OFFICE OF SPECIAL PROJECTS
To:
Shared Package
ML20151U907 List:
References
50-445-88-20, 50-446-88-17, NUDOCS 8805020204
Download: ML20151U932 (24)


See also: IR 05000445/1988020

Text

_ _ _ _ . - _ _ _ _ . _ _ _ _ _ _ . _ _ _

_

__

_ _ _

_

_ _ _

-__

_ _ _ ___ _ __

_ _ _ -

_ _ .

.

' '.

.

.

.

4

APPENDIX B

U.

S. NUCLEAR REGULATORY COMMISSION

OFFICE'OF SPECIAL PROJECTS

NRC Inspection Report:

50-445/88-20

Permits: CPPR-126

50-446/88-17

CPPR-127

Dockets: 50-445

Category: A2

50-446

,

l

L

Construction Permit

Expiration Dates:

L

Unit 1: August 1, 1988

Unit 2: Extension request

submitted.

!

Applicant:

TU Electric

l

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas

75201

!;.

.

Comanche Peak Steam Electric Station (CPSES),

Facility Name:

Units 1 & 2

Inspection At:

Comanche Peak Site, Glen Rose, Texas

.

Inspection conducted:

March 2 through April 5, 1988

l

'

Inspection conducted by NRC consultants:

J. Dale - EG&G (paragraph 2a, 3a, and Sc)

K. Graham - Parameter (paragraph 3b, 5b, 7a and 7b)

P. Stanish - Parameter (paragraph 2b, 4, Sa, and 7c-7f)

l

l

Reviewed by:

FA4((8L 6

M

E

H. E. Livermore, Lead Senior Inspector

'Dat6

,

4-

yDR805020204 880422

ADOCK 05000445

l

g

DCD

,

<

,

, ..

<

.

'

<

t

'

.,

.

.

,

,

'

.

.

'

2

t

4

'

~ Inspection SummarN:

'

-

'

Inspection Conducted:

March 2 through April 5,

1988 (Report

'

-

'

50-445/88-20; 50-446/88-17)

,

,.

Areas ~ Inspected:

Unannounced, resident safety inspection of

applicant's actions on previous inspection findings; follow-up on

violations / deviations; Comanche Peak Response Team (CPRT)

issue-specific action plans'(ISAPs); Corrective Action Program

(CAP) for instrumentation and controls, mechanical, and cable tray

and cable tray supports; general plant area (tours); and piping

systems and supports.

Results:

Within the areas inspected, the NRC inspections

identified a relatively strong inspection and design verification

program in place for cable tray supports.

During the inspection,

three violations (failure to control nondestructive examinatica

processes, paragraph 5.b; failure to comply with procedural

requirements, paragraph 5.b; and f ailure to identify and verif:r

undersized welds, paragraph 5.c) and three unresolved iteme were

identifed, paragraphs 7.c, d, and e.

i

e

L

1

i

.

4

.

3

.

.

DETAILS

1.

Persons Contacted

  • R.

W. Ackley, Project Manager, Stone & Webster Engineering

Corporation (SWEC)

  • R. P. Baker, Licensing Compliance Manager, TU Electric
  • D. N. Bize, Licensing Compliance Supervisor, TU Electric
  • M. R. Blevins, Manager, Technical Support, TU Electric
  • J.

T. Conly, Lead Licensing Engineer, SWEC

  • W.

G. Counsil, Executive Vice President, TU Electric

  • C. G. Creamer, Instrumentation & Control (I&C) Engineering

Manager, TU Electric

  • G.

G. Davis, Nuclear Operations Inspection Report Iteri.

Coordinator, TU Electric

  • R. D. Delano, Licensing Engineer, TU Electric
  • M. D. Gaden, CPRT, IT Corporation
  • P. E. Halstead, Manager, Quality Control (QC), TU Electric
  • T.

L. Heatherly, Licensing Engineer, TU Electric

  • R. T. Jenkins, Manager, Mechanical Engineering, TU Electric
  • J. J. Kelley, Manager, Plant Operations, TU Electric
  • J.

J. LaMarca, Electrical Engineering Manager, TU Electric

  • O.

W. Lowe, Director of Engineering, TU Electric

  • D. M. McAfee, Manager, Quality Assurance (QA) TU Electric
  • J. W. Muffett, Manager of Civil Engineering, TU Electric
  • L. D. Nace, Vice President, Engineering & Construction,

TU Electric

  • D. E. Noss, QA Issue Interface Coordinator, TU Electric
  • D. M. Reynerson, Director of Construction, TU Electric
  • M. J. Riggs, Plant Evaluation Manager, Operations, TU Electric
  • A.

B. Scott, Vice President, Nuclear Operations, TU Electric

  • C.

E. Scott, Manager, Startup, TU Electric

  • J.

C. Smith, Plant Operations Staff, TU Electric

  • M.

R. Steclraan, CPRT, TU Electric

  • J.

F.

Streeter, Director, QA, TU Electric

  • T.

G. Tyler, Director of Projects, TU Electric

  • R. D. Walker, Manager of Nuclear Licensing, TU Electric

The NRC inspectors also interviewed other applicant employees

during this inspection period.

  • Denotes personnel present at the April 5, 1988, exit

meeting.

2.

Applicant Action on Previous Inspection Findings (92701)

a.

(closed) Unresolved Item (445/8513-U-01):

NRC inspection

of cable tray supports identified a generic concern with

'

Richmond insert bolting.

Gaps were detected between the

head of the bolt and the structural angle used es base of

'

the support.

Procedure QI-QP-ll.lC-2 requirce contact

between faying surfaces on bolted connections.

l

i

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ . _ _ _ _ _ _ _ _ _

_

. - _ _

_

.

.

<

.

.

.

..

,

.

.

4

The NRC inspector reviewed QI-QP-11.10-2, Revision 29

'

.

,

dated July 9,

1985, "Cable Tray Hanger Inspection," and

NQI-3.09-M-001, Revision 0 dated October 1,

1987,

'

'

"Modification Rework and 'As-Built' Inspection /

Verification of Cable Tray Hangers in Unit

1."

The

inspector also performed a visual inspection of Cable

Tray: Supports 1-6057, 1-6058, 1-5995 and 1-1973 along

with the related documentation with the following

results:

While QI-QP-11.10-2 requires contact between faying

surfaces, it also gives the acceptance criteria for bolts

that do not have full contact.

Section 3.1.2.9 of

QI-QP-11.10-2, Revision 4 dated July 9, 1985, states, in

part, "Where bolts are used on surfaces having slopes

greater than 1-in-20 with a plane normal to the bolt

axis, beveled olashers shall be provided to give full

bearing to the head or nut."

When the NRC inspector

reinspected the supports in question, he found them to be

within the limits (1-in-20) specified in the procedure.

This item is closed.

b.

(Closed) Open Item (445/8513-0-21):

This item dealt with

Evaluation Research Corporation (ERC) identifying a stud

with loose nuts during the piping flange inspection for

Verification Package I-M-PBOM-048, for flange No. 1 on

Drawing BRP-SW-1-SB-003.

Subsequently, Deficiency Report

(DR) I-M-PBOM-048-DR1 was generated and resulted in the

issuance of Nonconformance Report (NCR) M-23317N dated

May

E.,

1986.

The NCR initially required the reinspection by Brown and

Root (B&R) of the nonconforming condition, loose nuts on

the flange stud.

During the B&R reinspection, the

nonconforming condition identified by ERC and witnessed

by the NRC inspector could not be found;

i.e.,

all of the

nuts on the studs for the applicable pipe flange were

tightened.

The NCR was subsequently voided without

additional action occurring.

The initial NRC review,

documented in NRC Inspection Report 50-445/87-18;

50-446/87-14, of all available documentation associated

with the verification package revealed that there was no

record of work being performed by craft personnel in

which the deficient condition was corrected.

The inspection report in which this open item was

originally identified covered inspections performed

between Augus' 23 and September 30, 1985; and, as stated

above, NCR M-23317N was dated May 8,

1986.

The applicant

reviewed documeatation generated during this time period

and found that ERC had written an out-of-scope

observation on September 6, 1985, reporting this

.

.

.

.

.

'

5

.

.

condition.

In response to the out-of-scope observation,

NCR XI-198 was generated on September 27, 1985,

'

documenting the loose nuts on one stud.

The work

required to correct this situation was performed under a

work order dated October 18, 1985, and inspected on

November 6, 1985.

Therefore, based on the documentation

presented, this nonconforming condition was reported

twice by different inspectors and was closed out properly

'

'

prior to the issuance of NCR M-23317N.

This item is

closed.

3.

Follow-up on Violations / Deviations (92702)

n.

a.

(Closed) Violation (446/8509-V-01):

No identification

number was assigned and no measurement result was

recorded on the QC inspection report for the wall-to-pipe

centerline dimension shown on pipe Drawing

AF-2-006-412-533A dated April 27, 1985.

The applicant's response to this Notice of Violation

stated, in part, "We do not feel that this item is a

violation," and the following reasons were cited.

Section A.2 of Attachment 3 of QI-QAP-11.1-28

(Revision 30 through 32) provides exceptions to the

requirements of Section A.1 which states that "QC shall

assign a number to each dimensional attribute identified

as a specific dimension."

The exceptions are as follows:

"The dimensions related to hanger location / elevation and

angularity dimension related to snubber / sway-strut /

spring-can and structural members shall not be verified

by QCI."

Dimensions related to support location,

elevation, and angularity will be verified by CPSES

engineering per TNE Procedure CP-EI-4.5.1.

The NRC inspector reviewed B&R inspection Procedure

QI-QAP-11.1-28, Revisions 30 through 32,

Drawing AF-2-006-412-533A, reinspected the support

identified on the drawing, and reached the following

conclusion.

The measurement

entified by this violation is a

location dimens..on relating to the distance from the wall

and, as such, is covered by Section A.2; therefore, this

is not a violation.

This item is closed.

b.

(Open) Deviation (445/8607-D-01):

This deviation

pertains to TU Electric's failure to resolve unacceptable

seismic arrester bracket weld quality on safety-related

Valve 1-FV-2456.

NRC Inspection Report 50-445/88-11;

50-446/88-09 providen additional discussion of this

inspection finding.

'

--

_ _ _ _ _ _ _ _

-.

.

'.

.

6

.

.

NRC management and NRC inspectors met with TU Electric

personnel on March 10, 1988, to discuss resolution of

this issue.

Based upon a review of ASME Code

requirements, the NRC inspection staff believes that

TU Electric's declassification of the pipe support

installations from ASME Section III NF to the current

non-ASME Class 5 designation is inappropriate.

Valve 1-FV-2456 and the piping system in which the valve

is installed are required to meet ASME Section III design

and construction requirements.

Accordingly, the NRC

believes the supports attached to seismic arrestor

brackets on the valve actuators, which also function to

restrain and limit stresses in the piping system, should

be classified as ASME Section III NF component supports.

During this meeting, TU Electric disclosed that during

construction the pipe supports had been inspected to the

requirements of an ASME pipe support installation.

Revision of existing documentation, without performing

any physical rework, would permit the non-ASME supports

to be upgraded to their previous ASME classification.

The NRC inspection staff stated that upgrading these

supports to the ASME classification would resolve any

concern about interpretation of ASME code requirements

for classification of pipe supports.

On March 25, 1988, another meeting was held to discuss

l

the correct classification of the valve supports.

TU Electric stated that a further review of ASME Code

requirements had been performed.

Per paragraph NA-3253 of the 1974 Summer Edition of the

ASME B&PV Code, "The owner either directly or through his

agent, shall establish the code classification of the

items which comprise the nuclear power plant."

,

'

Additionally, several inquiries have been published

regarding the interpretation of jurisdictional

boundaries.

In each of these interpretations the

response has been "the owner is responsible for defining

jurisdictional boundaries of code items."

As applied to

the situation in question, TU Electric has determined the

valve actuator (nonpressure retaining) to be non-ASME.

As such, in accordance with this interpretation, the

rules of ASME B&PV Code.are not applicable, and the

actuator is not considered as an intervening element.

However, the valve actuator and snubber are modeled in

the stress analysis of the Class 3 piping system in

accordance with CPPP-7.

This would, therefore, tend to

indicate that the actuator is an intervening element and

the snubbers and brackets should be considered as part of

an ASME piping system.

To classify the snubber and

__

,

.

'.

.

.

.

7

bracket as av ASME Section III NF component supports

I

would require the N-5 data package to be revised and

potentially require a revision of the N-3 certification.

The owner has determined that the clips supplied on the

actuator by the manufacturer as well as the connecting

welds are of indeterminate quality; therefore, the owner

will remove the existing clips.and welds and replace-with

traceable material installed with qualified welders using

approved welding procedures.

The NRC inspection staff has discussed the classification

of these supports with the Chief Inspector, Boiler

Division of the Texas Department of Labor and Standards,

who is the state enforcement authority pertaining to this

issue.

4.

CPRT ISAPs:

Electrical Conduit Supports (ISAP I.c) (48063B)

1

a.

Evaluation Interaction of Nonseismic Train C Conduit

Greater Than 2" (NRC Reference 01.c.01.00)

l

The CPSES Damage Study Program evaluated all Train C

!

conduit greater than 2" in diameter in Seismic Category I

l

areas and the results of this study are contained in

!

ISAP II.d.

Ebasco has been assigned to evaluate the

l

integrity of Train C conduit and conduit supports greater

I

than 2" as part of their efforts in the CPSES Corrective

Action Program (CAP).

The NRC inspector has reviewed

Field Verification Method (FVM) CPE-EB-FVM-CS-033,

i

I

Revision 2, which demonstrates that there is no

difference in design philosophy for Train C conduit and

conduit supports for conduit greater than 2" from the

approach for safety-related Trains A and B.

Therefore,

this design approach precludes any adverse interaction

with safety-related conduit or equipment.

Inspection of

I

this item is complete.

No violations or deviations were identified.

j

b.

Review of Action Plan Item Number II.d (NRC Reference

01.c.01.01)

The NRC inspector reviewed the subject action plan which

was chartered to assure that the control room ceiling,

including anything attached to it or located above it,

met the requirements of Regulatory Guide 1.29 and FSAR

Section 3.7B.2.8; and that nonseismic structures;

i.e.,

Train C conduit, meet the seismic interaction provisions

of Regulatory Guide 1.29.

Procedures used for the damage

,

'

study (TNE-DC-23 and CP-EI-4.0-63) were reviewed.

The

NRC inspector is satisfied that this action plan

.

[4~

4

.

8

adequately addresses Train C conduit greater than 2" in

diameter.

Inspection of this item is now complete.

No violations or deviations were identified.

c.

Review of 2" and Greater Conduits which had Interactions

(NRC Reference 01.c.01.02)

The-NRC inspector has reviewed the following FVMs:

CPE-FVM-CS033, "As-Built Field Verification Method for

-

Design Control of Electrical Conduit Raceways for Unit 1

Installation in Unit 1 and Common Areas," and

CPE-FVM-CS-014, "As-Built Field Verification Method for

Design Control of Electrical Conduit Raceways for Unit 2

Installation in Unit 1 and Common Areas."

These

procedures, developed by Ebasco, guide the walkdown

verification efforts of the Post Construction Hardware

Validation Efforts (PCHVP) of the CAP for Train A and B

conduit and Train C conduit larger than 2".

The walkdown

data obcained through the inspections performed to these

procedures forms the input to Ebasco's design

verification efforts.

The design verification effort of

the CAP insures that this conduit and its supports will'

maintain its integrity during all postulated plant

events.

NRC inspection efforts are closely following the

efforts in this area by Ebasco to ensure compliance with

the applicable CAP procedures.

Therefore, in light of

the fact that the design approach precludes failures.

There will be no adverse interactions between Train C

conduit and safety-related commodities. Therefore,

interactions have been adequately addressed.

Inspection

of this item is completed.

No violations or deviations were identified.

d.

Selection of Random and Engineering Sample of 2" and

under Conduit Runs (NRC Reference 01.c.02.00)

The CPRT has identified 126 conduit runs in their random

sample and 131 conduit runs in their enginaered sample.

The engineered sample was selected from runs with highest

probability for failure (i.e.,

largest diameter, etc.).

The NRC inspector has reviewed the procedures for

selection of the two samples to assure compliance with

the CPRT program plan.

This program has been included in

the CAP and is reported in a separate Project Status

Report (PSR).

Inspection of this item is complete.

No violations or deviations were identified.

.

'

r..

.

w

.

.

9

s

e.

Population and Sample (NRC Reference 01.c.02.01)

The population of 2" Train C conduit and under is

approximately 13,500 conduit runs, which is broken down

as follows:

3/4" diameter - 55%; 1" diameter - 17%;

,

1 1/2" diameter - 19%; 2" diameter - 9%.

A random sample

was. selected from the two larger diameter populations

which represents approximately 3700 conduit runs.

A

sampla plan, consistent with CPRT requirements, selected

126 runs.to be. evaluated with a detection number of 2,

(i.e., The critical region is 3 or more deficiencies

found in the sample.)

In addition, an engineered sample

as discussed above was selected based on specific

"

criteria in an effort to identify those conduit runs

expected to exhibit more limiting behavior during a

seismic event.

Based on the NRC inspector's review of

the sampling procedures presented, the inspector is

satisfied that the sample selected is representative of

the entire population.

Therefore, inspection of this

item is complete.

No violations or deviations were identified,

f.

As-Built Physical Configuration Documentation (NRC

Reference 01.c.02.02)

Field verification of the installed conduit was performed

by Comanche Peak Project Engineering (CPPE) with a

third-party overview, in accordance with Engineering

Instruction CP-EI-4.0-64, "Field Verification of 2"

Diameter and Smaller Train C Conduit Support Systems."

The NRC inspector's review of the procedure revealed that

this procedure-complies with Appendix D of the CPRT

'

program plan, and the inspector is satisfied that the

required attributes are adequately addressed.

Inspection

of this item is complete.

l

No violations or deviations were identified.

Seismic Analysis and Acceptance Criteria (NRC Reference

g.

01.c.02.03)

The intent of this analysis is to provide quantitative

evidence that the conduit support system will perform its

'

intended function;

i.e., ensure the conduit does not fall

and cause an adverse intoraction with a safety-related

item.

The analysis method used was the same as was

applied to Seismic Category II support hardware.

The NRC

inspector reviewed the method of analysis and acceptance

l

criteria and is satisfied that the conduit and supports

being evaluated will be adequately addressed to ensure

. . . - ..

. _ _

_

. - -

_ - _ _ - _ _____ _-_ _ - -__ _ -_ _ _ _

-

.,

'

,

.

10

there will be no adverse interactions.with safety-related

equipment.

Inspection of this item is complete.

No violations.or deviations were identified.

h.

Damage Analysis (NRC Reference 01.c.02.04)

All selected runs were considered'for interaction with

safety-related targets due to sway or possible fall when

a run failed to meet support performance requirements.

The NRC inspector has reviewed Impell's project

instructions related to identification of safety-related

targets, establishing zones of influence for a potential

source commodity, and method for determining adverse

interactions and is satisfied that they represent a

comprehensive plan, with several levels of screening for

potential interactions, detailed calculation methods,

detailed ~rowork procedures, and record turnover

instructions that will ensure that all potential

interactions are identified and satisfactorily resolved.

Inspection of this item is complete.

No violations or deviations were identified.

-

1.

Population A'cceptance Criteria (NRC Reference 01.c.02.05)

Acceptance criteria requires that all identified

interactions be evaluated and that any conduit run

predicted t'o cause damage to a safety-related target be

considered deficient.

The NRC inspector reviewed the

method for accepting the entire population in light of

the above definition of a deficient condition and found

that it is consistent with a standard statistical

sampling procedure such as MIL-STD-105D.

Furthermore,

dispositions of deficient conditions are addressed

properly and the proposed corrective actions, rcdesign of

supports or rerouting of conduit are deemed satisfactory.

pection of this item is complete.

'

No violations or deviations were identified.

{

j.

Installation Quality Review (NRC Reference 01.c.02.06)

The NRC inspector has reviewed the varic w projec

instructions written by Impell - ich cover field

verification of the attributes neccssary ror the input to

their design verification efforts.

This data was

partially generated through a revaew of the quality

documentation generated during inspection of the initial

installation.

Based on this review, design verification

methods were established to ensure the integrity of any

Irain C conduit 2" in diameter and smaller which had a

,

_

_

' , .

n

,

. .

.

'

.

.

11^

,

potential adverse interaction with safety-related-

equipment.

Based on the NRC review of Impell's design

verification efforts, the NRC inspector is satisfied that

>

the methods used are conservative with respect to data

.

obtained from quality reviews.

NRC inspection on this

item is complete.

No violations or deviations were identified.

k.

Issuance of Results Report (NRC Reference 01.c.07.00

The Results Report for ISAP I.c has been issued and dated

October 28, 1987.

This report covers the actions

performed in response to NRC concerns relative to Train C

(nonsafety-related) conduit and its potential for adverse

impact on safety-related equipment.

Issuance of the

Rest 11ts Report completes this item.

The Results Report

will be reviewed in detail and reported on at a later

date.

No violations or deviations were identified.

5.

Corrective Action Plan (CAP)

NRC inspections were parformed to verify the applicant's

activities associated with the PCHVP.

The PCHVP was

established to reconcile the design to the appropriate design

bases for satisfying licensing commitments, and to reconcile

the harduare to the design;-i.e., the constructed / installed

systers meet the intent of the design.

The following CAPS

,

were inspected during this report period:

a.

Instrumentation and controls (52053)

t:

In this inspection period the NRC inspector reviewed

'

Procedure CPE-SWEC-FVM-1C-059, Revision 2, "Field

,

Verification Method Safety /Non-Safety Related

i

j

Instrumente.t'.on and Tubing Connected to ASME III Fluid

Systems and ANSI Safety Class Installations."

This FVM

, describes the engineering program for verifying and

l

ensuring that the installation of safety and

nonsafety-related instrumentation, tubing and related

supports connected to ASME III fluid systems, or ANSI

safety-class installations is in accordance with Project

Specification CPES-I-1018, Design Basis Document

DBD-EE-035 and Project Drawings 2323/ECE-I-001 and

2323-I-002 series.

The tasks described will be performed

by SWEC.

The walkdowns performed as part of the design

verif. cation are being performed by teams of engineers

f rom SWEC-CAP Engineering 11echanics Division ( EMD), and

l

!

,

+

-

- -,

- , , - . , . - , . .

_

_ _ _ _

_ _ _ _

'

,

12

.

the SWEC-cap Instruments and Control Division (I&C).

This FVM outlines responsibilities, defines applicable

codes, licensing documents, industry standards, project

specifications, design criteria documents, project

proceduros and. drawings, and design standards.

In

addition, it provides the detailed checklists ensuring

that all attributes necessary for design verification are

adequately addressed.

The NRC inspector selected walkdown Package

1634501-1-LT-932-(IWP)-190, Revision 0 dated December 16,

1987, for System 4800 in order to assess SWEC's

implementation of the above FVM.

This was done by

performing a walkdown/ inspection of this instrument loop

in accordance with FVM-069.

Items inspected by the NRC

inspector included instrument data, tubing data, tubing

layout, location of fittings, support evaluation,

instrument stands and disposition of unacceptable items.

During the NRC walkdown, several items appeared to differ

from the data reported by SWEC's walkdown personnel.

However, further review of project documentation;

i.e.,

NCRs, component modification cards (CMCs), design change

authorizaticns (DCAs), etc., revealed that all

identified, apparent discrepancies, in fact, had been

previously identified and properly dispositioned in

accordance with project procedures.

Immediate

determination that visual discrepancies had previously

been identified was not possible as TU Electric does not

hang tags on discrepant items.

No violations or deviations were identified.

b.

Mechanical (49063)

The CPRT reviewed historical revisions of procedures

related to piping bend fabrication.

The CPRT review

determined that the pipe bending procedure could cause

thinning af the pipe wall thickness to less than ASME

Section III code requirements after completion of the

bending process.

To resolve this issue, all safety-related pipe bends

performed at CPSES are being inspected to verify

acceptable minimum post-bend wall thickness.

Quality

control procedures require an ultrasonic digital

thickness measurement of these site fabricated bends.

The NRC inspector has reviewed the following B&R ASME

quality. procedures which provide the required

verification action for pipe bends:

s-

..

4

, . -

-

.

.

,

13

.

,

'AQP-ll.5 _ASME Component Installation Verification

.

. .

AQP-l*_.2

Fabrication and Installation Inspection of

Pipe Equipment

AQP-10.9

Ultrasonic Digital Thickness Measurement

.

The NRC. inspector reviewed the training files and records

for two of the B&R QC inspectors involved with. inspection

of-the site-fabricated pipe bends.

Training files and

records were determined to be current and complete.

The NRC inspector witnessed the B&R QC inspection of the

follouing two pipe bends:

Piping Isemetric

Pipe

Drawing No.

Spool No.

Material

Size

BRP-WP-X-AB-041 R/CP-2

lQ3

Stainless Steel

2"

Schd.40

BRP-WP-X-SB-014 R/CP-1

1Q2

Carbon Steel

3/4"

Schd.40-

The NRC inspector reccrded the following measuring and

test equipment (MTE) identification numbers, which were

being used by the QC inspectors daring performance of the

ul*rasonic digital thickness measurement, and determined

that calibration standards and controls were in

compliance with procedural requirements:

calibration

~~

Equipment Description

Serial No.

Due Date

Stress Tel T-Mike

MTE-5006

4/14/88

Carbon Steel Calibration

MTE-2043

4/22/88

Block

Stainless Steel Calibra-

MTE-2054

5/5/88

tion Block

While witnessing the QC inspection of the pipe bend

located on B2P-WP-X-SB-014, the NRC inspector noted that

the ultrasonic (UT, thickness measurement was being

performed through paint which had been previously applied

to the piping surface.

The failure to remove paint prior

to performing the UT inspection creates an error in the

measurements recorded by the QC inspector due to the

differ (nces in UT sound velocity.

Paint and the piping

material (carbon steel) have different UT sound

velocities.

In addition to this error, the thickness of

the paint had not been determined, recorded, and

subtracted from the QC recorded thickness dimension.

The

NRC inspector has determincd that Procedure AQP-10.9 is

inadaquate as implemented in that it does not require the

__

r~ -

. -

Ea

,

f. '

P

14

+

removal of paint from the examined surface.

Furthermore,

the UT calibration process is not representative of

actual field conditions.

The UT calibration block used

by the QC inspector does not have paint applied to its

surface.

Failure to control nondestructive examination

processes is a violation of Criterion IX

(50-445/8820-V-01; 50-446/8817-V-01).

While witnessing the QC inspection of the pipe bend on

Spool 1Q3 of Piping Isometric BRP-WP-X-AB-041, the NRC

inspector observed the QC inspector marking the stainless

steel pipe surface with ballpoint pen ink in order to

identify the areas where UT thickness measurements are

performed.

B&R ASME Quality Procedure AQP-10.7,

"Nondestructive Examination Marking Requirements,"

approves only the use of Nissen ink markers and Marsh

stencil ink markers for temporary marking of stainless

sreel surfaces.

This procedure does not approve the use

of any other type of ink marker.

Adherence to these

procedural requirements is necessary to prevent an

unacceptable stainless steel surface Halogen

contamination level which could change the mechanical and

chemical characteristics of the htateria) .

The failure to

comply with procedural requirements is a violation of

Criterion V (50-445/8820-V-02; 50-446/8817-V-02).

As a result of the NRC inspection findings, the applicant

issued Corrective Action Request (CAR)88-019 dated

March 25, 1988, to document that ASME Quality

Procedures AVP-11.5 and AQP-10.9 do not address UT

thickness measurements through paint.

This CAR resulted

in Stop Wc':k order (SWo)88-008.

NCR 88-05684 was issued

to document the use of an unapproved marker on a

stainless steel pipe surface.

The CPRT is responsible for overviewing the correctivz

actions resulting from CPRT findings.

In order to assure

that corrective actions are being effectively

implemented, CPRT overviews are required to be performed.

Discussions with project personnel indicate that

verification of proper implementation will be

accomplished by performing activity overviews and audits

of the TU Electric Technical Audit Program (TAP) and the

Engineering Functional Evaluation (EFE).

The NRC inspector contacted the TAP supervisor and

obtained a copy of the piping bend fabrication audit,

ATP-87-539, which was performed November 16 to

December 8, 1987.

The audit objective was to evaluate Comanche Peak

Engineering, SWEC, and B&R corrective actions taken in

_

_

_

__-__ __- ___ ._- _

.

-

'

. .

q,

.

15

response to ISAP VII.c, Results Report,. Revision 0,

Appendix 10, "Piping Bend Fabrication."

A checklist

' work' sheet: for the following three objectives was

completed by the auditors:

1.'

_ Verify that an adequate CAP exists for each

commitment audited.

.2.-

Verify that the CAP for the commitment has been

,

effectively implemented.

3.

_ Verify that the corrective action for the commitment

-

-has been properly documented in QA records.

The NRC inspector has reviewed the results of' TAP

'

Audit ATP-87-539 and found that this audit did.not

' identify any concerns relative to performr.nce of the UT

digital thickness measurements through paint primer and

paint, which creates error in the QC recorded thickness

measurements.

The NRC inspection staff will perform

additional evaluations of the effectiveness of the TAP in

a subsequent inspection report.

This activity is an open

item (50-445/8820-0-03).

c.

Cable Tray and cable Tray supports (48053)

The cable tray / cable tray support portion of the CAP was

initiated with the following objectives:

Demonstrate that the design of safety-related

.

systems, structures and components complies with

licensing commitments.

Demonstrate that existing systems, structures, and

.

components are in compliance with the design

requirements or develop modifications which will

bring systems, structures, and components into

compliance with design requirements.

Develop procedures, an organizational plan, and

.

documentation to maintain compliance with licensing

commitments through the life of CPSES.

The Cable Tray and Cable Tray Hanger Project Status

Por7rt (PSR) describes the validation effort, traces the

updating of design / installation specifications and the

construction /QC procedures.

The NRC inspector has

performed a preliminary review of these procedures and

will evaluate their adequacy during future inspections.

The implementing procedures were evaluated to determine

whether:

,

.-

.

'.

,

'

.

16

Means have been established to ensure that any

.

design and field changes from approved drawings are

controlled and processed commensurate with the

original design control activities.

=

Procedures and instructions have been approved and

.

means established to ensure that quality

requirements are met.

i

The NRC inspector performed documentation reviews and

field inspections of the following cable tray supports to

determine the adequacy of the applicant's installation

and QC records.

The supports had been completed by

construction and bought-off as complete by inspection.

Support

Location

Unit

CTH-1-01336

Reactor bldg.

1

CTH-1-06537

Reactor bldg.

1

CTH-1-06538'

Reactor bldg.

1

CTH-1-06539

Reactor bldg.

1

CTH-1-06544

Reactor bldg.

1

CTH-1-06550

Reactor bldg.

1

I

CTH-1-06555

Reactor bldg.

1

CTH-1-06560

Reactor bldg.

1

CTH-1-12057

Reactor bldg.

1

CTH-1-00820

Safeguards bldg.

1

CTH-1-01317

Safeguards bldg.

1

CTH-1-02008

Safeguards bldg.

1

CTH-1-02470

Safeguards bldg.

1

CTH-1-06974

Safeguards bldg.

1

CTH-1-06978

Safeguards bldg.

1

CTH-1-07129

Safeguards bldg.

1

l

CTH-1-01345

Auxiliary bldg.

1

CTH-1-01616

Auxiliary bldg.

1

CTH-1-01916

Auxiliary bldg.

1

'

CTH-1-01950

Auxiliary bldg.

CTH-1-02804

Auxiliary bldg.

CTH-1-02825

Auxiliary bldg.

1

CTH-1-07279

Auxiliary bldg.

1

CTH-1-01711

Fuel handling bldg.

1

CTH-1-01735

Fuel handling bldg.

1

CTH-1-01741

Fuel handling bldg.

1

UTH-1-01957

Fuel handling bldg.

1

CTH-1-02010

Diesel generator bldg.

1

CTH-1-02013

Diesel generator bldg.

1

CTH-1-02038

Diesel generator bldg.

1

NRC inspection of Cable Tray Supports CTH-1-06537 and

l

CTH-1-12057 identified three undersize welds, weld No. 2NS 7A

and 7B, respectively.

All three welds were undersize by 1/16"

,

to 1/8" for the full length of the weld.

l

l

[

..

.

.

,

17

TU Electric Procedure QI-QP-11.10-9, "Visual Weld Acceptance

Criteria for Structural Welding at Nuclear Power Plants,"

states that a weld can be undersized by 1/16" for 25% of its

length.

AWS Dl.1 criteria states that if member separation is

greater than 1/16", the fillet weld size will be increased by

the amount of-the separation.

The three subject welds were

undersize for 100% of their length.

This failure to identify

and verify the undersize welds is a violation of

Procedure Ql-QP-11.10-9 and its applicable acceptance ;riteria

(445/8820-V-04).

The NRC inspector notes that a total of 408 welds were

inspected for approximately 2500 attributes with only

3 attributes found to be incorrect.

The NRC inspector was

impressed with the quality-of both the documentation and the

physical work he inspected in cable tray supports.

6.

Plant Tours (92700)

The NRC inspectors made frequent tours of Unit 1 and common

areas of the facility to observe items such as housekeeping,

equipment protection, and in-process work activities.

No

violations or deviations were identified and no items of

significance were observed.

7.

gj. ping Systems and Supports (50090)

)

a.

During this inspection period, the NRC inspector

performed tours of various areas of Unit 1 to verify

control of activities related to welding of pipe supports

on the evening shift.

The NRC inspector interviewed five B&R welders, welder

symbols CUX, CUW, BZR, CSU, and BDB, to determine their

knowledge of work control requirements.

All welders

interviewed were cognizant of applicable requirements.

The NRC inspector noted that a copy of the welding

procedure specification (WPS) which defines all welding

parameters was issued with the weld filler material and

attached to the weld filler material storage container

for use by the welder.

The NRC inspector recorded the welder's symbol

designation, weld procedure specification number being

used, heat code of weld filler material being used,

serial number of filler material storage container, and

calibration due date of filler material storage

container.

Weld filler material is not issued to a

welder unless the welder is certified to the WPS

specified in the construction operation traveler, and the

welder's certification is current.

The NRC inspector

compared the recorded information with records which are

,

-

_ __ ____ _______

O

.

.

.

,

.

.

18

maintained at the weld filler material issue location.

NRC inspection determined that the welders interviewed

were certified to the WPS being used and that weld filler

material control was in compliance with project

procedures.

No violations or deviations were identified.

b.

During a CPRT related inspection of the installation of

Unit 1 containment spray system box-frame supports

(reference NRC Inspection Report 50-445/85-14;

50-446/85-11), the NRC inspector observed that clearances

exist between the pipe and the pipe support, indicating

that the pipe support was not supporting the piping

system.

Project inspection procedures permit a maximum

of a 1/8" gap to exist between the bottom of the pipe and

the pipe support.

The gap conditions identified above

increase loading on adjacent pipe supports and increase

stresses on the piping system.

The conditions identified above have been addressed by

SWEC as a part of the design requalification program for

piping and pipe supports.

SWEC has performed

Calculation GENX-255 to determine the effect of

deadweight gap on pipe stresses and pipe supports.

The

SWEC calculation evaluated the potential increase in

piping stress and support loads for various enveloping

cases.

For pipe stress, the potential increase due to

the gap was found to be 12 %.

For the specific case of

the containment spray header supports where several

box-frame supports exist adjacent to one another, SWEC

has determined that each support is capable of

withstanding the edditional dead weight of the piping

assuming two consecutive suppcrts are missing.

The SWEC

report found that all the containment spray supports have

a minimum safety factor of three to their designed dead

load without exceeding ASME Code requirements.

Thus, the

safety margin ensures that the 1/8" gap between the

bottom of the pipe and the support will not cause an

overstress of the pipe and pipe supports.

The NRC inspectors have reviewed SWEC Calculation

GENX-255 dated October 26, 1887, and found the evaluation

to be adequate and concur with the conclusions reached.

On a plant tour the NRC inspector observed that there

c.

were no washers under the bolt head on the mechanical

shock arresters which were assembled using high strength

bolting.

Paragraph NF4724 of ASME Section III,

subsection NF, states that high strength structural

bolting will be tightened to a torque value not less than

that given in the design specification; and, further,

that if the tightening is performed by means of a

calibrated wrench that a hardened washer should be used

1

x

Q

',

.4

19

' under the bolt head in'this application. .The code uses

the word "structural" in this paragraph; however, since-

- Subsection NF is-not a structural code, the apparent

implication is that hardened washers should be installed

when utilizing what would normally be considered as a

high strength-structural bolt _within the jurisdictional-

boundaries of this subsection.

Review of the design

m

specification reveals that there are no torque values

given for several of the high strength bolt sizes used in

this particular application.

This_ item was discussed

with the utility and contractor personnel who felt since

these bolts were not being used in a classically defined

structural capacity that NF4724 is not applicable;

however, they committed to request.a code _ interpretation

of this paragraph relative to this particular

application.

This item will remain unresolved pending

receipt and acceptance of the code committee

Einterpretation (445/8820-U-05).

'

u

On one-of two material certifications reviewed by the NRC

d..

inspector in an~ attempt to identify the bolt material

e

<

<

used for' assembling mechanical shock arrester assemblies,

-

Nuclear Power Services, Inc. (NPSI), the vendor for these

units, supplied a certificate of compliance stating that

the bolt material was SA-307-GR.A.

SA-307-GR,A was not

'

added;t'o Section III, via Code Case N-249, until 1985;

1

i

however NPSI's certification was dated in 1981.

Again,

discussing this with the applicant, it was stated that

'

ASTM-A307-GR.A appeared in the code, Code Case 1644-2, in

1975 and in accordance with the requirements in NA-1220

the SA-307-GR.A would be acceptable.

However, NA-1220

states, in part, "Materials produced under an American

Society for Testing and Materials (ASTM) designation may

be accepted as complying with the corresponding ASME

specification provided the ASME specification is

designated as being identical with the ASTM specification

for the grade, class, or type produced and provided that

the material is confirmed as complying with the ASTM

specification by a Certified Mill Test Report or

"

Certification from the Material Manufacturer .

. . .

The code appears to allow substitution of ASTM material

for AGME materials, but the rev nse of this is not

addreseed; further, the certificate of compliance for the

material was supplied by NPSI who is not the material

manufacturer of the bolting material.

This item will-

remain unresolved pending further review by the applicant

(445/8820-U-06).

1

e.

As a result of documentation reviews, the NRC inspector

observed that for structural frames and mechanical shock

arresters the effects of seismic accelerations have been

included in the evaluation of allowable stresses and

>

1

-

-

-

-

-

- -

.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

,

.

.i

.

-

20

loadings.

However, for rigid sway struts this type of

evaluation apparently has not been performed and the NRC

inspector has observed that there are several very long

struts being utilized (installed) in the plant.

Inclusion of the self weight excitation in the evaluation

of these compression members may reduce their rated

capacity.

The applicant has requested that SWEC evaluate

the impact, if any, of this concern on the struts being

used on the site.

This item will remain unresolved

pending completion of SWEC's evaluation (445/8320-U-07).

f.

On March 4, 1988, a meeting was held between members of

NRC Office of Special Projects, TU Electric, SWEC, and

NPSI to discuss concerns relative to snubber

installations and supports in general.

The items

discussed were:

(1)

Clearances on end attachments of snubber.i and struts

The concern is that excessive clearances would

adversely effect the stiffness of these items and

i

that change may impact the piping analysis; also,

that impact loads due to excessive clearances may

impair operability of the snubbers.

TU Electric

presented arguments to show that the existing

conditions are acceptable from a piping analyais

standpoint.

This is based on a parametric study

previously performed which concluded that changes in

,

stiffness have minimal effects on system response

and support loads until the change in stiffness

exceeds an order of magnitude.

The applicant will

provide the NRC with a copy of this study for

further review.

As for the effects of the impact load on the

,

l

snubber, the applicant stated that this is

conceptually similar to the manner in which loads

are applied to a box-frame type restraint assembly.

However, the NRC inspector stated that there have

been instances where mechanical shock arresters have

been damaged (broken' by the impact caused by

dropping the units on end and that this is similar

!

to the loading caused by excessive clearances in the

end connections.

The applicant committed to pursue

this matter further with pacific Scientific, Inc.

(PSI), the manufacturer of the shock arrester base

units to get their concurrence that this condition

is acceptable.

Also, all dual snubbers are being

ir.spected for end clearances per the latest

requirements of NUREG-0800 (SRP), Section 3.9.3.

Those not in compliance will be replaced.

This item

was previously reported in Inspection

.

-

-

_

-,

u

-

[a,

-

.

21

Report 50-445/88-11; 50-446/88-09 and will'be

tracked as 445/8811-U-03.

~

(2)

PSA 35 and 100 snubber adaptors not torqued into

snubber body

The concern is that by not preloading this

connection that the units installed on site are not

representative of PSA qualification units.

The

applicant stated that these units are in compliance

with the CPSES specification and, as above, the

change in stiffness will not have a significant-

impact on the piping analysis.

The same actions

will be taken on this item as in Item 1 above.

This

item was previously reported in Inspection Report

50-445/88-11; 50-446/88-09 and will be tracked as

445/8711-U-04.

(3)

Preloads applied to A307 bolts in transition kits

for mechanical shock arrester

The concern is that the installation procedure for

these units uses the torque values specified by PSI;

however, PSI only uses high strength bolts in this

application.- At these torque values, the induced

tensile stress in the bolt exceeds code allowable at

room temperature and yield strength at design

temperature.

Also, A307 will not hold the preload

which will effect the stiffness of the units.

The

applicant stated that to increase the design margins

for these assemblies the A307 bolts will be replaced

by high strength bolting and will advise the NRC

when this program commences and is complete.

The

response to stiffness concern is similar to the

response in Items 1 and 2.

This item was previously

reported in Inspection Report 50-445/88-11;

50-446/88-09 and will be tracked as 445-8811-U-05.

(4)

Evaluation of local stresses in wide flanges

The NRC inspector had reviewed three SWEC

calculation packages and found that in each case the

engineer did not check all the local stresses (i.e.;

flange bending and web crippling) as required by

CPPP-7, Revision 3.

In response to this item,

DR-C-88-01165- was issued.

SWEC sampled 1200

calcalations; of these calculations, 15 of the

supports had wide flanges.

In addition to the

calculations identified by the NRC, four

calculations had not evaluated both web crippling

and flange bending.

SWEC performed the necessary

calculations and determined that all seven supports

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _

'

q_

,

'

.

J*

.

-

'

~

22

.

were-acceptable as designed.

SWEC committed to

emphasize these attributes in'CPPP-7, Revision 4,

training and to add checklist items to the final

reconciliation checklist to cover these items.

Th!.s

-item was previously reported in Inspection Report.

50-445/88-11; 50-446/88-09 and will be tracked as

445/8811-U-02.

- (5)

Sway Strut CS-1-912-001-SS2R which appeared to have

excessive play in the threaded connection

,

Further evaluation by the applicant revealed that

the play was well within the tolerances allowed by

the code.

(6)

Dents in dust cover for the constant support on'

MSl-001-001-c72S

The concern was that the damage caused to the dust

cover may have also damaged the spring coil and was

thus not fully evaluated.

The applicant is in the

'

process of issuing an additional NCR to obtain a

.

complete evaluation.

(7)

Snubber design temperature on NPSI Certified Design

Report Summary (CDRS)

PSI's design reporg for these units lists a design

temperature of 300

Fahrenhgit and NPSI's C'DRS gave

a design temperature of 350

Fahrenheit.

(This was

not a site concern since there are no postulated

g

operating conditions which exceed 300

Fahrenheit.)

NPSI stated that this was the temperature that

appeared on Revisions 0 and 1 of their CDRS (which

PSI does reference in their des?.gn specification,

but limits exposure time to 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />).

NPSI stated,

based

n their discussions with PSI, tgeydecidedto

reduce their design temperature to 300

Fahrenheit.

This was done on Revision 2 of their CDRS issued on

J.ugust 1, 1983.

Therefore, the revised CDRS is

consistent with the manufacturer's data and is

considered to be acceptable.

(8)

Preloaded bolts on snubbers with no hardened washers

The applicant's response to this item was that since

the design specification did not require these bolts

to be proloaded that the torque applied is for

workmanship only; therefore, it is not necessary to

use hardened washers.

Also, these bolts are not

"structural" bolts.

However, since the bolts they

are going to install are high strength, the

,

t

-

+

-

. _ - - __

_

. - _ - - -

--

_

- - _ - - - -

a ao

j-

3

,

,.

.

..

23

applicant committed to investigate whether a code

interpretation exists to cover this item. .If not,

they will pursue one and they further committed ~to

abide by the result.

(9)

Material-certification

The concern was that the NRC inspector reviewed two

certificates'of compliance for bolt material and

found apparent inconsistencies in each.

On one, the

bolt material was certified to ASTM-A307-GR.B which

is not in the code.

However, the applicant advised

that NA-1220 allows the use of ASTM materials

provided the ASME specification is designated as

identical to the ASTM specification.

The other

example was bolting that was certified to

SA-307-GR.A in 1981; this material was added to the

code in 1985.

They stated that ASTM-A307-GR.A was

in Code Case 1644-2 in 1975; therefore, the material

was acceptable.

However, since the code allows

going from ASME material to ASTM, it does not

specifically allow going from a code case material

to a ASME material; therefore, the. applicant

committed to do further investigation.

Also, the

applicant will research when SA-307-GR.A was

included in St?'. ion II of the ASME Code.

(10) Side loads on sway struts

i

The NRC inspector-brought up the fact that NPSI has,-

in their CDRs, addressed side loads on snubbers due

to seismic accelerations in the axis perpendicular

to the snubber.

SWEC in their evaluation of

structural members used as pipe supports / restraints

evaluates the effects of seismic acceleration 1 cads

due to the self-weight of the members.

Therefore,

the NRC inspector asked how this was evaluated for

sway struts.

In response to this, the applicant has

requested SWEC to perform an evaluation of whether

this needs to be evaluated for the comanche Peak

Project.

8.

Unresolved Items

Unresolved items are matters abour which more information is

!

rcquired in order to ascertain whether they are acceptable

items, violations, or deviations.

Three unresolved items

disclosed during the inspection are discussed in

paragraphs 7c, 7d, and 70.

.

i

__

L (U\\ ' [

Iil<;

'

~[

s

'

'

,,

"f'.'

g :oi

I*

-

-

,

-

.

24

,

9.

Open Items

open items are matters which have been discussed with the

applicant, which will be reviewed further by the inspector,

and which involve some action on the part of the NRC or

applicant or both,

one open item disclosed during the

inspection is discussed in paragraph 5b.

10.

Exit Meetino (30703)

An exit meeting was conducted April 5, 1988, with.the

applicant's representatives identified in paragraph 1 of this

report.

No written material was provided to the applicant by

the inspectors during this reporting period.

The applicant

did not identify as proprietary any of the materials provided

to or reviewed by the inspectors during this inspection.

During this meeting, the NRC inspectors summarized the scope

and findings of the inspection.

.

O

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ . _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ . _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _