ML20151N871

From kanterella
Jump to navigation Jump to search
Insp Repts 50-313/88-02 & 50-368/88-02 on 880221-26. Violation Noted.Major Areas Inspected:Radiation Protection Activities During Unit 2 Refueling Outage
ML20151N871
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 04/08/1988
From: Chaney H, Murray B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20151N827 List:
References
50-313-88-02, 50-313-88-2, 50-368-88-02, 50-368-88-2, NUDOCS 8804260031
Download: ML20151N871 (8)


See also: IR 05000313/1988002

Text

. ,

,..-

,.

4

APPENDlX 8

.

,

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

I

-NRC Inspection Report:

50-313/88-02

Operating Licenses:

OPR-51

50-368/88-02

NPF-6

Dockets:

50-313

50-368

Licensee:

Arkansas Power & Light Company (AP&L)

P.O. Box 551

Little Rock, Arkansas 72203

Facility Name:

Arkansas Nuclear One (AN0)

Inspection At:

AND Site, Russellville, Pope County, Arkansas

Inspection Conducted:

February 21-26, 1988

Inspector:

4

9

H. D. Chdnby,'Radiatiori Specialist, facilities

.Date ~

Radiological Protect'on Section.

Approved:

Ok 0,

llAL.4/A

8

B. Murray, ClieT,~ Facipities Radiological

Oate/

Protection Section

Inspection Summary

Inspection Conducted February 21-26, 1988 (Report 50-3: l/88-02; 50-368/88-02)

l

Areas Inspected:

Routine, unannounced inspection of the licensee's radiation

j

protection activities during the Unit 2 refueling outage (2R6).

l

Results:

Within the areas inspected, one violation (failure to sur' rey and

post, paragraph 5.e) was identified.

No deviations were identified,

i

I

'

l

1

8804260031 8e]415

gDR

ADOCK 05000313

l'

DCD

- _ _ _

_ _ _ .

. _ _ _

_ _ _ _ _

_

._

. _ _ .

..

_

__ _

_

i

.

(

,

,

4

-2

DETAILS

- l' .

Persons Contacted

AP&L

  • D. Akins, Radioactive Waste (Radwaste) Supervisor
  • T. Baker, Technical Support Manager
  • E.' Bickel, Health Physics (HP) Superintendent
  • E. Ewing, Assistant Plant Manager
  • 0. Lomax, Plant Licensing Supervisor
  • P. Michalk, Plant. Licensing Engineer
  • S. Quennoz, Plant General Manager
  • R. Wewers, Work Control Center Supervisor

-Others

  • W. Johnson, Senior NRC Resident Inspector
  • Denotes those present at the exit interview on February 26, 1988.

2.

Inspector Observations

The following are observations the NRC inspector discussed with the

licensee during the exit interview on February.26, 1988.

These

. observations are not violations, deviations, unresolved items, or open

items. These observations were identified for licensee consideration for

program improvement, but the observations have no specific regulatory

requirement.

The licensee stated that the observations would be reviewed.

a.

HP Supervisor Job Oversight

The HP Supervisors (licensee and contractor) have not spent an

adequate amount of time inside containment and other radiological

work areas since the start of the Unit 2 outage,

b.

Personnel Contamination Control Work Practices

Many poor radiological work practices employt.1 by workers are not

being observed by the licensee, and when they are observed the

workers are not being critiqued on their poor contamination control

practices.

c,

Use of the-PCM-1 Monitors

Personnel were observed to be turning their face away from the

monitoring screen thus reducing the effectiveness of the monitor to

de c':ct radioactive contamination.

.

.

..

_

. _.

_

_

-

_ __

.

1

-l

-

.

i

.

'

.

3

3.

Open Items Identified During This Inspection

An open item is a matter that_ requires _further review and evaluation by

'

the NRC inspector.

Open items are used to document, track, and ensure

adequate followup on matters of concern to the NRC inspector.

The

following open items were identified:

Open' Item

Title

See Paragraph

313/8802-02 &

Control Room Habitability

6

368/8802-02

4.

Followup on Previous Inspection Findings (92701 and 92702)

(Closed) Open Item 313/8724-04; 368/8724-04:

Radioactivity in Sanitary

System Filter Beds - This item was identified in NRC Inspection

Report 50-313/87-24 and 50-368/87-24 and involved the detection of

radionuclides in the sanitary effluents.

The licensee had implemented

weekly sampling and analysis of sanitary effluent to and from the filter

beds.

Since Iodine-131 was not found in the sanitary filter beds following

the initial discovery, the licensee believes that the radioiodine in the

efficient was the result of a person using the sanitary facilities at AN0

following a medical administration of iodine for diagnostic purposes.

The

licensee has determined that the most likely source of the Cesium-137 in

the filter beds was due to effluents from the secondary side (steam) of

Unit 1 which still has residual fission products in the system from a

4

previous fuel and steam generator integrity problem.

The licensee has been

sampling and accounting for the additional cesium and other fission

products in the semiannual effluent reports.

The NRC inspector reviewed

the licensee's sampling protocols for the sanitary system (monthly

frequency) and documentation of their evaluation of the situation.

(Closed) Violation 313/8631-01; 368/8631-01:

Failure to Provide Timely

Update of Worker Internal Exposures - This violation was identified in NRC

Inspection Report 50-313/86-31 and 50-368/86-31 and involved the failure

to provide a timely update of a worker's exposure to airborne radioactive

materials.

The NRC inspector reviewed the licensee's corrective actions

and their written response to the violation and verified the adequacy of

the licensee's corrective actions.

5.

Outages (83729)

The NRC inspector reviewed the licensee's radiation protection program in

effect during the Unit 2 refueling outage (2R6).

The NRC inspector

reviewed planning and scheduling activities, worker briefings, HP staffing

and manning, control of radiological work activities, qualifications of

contract HP personnel, and compliance with Unic 2 Technical Specification 6.11 and radiological work and industrial safety

instructions.

The licensee's ALARA activities associated with conduct of

the 2R6 outage were also reviewed.

The following specific areas were

reviewed:

'

.+

.

.

4

.

a.

Planning and Preparation

The NRC inspector attended daily planning and scheduling meetings,

held discussions with senior plant managers concerning outage

preparations, and reviewed job preplanning for issuance of Radiation

Work Permits (RWP). The NRC inspector discussed with. licensee

representatives several industrial safety observations associated

with the head removal that should be evaluated.

These items of

concern were:

Lighting in the refueling canal during lifting of the head and

inspection for equipment hang-ups was marginal.' The workers

used hand-held 3-cell flashlights.

Use of the plant paging system was not co'ntrolled and coupled

with its excessive volume, it was very distracting during head

lifting when verbal communication between riggers and

maintenance personnel.was critical to safety.

A maintenance mechanic did not follow instructions to obtain and

wear a safety belt while working over the open refueling pit.

The licensee indicated that the above noted concerns would be

addressed.

The NRC' inspector noted that the licensee had installed a temporary

weather proof passageway and auxiliary offices for HP technicians,

dosimetry. issue and protective clothing issue at the Unit 2 equipment

hatch.

This facility (Alternate Controlled Access) greatly improves

accessibility to the reactor containment and provides greater HP

control over reactor access and work operations.

No violations or deviations were identified.

b.

Training and Qualification of Workers

The NRC inspector reviewed the licensee's program and its

implementation for evaluation and screening of contract HP workers.

The NRC previously reported in NRC Inspection Report 50-313/87-33;

50-368/87-33, an investigation into the circumstances surrounding the

failure of a contract HP technician to properly control a

radiological work operation.

The NRC inspector determined that the

licensee had screened, by testing, approximately 126 contract

technicians and 37 of these technicians (senior and junior

technicians) failed the screening test.

The licensee had a technical

review board evaluate each person that failed and determine if

retesting would be warranted.

Of the 37 that initially failed, 20

were hired after a review of their experience and weaknesses.

The

licensee had hired five contract HP supervisors to assist the

- ,

_ _

. _ .

_ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _

___

.. .

..

_

5

licensee's inheuse supervisors during the outage.

Each contract

technician completed on-the-job training and was evaluated by a

licensee senior technician prior to being assigned for independent

work responsibilities.

No violations or deviations were identified.

c.

External Exposure Control

The NRC inspector reviewed the licensee's control of radiation and

high radiation areas, hot spot posting,. dose rate evaluations for

steam generator entries, multiple whole body and extremity dosimetry

use, and the conduct of radiological surveys.

The NRC inspector reviewed the radiological controls associated with

~

,

the removal and replacement of the pressurizer spray line, inspection

and maintenance on the two U-tube steam generators, and the reactor

head removal.

The NRC inspector discussed with licensee representatives the

apparent need for HP technicians working as rovers within the reactor

containment to be more attentive in maintaining hotspot and high

radiation area postings.

Two high radiation area perimeter postings

in the lower level of the containment in equipment congested areas

werc noted to be marginal, but within the limitations of the TS.

The

NRC inspector identified to the licensee two hotspot warning labels-

that stated the contact dose rate was a factor of at least 3 times

lower than NRC and licensee radiation surveys indicated.

The licensee

immediately corrected the situations with shielding and updated the

hotspot warning signs.

No violations or deviations were identified,

d.

Internal Exposure Control

l

The NRC inspector reviewed the licensee's respirator issue program,

l

airborne radioactivity surveys, internal exposure trending and

tracking program, and on-the-job respirator use.

The NRC inspector noted that workers routinely inspected and properly

performed negative fit tests of their respirators prior to use.

The

licensee maintains positive control over issuance and return of

respirators.

The licensee's internal uptake tracking system was

reviewed and found to be well run and only 2 to 3 days lapse before

records are updated to reflect an individual's uptake.

This is a

major improvement over the situation found during the refueling

outage IR7 for Unit 1.

No violations or deviations were identified.

- - -

- ,

.

_ __

_ _.

- __--___. __

-_

_ _ _ .

.

.. -

.. .

.

_

..

.-

.

6

e.

Control of Radioactive Materials and Contamination, Surveys, and

Monitoring

The NRC inspector inspected the licensee's radioactive material

control program for release of materials from radiological work

areas, implementation of contamination control prcctices for major

jobs, cleaning of welds on the exterior of the steam generators, and

the removal of radioactive piping from the. pressurizer system.

The

licensee's use of contamination control containments and partial

enclosures has improved over past outages.

The NRC inspector noted

to the licensee that they were apparently allowing loose surface

contamination levels in work areas to increase to a high level

prior to having the areas decontaminated (100 millirad per hour

smearable).

The NRC inspector discussed with the licensee's

representative the need to improve preplanning and the use of layered

plastic film flooring to aid in the decontamination of areas and to

allow decreased use of respiratory protection equipment and

additional protective clothing.

The NRC inspector reviewed material

release logs at exits from contamination controlled areas.

10 CFR Part 20.201(b) requires that licensees shall make or cause to

be made such surveys as:

(1) may be necessary for the licensee to

comply with the regulations in this part, and (2) are reasonable

under the circumstances to evaluate the extent of radiation hazards

that may be present.

As defined in 10 CFR Part 20.201(a), "survey"

means an evaluation of the radiation hazards incident to the

production, use, release, disposal or presence of radioactive

materials, or other sources of radiation under a specific set of

conditions.

10 CFR Part 20.202 states, in part, that a "Radiation Area" means any

area, accessible to personnel, in which there exists radiation and a

major portion of the body could receive in any 5 consecutive days a

dose in excess of 100 millirems.

This limits equates to a dose rate

of approximately 0.8 mR/hr.

Furthermore, Part 20.203 states, in

part, that each radiation area shall be conspicuously posted with

signs identifying the radiation area.

In addition, TS 6.10 and 6.11 for ANO Units 1 and 2, respectively,

require that procedures for personnel radiation protection shall be

adhered to for all operations involving personnel radiation exposure.

Licensee Procedure 1622.003, "Radiological Posting and Entry

Requirements," requires that in plant radiation areas located outside

of Controlled Access be posted at 0.8 mR/hr.

During a review of facility surveys on February 24-26, 1988, it was

noted that three radiation area surveys conducted on February 14,

1988, and one on February 17, 1988, indicated that areas (Quadrex

decontamination trailer outside perimeter, offices adjacent to the

Unit 1 Controlled Access 386-foot level, and nonradiological

- -

, . w

..

'

.

e

7

-

Instrument and Controls Department work areas above the Maintenance

Shop) normally not classified or posted as radiation areas were

identified as having dose rates under 2.0 mR/hr which would indicate

that they may exceed the posting limit of 0.8 mR/hr.

Furthermore,

the surveys were accomplished with portable radiation survey

instruments that did not have the necessary sensitivity to accurately

measure 0.8 mR/hr of gamma radiation nor did the meter readout allow

for interpretation of values below 1 or 2 mR/hr.

The instruments

used were both high range beta gamma dose rate survey instruments.

These surveys were taken by contract HP technicians and were not

representative of the quality of the majority of the surveys taken at

the plant by both contract and licensee HP technicians.

The NRC

inspector noted also that the surveys in question had been reviewed

by a different licensee HP supervisor as a final stop in the

documentation process.

The NRC inspector noted that sufficient

surveys prior to and after the dates of the questionable surveys

substantiate the fact that the areas were and have been nonradiation

areas, and that the questionable survey results were not the result

of transient radioactive materials.

The failure to properly conduct radiation area surveys is considered

an apparent violation of 10 CFR Part 20.201 requirements.

The

failure to recognize and have posted identified radiation areas is

considered an apparent violation of 10 CFR Part 20.203(b).

These are

considered one violation due to their interrelationship.

(313/8802-01 and 368/8802-01)

No deviations were identified.

f.

Ind,ependent Surveys by the NRC Inspector

The NRC inspector conducted independent radiation surveys of high

,

radiation areas, radiation areas, office spaces, and waste

receptacles.

The NRC inspector also verified licensee controls and

periodic inspection records for very high radiation areas.

No violations or deviations were identified,

g.

ALARA Program

j

The NRC inspector reviewed the licensee's ALARA program.

The NRC

inspector noted that the licensee was providing 24-hour ALARA

l

technician support for resolution of problems concerning radiological

t

I

job requirements and temporary shielding installation.

The licensee

had provided an ALARA technician for interfacing with Work Control

Center Personnel for early review of maintenance work packages for

determining Radiation Work Permit requirements.

The NRC inspector

observed senior plant managernent interfacing with the ALARA

coordinator on resolving major radiological problems involving

L

i

t

- _ _ _ _ _ _ _ _ _ _ .

_ _

_

. _ _ _ .

. _ _ _

_ _ _ _ _

e

,

.#

.

'

8

removal of the reactor head.

The licensee was found to be closely

' tracking job performance based on person-rem exposure.

No violations or deviations were identified.

h.

Staffing

The NRC inspector reviewed the licensee's HP staffing for the outage

and determined that it~was adequate, but was stretched thinly'during

some instances when maintenance work scheduling exceeded the

available HP manpower.

No violations or deviations were identified.

6.

Control Roon, ilabitability

.

'

The NRC inspector reviewed the licensee's corrective actions taken in

response to NRC Memorandum, "Survey of ANO Units 1 and 2 Control Rooms,"

dated July 28, 1987 (J. Hayes, NRR to R. Lee, NRR).

The licensee had initiated a project to conduct a detailed review of

control room habitability systems.

The licensee had issued at least one

Licensee Event Report (LER 87-08, concerning air leakage into the control

rooms) due to this review project.

The licensee is drafting a response to

the NRC regarding their review of the NRC information concerning the ANO

control rooms which was transmitted to the licensee on or'about August 1,

1987.

The NRC inspector obtained procedures for testing and surveillance of the

control room ventilation and safety systems.

Due to the extensive amount

of material presented for review, this item will be considered an'open

item pending further NRC review for close out of the NRC's concerns in

this area.

(313/8802-02; 368/8802-02)

No violations or deviations were identified.

7.

Exit Interview

The NRC inspector met with the NRC resident inspector and licensee

representatives denoted in paragraph 1 on February 26, 1988, and

summarized the scope and inspection findings.