Monthly Operating Repts for Mar 1988
ML20151F981
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 03/31/1988
From: Peterson M, Querio R
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
BW-88-178, NUDOCS 8804190114
Download: ML20151F981 (14)


Text

.-__,,

4.*.>. .

BRAIDM000 NUCLEAR POWER STATION UNIT 1 AND UNIT 2 MONTHLY PERFORMANCE REPORT COMMONHEALTH EDISON COMPANY NRC DOCKET NO. 050-456, LICENSE NO. NPF-72 NRC DOCKET NO. 050-457, LICENSE NO. NPF-75 3

1 l

l 8804190114 880331 PDR ADOCK 05000456 R DCD (4957z/2) (

~

I. Monthly Report for Braidwood Unit 1 A. Summarv of Ooeratina Experience The unit entered the month of March in Mode 5. On March  ;

21, the unit was brought on line and taken up to 24% l reactor power. On March 23, the unit was shut down to replace Limitorque valve operator grease due to environmental qualification concerns. The unit remained in Mode 5 through the end of the month. L l

i t r l

l I

l l

l (4957z/3)

B. ' OPERATING DATA REPORT DOCKET NO.: 50-456 UNIT: Braidwood 1 DATE: 04/08/88 COMPILED BY: M. H. Peterson TELEPHONE: (815)458-2801 ext. 2480 OPERATING STATUS

1. Reporting Period: March, 1988 Gross Hours: 744.0
2. Currently Authorized Power Level (MHt): 3411 Design Electrical Rating (MHe-gross): 1175 Design Electrical Rating (MHe-net): 1120 Max Dependable Capacity (MHe-gross): 1175 Max Dependable Capacity (MHe-net): 1120
3. Power level to which restricted (If Any): None
4. Reasons for restriction (If Any): None THIS MONTH YR TO DATE CUMULATIVE
5. Report period Hours: 744.0 2184.0 6337.0
6. Hours Reactor Critical: 71.4 85.9 3145.6
7. RX Reserve Shutdown Hours: 0.0 0.0 0.0
8. Hours Generator on Line: 58.1 72.6 2683.3
9. Unit Reserve Shutdown Hours: 0.0 0.0 0.0
10. Gross Thermal Energy (MHH): 49033 96316 5111990
11. Gross Elec. Energy (MHH): 13498 30554 1635158
12. Net Elec. Energy (MHH): 0.0 16111 1472762
13. Reactor Service Factor: N/A N/A N/A
14. Reactor Availability Factor: N/A N/A N/A
15. Unit Service Factor: N/A N/A N/A
16. Unit Availability Factor: N/A N/A N/A
17. Unit Capacity Factor (MDC net): N/A N/A N/A
18. Unit Capacity Factor (DER net): N/A N/A _ N/A
19. Unit Forced Outage Rate: N/A N/A N/A
20. Unit Forced Outage Hours: 205.0 205.0 1527.3
21. Shutdowns Scheduled Over Next 6 Months:
22. If Shutdown at End of Report Period, Estimated Date of Startup: 04/15/88 l
23. Units in Test Status (Prior to Comercial Operation):

FORECAST ACHIEVED Initial Criticality 05/23/81 05/29/87 Initial Electricity 07/11/87 07/12/87 Comercial Operation 04/23/88 (49572/4)

C. AVERAGE DAILY UNIT NET POWER LEVEL LOG DOCKET N0.: 50-456 UNIT: Braidwood 1 DATE: 04/08/88 COMPILED BY: M. H. Peterson TELEPHONE: (815)458-2801 ext. 2480 HONTH: March, 1988

1. 0 17. 0
2. 0 18. 0
3. 0 19. 0
4. 0 20. 0
5. 0 21. 183
6. 0 22. 202
7. 0 23. 70
8. 0 24. 0
9. 0 25. 0
10. 0 26. 0
11. 0 27. 0
12. 0 28. 0
13. 0 29. O __
14. 0 30. O __
15. 0 31. 0
16. O INSTRUCTIONS On this form list the average daily unit power level in MHe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

These figures will be used to plot a grcph for each reporting month.

Note that when maximum dependable capacity is used for the net electrical rating of the unit there may be occasions when the daily average power

! level exceeds the 100% line (or the restricted power level line). In such cases the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

(49572/5)

I

D. UNIT SHUTDOWNS / REDUCTIONS DOCKET NO.: 50-456 UNIT: Braidwood 1 '

DATE: 04/08/88 .

COMPILED BY: M. H.-Peterson ,

TELEPHONE: (815)458-2801 ext. 2480 REPORT PERIOD: March, 1988 No - DAIE IY_PEPHOURS REASON METHOD LER NUMBEli SYSTEM COMPONENT CAUSE & CORRECTIVE ACTION TO PREVENT RECURRENCE 01 880101 S 480.9 H 4 N/A N/A N/A Continuance of 6 week surveillance outage.

02 880323 F 205.0 H 1 N/A N/A N/A Unit shut down due to environmental qualification concerns with Limitorque valve operator grease. Grease is being changed as required.

SUMMARY

TYPE REASON METHOD SYSTEM & COMPONENT F-Forced A-Equipment Failure 1 - Manual Exhibit F & H S-Scheduled B-Maint or Test 2 - Manual Scram Instructions for Preparation of C-Refueling 3 - Auto Scram Data Entry Sheet D-Regulatory Restriction 4 - Continued Licensee Event Report E-Operator Training & License Examination 5 - Reduced Load (LER) File (NUREG-1022)

F-Administration 9 - Other G-Oper Error H-Other (4957z/6)

. . i' l E. UNIOUE REPORTING REOUIREMENTS- UNIT I .,!

1. Safety / Relief valve operations.

VALVES NO & TYPE PLANT DESCRIPTION MIE ACTUATED ACTUATION CONDITION OF EVENT None

2. Licensee generated changes to 00CM.

None (4957z/7)

~-_ . . . - _ - . - - - - - - - . =_ -

F. LICENSEE EVENT REPORTS - UNIT I The following is a tabular summary of all Licensee Event Reports submitted during the reporting period, March 1 through March 31, 1988.

This information is provided pursuant to the reportable occurrence reporting requirements as set forth in 10 CFR 50.73.

Licensee Event Reoort Baparf Number Data Titie of Occurrence 88-002-00

  • 02/17/88 Reactor trip and safety injection due to cognitive personnel error.

88-003-00

  • 01/29/88 Loss of pulses to fuel handling incident monitor ORT-AR056 for unknown reasons.

88-005-00 02/23/88 1A Diesel Generator start on a safety injection signal instead of an undervoltage signal during testing due to operator miscommunication.

88-007-00 03/13/88 Residual Heat Removal Pumps declared inoperable due to improper surveillance execution.

Submitted during February, however, not included in February's report.

l l

l

( (4957z/8)

( .

II. Monthly Report for Braidwood Unit 2 A. Summarv of Operatino Exoerience The unit entered the month of March in Mode 3. On March 8 at 1150 the unit reached initial criticality and by March 14 the unit was at 3% reactor power. On March 16, the reactor was shut down due to main generator seal leakage and to replace Limitorque valve operator grease based on environmental qualification concerns. The unit remained in Mode 5 through the end of the month.

l (4957z/9) l

B. ' OPERATING DATA REPORT DOCKET NO.: 50-457 UNIT: Braidwood 2 DATE: 04/08/88 COMPILED FY: M. H. Peterson TELEPHONE: (815)458-?801 ext. 2480 OPERATING STATUS

1. Reporting Period: March, 1988 Gross Hours: N/A
2. Currently Authorized Power Level (MHt): 170 Design Electrical Rating (MWe-gross): 1175 Design Electrical Rating (MHe-net): 1120 Max Dependable Capacity (MWe-gross): 0 Max Dependable Capacity (MWe-net): 0
3. Power level to which restricted (If Any): 57.
4. Reasons for restriction (If Any): Terms of Braidwood Station's Factilty Operating License.

THIS MONTH YR TO DATE CUMULATIVE

5. Report period Hours: N/A -- --
6. Hours Reactor Critical: N/A -- --
7. RX Reserve Shutdown Hours: N/A -- --
8. Hours Generator on Line: _ N/A -- --
9. Unit Reserve Shutdown Hours: N/A -- --
10. Gross Thermal Energy (MHH): N/A -- --
11. Gross Elec. Energy (MHH): N/A - . _ _ --
12. Net Elec. Energy (MHH): N/A -- --
13. Reactor Servir.e Factor: .. N/A -- --
14. Reactoi Availability Factor: N/A --
15. Unit Service Factor: N/A -- --
16. Unit Availability Factor: N/A -- --
17. Unit Capacity Factor (MDC net): N/A . - - --
18. Unit Capacity Factor (DER net): N/A -- --
19. Unit Forced Outage Rate: N/A --
20. Unit Forced Outage Hours: N/A -- --

l . ,

21. Shutdowns Scheduled Over Next 6 Months:

l

22. If Shutdown at End of Report Period, Estimated Date of Startup:

1 23. Units in Test Stutus (Prior to Commercial Operation):

l FORECAST ACHIEVED l Initial Criticality 02/29/88 03/08/88 l Initial Electricity 03128/88 Commercial Operation 07/25/88 (4957z/10)

C. AVERAGE DAILY UNIT NET P0HER LEVEL LOG DOCKET NO.: 50-457

~

UNIT: Braidwood 2 DATE: 04/08/88 COMPILED BY: M. H. Peterson TELEPHONE: (815)458-2801 ext. 2480 MONTH: March, 1988

1. N/A 17. N/A
2. N/A 18. N/A
3. N/A 19. N/A
4. N/A 20. N/A
5. N/A 21. N/A
6. N/A __ 22. N/A
7. N/A 23. N/A
8. __

N/A 24. N/A

9. N/A 25. N/A
10. N/A 26. N/A
11. N/A 27. N/A
12. N/A 28. N/A
13. N/A 29. N/A
14. N/A 30. N/A i 15. N/A 31. N/A
16. N/A INSTRUCTIONS On this foem list the average daily unit power level in MMe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month.

Note that when maximum dependable capacity is used for the net electrical rating of the unit there may be occasions when the daily average power

- icvel exceeds the 100% line (c the restricted power level line). In j such cases the average daily z't power output sheet should be footnoted I to explain the apparent anor+1y.

(4957z/11)

D. U_ NIT SHUTDOWNS / REDUCTIONS DOCKET NO.: 50-457 '

UhlT: Braidwood 2

  • DATE: 04/08/88 COMPILED BY: M. W. Peterson' .

TELEPHONE: (815)458-2801 .

ext. 2480 REPORT PERIOD: March, 1988 No DATE IIPE HOURS REASON METHOD LER NUMBER SYSTEM COMPONENT CAUSE & CORRECTIVE ACTION TO PREVENT RECURRENCE N/A

SUMMARY

TYPE REASON METH00 SYSTEM & COMPONENT F-Forced A-Equipment Failure 1 - Manual Exhibit F & H S-Scheduled B-Maint or Test 2 - Manual Scram Instructions for Preparation of C-Refueling 3 - Auto Scram Data Entry Sheet D-Regulatory Restriction 4 - Continued Licensee Event Report E-Operator Training & License Examination 5 - Reduced Load (LER) File (NUREG-1022)

F-Administration 9 - Other G-Oper Error H-Other l

(4957z/12)

h E. UNIOUE REPORTING RE0VIREMENTS - tmIT 2 _.

. 1. Safety / Relief valve operations.

VALVES NO & TYPE PLANT DESCRIPTION D&IE ACTUATED ACTUATION CONDITION OF EVENT None

2. Licensce generated changes to 00CM.

None (4957z/13)

L

. 0, . -

4 J

F. LICENSEE EVENT REPORTS - UNIT 2 The following is a tabular summary of all Licensee Event Reports submitted during the reporting period, March 1 through March 31, 1988.

This information is provided pursuant to the reportable occurrence reporting requirements as set forth in 10 CFR 50.73.

Licensee Event Reoort Report Number QAlt Title of Occurrence 88-006-00 03/04/88 Inadvertent start of the Unit 2 auxiliary feedwater pump due to personnel error.

88-007-00 03/09/88 Reactor coolant valve found out of position.

I 88-008-00 03/17/88 Inadequate capacitor connection results in degraded instrument bus

4

)

i 1

(4957z/14)

, 7 3 _. .

. CN" Commonwealth Edison jE-, , ] O ) One FirstRipty Addrsss National to: Post Plata.

Othcs Box Chicago, 767 lihnois Y% Chicago, linnois 60690 BW/88-178 i

April 8, 1988 Director, Office of Resource Management United States Nuclear Regulatory Commission Hashington, D.C. 20555  ;

ATTN: Document Control Desk

Gentlemen

Enclosed for your inforniation is the Monthly Per'ormance Report covering Braidwood Nuclear Power Station for the period March 1 through March 31, 1988.

Very truly yours, R. E. Q io Station Manager Braidwood Nuclear Station REQ /RCB/ jab (4957z)

Attachments cc: A. B. Davis, NRC, Region III j NRC Resident Inspector Braidwood Gary Wright, Ill. Dept. of Nuclear Safety T. J. Maiman K. L. Graesser H. E. Bliss Nuclear fuel Services, PHR Plant Support i INP0 Records Center Performance Monitoring Group, Tech Staff Braidwood Station Nuclear Group, Tech Staff Braidwood Station S. Sands - USNRC l P. L. Barnes i