Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers to Confirm That short-term Insp Completed on 880309,per Request.Replacement Pole Shafts Ordered.Cost of Compliance W/Bulletin Stated
ML20151B820
Person / Time
Site: Summer 
Issue date: 03/30/1988
From: Nauman D
SOUTH CAROLINA ELECTRIC & GAS CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
IEB-88-001, IEB-88-1, NUDOCS 8804110292
Download: ML20151B820 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ -

^

gthggna Electric & Gas Company n

umn

,')i lumb 29218 Nuclear Operations SCE&G sma m o 9 *. U 6

g

,e 7,30-March 30, 1988 Dr. J. Nelson Grace Regional Administrator U. S. Nuclear Regulatory Commission Suite 2900 101 Marietta Street, NW Atlanta, Georgia 30323

SUBJECT:

Virgil C. Summer Nuclear Station Docket No. 50/395 Operating License No. NPF-12 NRC Bulletin No. 88-01

Dear Dr. Grace:

On February 9, 1988, South Carolina Electric & Gas Company (SCE&G) received NRC Bulletin No. 88-01, "Defects in Westinghouse Circuit Breakers." This response is a letter of confirmation that SCE&G comp'ated the requested short term inspection at its Virgil C. Summer Nuclear Station on March 9, 1988. The Westinghouse 0S-416 circuit breakers are the only circuit breaker types listed in NRC Bulletio 88-01 which are in use at the Virgil C. Summer Nuclear Station. We have five Westinghouse DS-416 circuit breakers that are rotated into four reactor trip main and bypass breaker positions. These breakers are id;ntified by equipment numbers XSW0001-RTl through XSW0001-RT5. All five redctor trip breakers did not meet the acceptance criteria of 6.1.1 in the bulletin.

Four breakers did meet the 6.1.2 acceptar.ce criteria. One breaker, 3

XSW0001-RT3, required corrective action due to the pole shaft welds not meeting the acceptance criteria of 6.1.2 in the bulletin. The pole shaft did not meet the criteria for weld size over a continuous length. An additional weld on the same cole shaft contained a crack of approximately 5/8".

This weld was locateo on the main drive link bushing where it joins the center pole lever, and it is not covered by the short term or long term inspection. A replacement pole shaft was ordered and received from Westinghouse.

The replacement pole shaft was inspected by SCE&G prior to installation, and it was discovered that the replacement pole shaft uld not meet the acceptance criteria of 6.1.1 in the bulletin but met the acceptance criteria of 6.1.2.

The weld for one of the three main pole shaft welds dropped slightly below the 3/16" acceptance criteria for a small section of the 180* continuous length of the weld. NRC Region !! was contacted along with the Resident Inspector to discuss whether the replacement pole shaft could be used under the time limits as stated in 6.2.2 of the bulletin. NRC Region II stated that the replacement pole shaft could be used under the time constraints in 6.2.2 of the bulletin until a pole shaft meeting the acceptance criteria of 6.1.1 could be procured. SCE&G has ordered five replacement pole shafts, which meet the 6.1.1 acceptance criteria, for the five reactor trip breakers at the Virgil C. Summer Nuclear Station.

8804110292 880330 PDR ADOCK 05000395 g 0, Q

DCD TEt t

~, -,

  • m.'

__s:

Dr. J. Nelson Grace NRC Bulletin No. 88-01 Page 2 March 30, 1988 The number of breakers recuiring corrective actions, if any, due to mechanism alignments has not been determined as this is an item to be addressed under the long term inspection program. The long term inspection is scheduled for the fall of 1988,'during the fourth refueling.

The following are items which were requested in the bulletin regarding cost of complying with this bulletin.

(1) The staff time to perform inspe';tions, corrective actions, and operability testing was 165 manhours.

(2) The staff time to review testing,nd prepare documentat'.' was 60 manhours.

(3) Additional cost incurred as a result of corrective actions was

$7500.00 for five pole shafts ar.d associated hardware.

The information contained in this letter is true and correct to the best of my knowledge, information and belief.

If you have any questions, please advise.

Very truly yours.

[

I Lfh D. A. Nauman JSB: DAN / led i

pc:

J. G. Connelly, Jr./0. W. Dixon, Jr./T. C. Nichols, Jr.

E. C. Roberts W. A. Williams, Jr.

J. C. Snelson General Managers G. O. Percival l.

L. A. Blue R. L. Prevatte C. A. Price J. B. Knotts, Jr.

R. B. Clary Document Control Oesk W. R. Higgins NSRC J. R. Proper RTS (IEB 880001)

L R. M. Campbell, Jr.

NPCF K. E. Nodland File (815.02) i l