ML20151U379

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-361/88-10 & 50-362/88-10 on 880516-27 & 0606-10 & Notices of Violation & Deviation
ML20151U379
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 08/03/1988
From: Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Fogarty D
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML20151U382 List:
References
NUDOCS 8808190064
Download: ML20151U379 (5)


See also: IR 05000361/1988010

Text

$4

'

f

o

UNITO STATES

!,

NUCLEAR REGULATORY COMMISSION

o

$

I

R4 TON V

'4

@

1450 MARIA LANE,SUlTE 210

W ALNUT CRE E K, C ALIFORNI A 94596

% . . . . . ,o

AUG 0 31983

'

Docket Nos. 50-361

50-362

Southern California Edison Company

P. O. Box 800

2244 Walnut Grove Avenue

Rosemead, California 91770

Attention:

Mr. David J. Fogarty, Executive Vice President

SUBJECT:

NRC INSPECTION OF SAN ONOFRE NUCLEAR GENERATING STATION

UNITS NO. 2/3

Gentlemen:

This refers to the special team inspection of May 16-27 and June 6-10, 1988,

conducted by Mr. S. A. Richards and other members of our staff, of activities

authorized by NRC License Nos. NPF-10 and NPF-15 and to the discussion of our

findings held with you and members of your staff on June 10, 1988.

.

i

Areas examined during this inspection are described in the enclosed inspection

report.

Within these areas, the inspection consisted of selective

,

examinations of procedures and representative records, interviews wit!.

!

personnel, and observations by the inspectors.

Based on the results of this inspection, it appears that certain of your

activities were not conducted in full compliance with NRC requirements, as set

forth in the Notice of Violation and Notice of Deviation, enclosed herewith as

Appendices A and B.

Your response to these notices is to be submitted in

accordance with the provisions stated in the Notice of Viola' ion and Notice of

Deviation.

l

Inspection Overview

,

The inspection conducted by the teem was a safety system functional inspection

(SSFI).

The objective of this SSFI was to asst:ss the operational readiness of

the component cooling water (CCW) and salt water cooling (SWC) systems under

operational and analyzed accident conditions.

These systems were selected

because it is considered essential that they function correctly following an

event such as a loss of offsite power, a Safe Shutdown Earthquake (SSE), or a

major plant transient.

Additionally, Probabilistic Risk Assessment studies of

i

pressurized water reactors have indicated that the failure of these systems,

'

during a major plant transient, or event, generally contributes highly to the

probability of occurrence of a core melt event or an event with significant

4

offsite consequences.

In assessing the operational readiness of these

systems, the team focused heavily on the following three broad questions:

\\\\

8808190064 880803

/

PDR

ADOCK 05000361

i

O

PDC

'4 fl

'

i

l

f

I

2

AUG 0 31908

i

Do SCE engineers have a full knowledge of, and ready access to,

accurate design information for the Unit 2/3 safety systems?

'

Is the technical work performed by SCE engineers and contractors of

a consistently high quality, and does SCE maintain a level of

in-house engineering :apability which is sufficient to both oversee

contractor work and to ensure a continuing base of company knowledge

-

of the basic plant design?

Are operations, maintenance, and testing activities conducted in a

manner which is consistent with the design bases, regulatory

requirements, and industry practices, such that safety system

operability is ensured over the life of the facility?

Overall Conclusions

The team reached the following basic conclusions:

SCE engineering does not fully understand the basic design of the

systems reviewed and does not have ready access to accurate design

information.

.

Technical work is not alw lys performed in a complete, technically

correct manner. With regard to San Onofre Nuclear Generating

Station (SONGS) Units 2/3, SCE is heavily reliant on contractors for

l

the performance of technical work.

Deficiencies were identified with the testing, maintenance, and

operation of the selected systems.

Many of these deficiencies

,

appear to be related to a less than full knowledge of or access to

the system's basic design on the part of your staff.

l

The above conclusions were based on inspection findings made by both our team

and by your own internal reviews.

Examples of these findings are as follows:

The design of the CCW system erroneously did not consider a single

active failure with a safe shutdown earthquake.

SCE was apparently,

until recently, unaware of this requirement.

.

The CCW system has been almost exclusively operated during the

commercial life of Unit 2/3 in a manner contrary to that described

in the Final Safety Analysis Report (FSAR).

Although this fact was

recently identified by SCE engineers, the significance of this

deficiency was not recognized.

'

,

The reevaluation of the CCW system accident response by SCE

engineers indicates that the original accident analysis for this

system was inadequate.

The FSAR was noted to contain numerous errors.

The FSAR description

of the CCW system response under accident conditions was observed to

be inaccurate or incomplete.

<

_ _ .

,

__

-

__

- - -

__ .__

..

3

AllG 0 31988

,

A number of calculations related to the design of the systems

reviewed were found to be out of date or contained assumptions that

had not been verified.

Calculations and analyses were identified that did not always

consider the worst case conditions or did not correctly consider

instrument inaccuracius.

Certain system design aspects were found to be inadequate, such as

)

CCW system leakage; water flow available to the SWC pumps following

a seismic event; and the non-seismic design of the CCW surge tank

outlet valve control circuits.

Additionally, as we discussed with you at the team exit meeting, the team

reviewed the results available from your own internal review efforts.

We

understand that these efforts were intended to either prepare for our

inspection, or as actions in response to recent engineering problems.

These

1

efforts included the preparation of "State of the System" reports by your

l

en-site cognizant engineers, based on a dedicated 4-6 week review of their

'

>1gned systems; the performance of a design control audit by your Quality

murance organization, which involved over 5500 man-hours and 6 months to

'

complete; the performance of a limited scope internal SSFI; and the assembly

of recently drafted design reports.

To the extent that the results of these

,

efforts were available, the team found the results to be consistent with the

tu W s findings and strongly indicative of the need for SCE to make a

significant commitment to increasing your techr.ical capability; to take action

i

to recapture the basic design information for your facility; and to ensure

)

that that information is maintained in the future.

These conclusions are also

supported by several recent engineering problems at SONGS including the Unit 1

Environmental Qualification issues, the Unit 1 Emergency Diesel Generator

overload issue, the Unit 1 steam line pressure single failure problems, and

1

the findings of the 1987 NRC team inspection with regard to the Unit 1 safety

related batteries.

We stated at the exit meeting that the team had not found the CCW system to be

inoperable at the time of inspection, however, due to the number of questions

and concerns which have recently been raised regarding the system by both your

staff and the NRC, we strongly encouraged you to perform a prompt, thorough,

reassessment of the entire system.

We have received your correspondence of

June 24, 1988, in which you indicate that the initial phase of your

reassessment has been completed. We urge you to continue to aggressively

pursue this reassessment.

P1mase keep us informed of the results of your

efforts.

.

At the exit meeting, you stated your acceptance of the basic team findings.

l

You also discussed actions you have in progress to address these issues,

including the formation of a Design Process Task Force, a commitment to

additional training of eagineering personnel, the initiation of efforts to

assemble design basis ducuments, and the continuation of Quality Assurance

.

audits of technical work.

You further stated that a more detailed discussion

i

of your plans to addre6s the above issues would be provided at an upcoming

j

NRC/SCE management meeting.

In addition, we request that you provide a

written description o$ your action plan within 60 days of the date of this

1etter.

Please ensLi-e that you address those actions planned to accurately

__

e.

4

AUG 0 31039

update the Final Safety Analysis Report (FSAR) and to maintain the FSAR

current in the future.

We anticipate meeting with you periodically to discuss

the status of your actions.

A somewhat separate issue we wish to highlight is your lack of communication

with the NRC regarding the issues you have encountered with the CCW system.

In the enclosed inspection report, we have concluded that you failed to report

several conditions which we consider to have been reportable in accordance

with regulatory requirements.

Although we recognize that the reportability

requirements allow for a degree of engineering judgement for certain types of

issues, we remain disappointed that you did not bring your reevaluation of the

CCW system to our attention earlier, due solely to the number and significance

of issues surrounding the reevaluation.

In the interest of maintaining open

and straight-forward lines of communication between the NRC and SCE, we

strongly urge you to lower your threshold for discussing developing issues and

problems with us.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosures

will be placed in the NRC Public Document Room.

The responses directed by this letter and the attached Notice are not subject

to the c1'earance procedures of the Office of Management and Budget as required

by the Paperwork Reduction Act of 1980, PL 96-511.

Should you have any questions concerning this inspection, we will be glad to

discuss them with you.

Sine ely,

,

J. B. Martin

Regional Administrator

Enclosures:

A.

Appendix A. Notice of Violation

B.

Appendix B, Notice of Deviation

<

C.

Appendix C, Summary of Significant Findings

D.

Inspection Report No. 50-361/88-10

50-362/88-10

'

cc w/ enclosures:

t

K. P. Baskin, SCE

C. B. McCarthy, SCE

H. E. Morgan, SCE (San Clemente)

i

State of CA

i

,

\\

.

~

, .

5

.

AUG 0 31983

bec w/ enclosures:

RSB/ Document Control Desk (RIDS) (IE01)

D. Persinko, NRR/LPEB

C. Haughney, NRR/ SIB

D. Hickman, NRR/PDS

M. Johnson, EDO Project Inspector

Resident Inspector

R. Huey (2)

G. Cook

A. Toth

B. Faulkenberry

J. Martin

Docket File

bec w/o enclosure 0:

LFMB

H. Smith

TG't f*A;.:

k$

qfn

c.rn

JMelfi

CJMyers

JERussell

JR;Iall

RCBarr

7/M /88

7/sr/88

ffb /88

1/R/88

7Q!88

RE UEST COPY ] REQUEST COPY ] R UEST COPY ]

ST COPY ] R QUEST COPY ]

/ NO

1 YED / NO

]

S / NO

YES / NO

] E

/ NO

]

SARt

s

RJPate

ADJohnson

bh

7/M/88

7/ /88

7/ /88

$//f/88

EST COPY ] REQUEST COPY ] REQUEST COPY ] R UEST COPY ]

YES / NO

] YES / NO

] YES / H0

YES / NO

]

l

_

TO PDR ]

YES / NO

]

..

. ,.... ... . a

..m

wr a a ncyucsi t,urt j NtQUtbl COPY ] REQUEST COPY ]

YES / NO

] YES / NO

] YES /, NO

] YES / NO

] YES / NO

]

'

SARichards

RJPate

ADJ

son

DFKirsch

i

7/ /88

74f/88

7/ /88

REQUEST COPY ] R

EST COPY ] REQUEST

] REQUEST COPY ]

YES / NO

] ES / NO

] YES /

0

] YES / NO

]

l

V

V

j

.

D TO POR ]

ES / NO

]

-

. .

.

h