ML20150E168

From kanterella
Jump to navigation Jump to search
Affidavit of Wp Murphy.* Discusses Installation of New Nes Racks Prior to Next Refueling Outage.W/Certificate of Svc
ML20150E168
Person / Time
Site: Vermont Yankee Entergy icon.png
Issue date: 07/07/1988
From: Murphy W
VERMONT YANKEE NUCLEAR POWER CORP.
To:
Shared Package
ML20150E156 List:
References
OLA, NUDOCS 8807150021
Download: ML20150E168 (10)


Text

.

i UNITED STATES OF AMERICA NUCLEAR REGULATORY-COMMISSION before the ATOMIC SAFETY AND LICENSING BOARD

)

In the Matter of ) -

~'

) Docket No. 50-271-OLA VERMONT YANKEE NUCLEAR ) (Spent Fuel Pool POWER CORPORATION ) Expansion)

)

(Vermont Yankee Nuclear )

Power Station) )

)

AFFIDAVIT OF WARREN P. MURPHY Warren P. Murphy, being first duly sworn, hereby deposes and says as follows:

1. My name is Warren P. Murphy. I am the Vice Presi-dent end Manager of Operations of Vermont Yankee Nuclear Power Cerporation ("Vermont Yankee"), the owner and operator of Vermont Yankee Nuclear Power Station ("VYNPS"). I make this affidavit in support of Vermont Yankee's "Licensee's l

l l

Response to ' Joint Motion of the Commonwealth of Massachu-setts and New England Coalition on Nuclear (Pollution) for Order Staying the Effectiveness of License Amendment No.

104 . . . .'"

l 2. The purpose of this affidavit is to explain the facts and circumstances leading Vermont Yankee to the conclusion that it was necessary to install the so-called "new" racks (NES racks) prior to the next refueling outage in 8807150021 880707 PDR ADOCK 05000271 0 PDR

. ~ -

order to avoid a number of economic and non-economic penal-ties to Vermont Yankee and the ratepayers whom VYNPS serves.

3. Vermont Yankee began considering its options for accommodating the next refueling early in 1988, concluding that it had to make'an election, by approximately June 1, 1988, either to perform the next refueling using "old" racks (PAR racks) or install the NES racks prior to refueling. Its

~

final decision was made a few days prior to June 1, 1938.

4. As of approximately June 1, 1988, the last of the PAR racks had not yet been installed in the VYNPS spent fuel pool, and at least one additional PAR rack would have to be purchased in order to have enough capacity in the PAR racks on-site to accommodate the one-third core refueling plus the possibility of a full core off load.

S. At the same time, sufficient NES racks to accom-modate the refueling and a possible full core off load had been ordered, were either already on-site or already scheduled for delivery in time to meet the refueling schedule, and had already been paid for or committed to be paid for.

6. As of approximately June 1, 1988 there were suffi-cient unused cavities in the PAR racks then in the pool to accommodate a one-third core reload. However, the an-ticipated re-racking, and the necessary movement of spent fuel assemblies to perform that re-racking, depended upon those empty spaces remaining empty. Were the existing PAR

-2 -

t

1 rt.cks used for the next refueling, then subsequent re-racking would not be possible without devising and employing some means of temporary storing spent fuel assemblies during the re-racking.

7. As of June 1, 1988 there were insufficient unused cavities in the PAR racks then in the pool to accommodate both the one-third core refueling and the possibility of a

~

full core off load thereafter. Were the next refueling to be ~-

done using the PAR racks, then, in order to accommodate a full core off lord, it would be necessary to insert addition-l al PAR racks into the pool, at which point those racks become for the first time low level radioactive waste.

8. If the re-racking and consequent removal of the PAR

~

racks were to be done prior to the next refueling, all or l substantially all of the PAR racks could be removed from the pool prior to December 31, 1988. As of June 1, 1988 Vermont Yanhee has contracts with persons to prepare the PAR racks 1

f removed from the pool for off-site shipment and ship them t'o l

! an off-site burial facility. As of June 1, 1988 Vermont

! Yankee had no place to ship low level radioactive waste after l

December 31, 1988, and there was substantial uncertainty as to whether or not such offsite shipments would be possible after that date.

9. The next VYNPS refueling is presently scheduled to commence February 4, 1989. This schedule is established to accommodate a number of factors, including the burnup of the

core presently in the VYNPS reactor, and in coordination with the needs of the New England Power Pool. For these reasons, changes in the refueling date can be difficult and expensive to effect, based upon a number of factors not urder Vermont Yankee's control.

10. In order to accommodate the refueling date, any re-racking activity must be completed by approximately November

~

15, 1988. A minimum of five NES racks must be installed in the pool to accommodate the refueling, and in order to install this number of racks by November 15, 1988, a decision to commence such installation was required by approximately June 1, 1988.

11. All of the foregoing facts are equally true as of the date of this affidavit with the following exception:

since June 1, 1988, Vermont Yankee has commenced the re-rack-ing and as of the date of this affidavit one NES rack has been installed in the pool.

12. Were the installation of the NES racks to be stopped, it will be necessary, in order to accommodate the next refueling, to reinstall any PAR racks that have been removed (and, depending on the point at which the decision were made, also to remove the NES racks already in the pool).

This will require additional movements of spent fuel as-semblies and additional movements of the contaminated PAR racks, with not insignificant attendant economic and environ-mental costs (primarily related to worker exposure).

. l

- j

, 13. Given the foregoing facts, Vermont Yankee was obliged to elect to perform the next refueling using either PAR racks or NES racks, and to make such election by on or before June 1, 1988. This decision was required to be made in the face f some uncertainty as to whether or not the pending i,-plication to increase the authorized maximum nunber of spent fuel assemblies from 2,000 to 2,870 would be approved, together with the certainty that that uncertainty would not be resolved prior to the date by which the decision had to be made.

14. As stated above, Vermont Yankee elected to perform the re-racking, that is to say, the subetitution of NES racks for PAR racks, prior to the next refueling, for the following reasons:
a. If the refueling was to be done using PAR racks, then Vermont Yankee would have to acquire one additional PAR rack, to be kept on-site in order to accommodate a possible full core off load, at a cost of between $150,000 and $200,000. Were this option to be taken and subsequently the spent fuel poo? expansion were approved and the re-racking performed, this

$150,000-$200,000 would have been a wasted expenditure.

On the other hand, the cost of the NES racks (excluding the cost of installation) had already been incurred (either paid or contractually committed), and those racks are equally functional for the storage of up to t -

- - - , --- - - - - + - - - - - - - -x -- - - - - - - . -+ - - - - -

. 2,000 spent fuel assemblies as they are for the storage of up to 2,870 spent fuel assemblies. Consequently, Vermont Yankee concluded that electing the path it chose imposed no economic penalty regardless of the outcome of the uncertain event, whereas electing the other path would have imposed a substantial economic penalty under one of the two possible resolutions-of the uncertain

~

event.

b. Were the refueling to be done prior to re-rack-ing, then each of the spent fuel assemblies making up the one-third core reload would have to be moved twice, first into the PAR racks and then into the NES racks.

There is a discrete environmental cost, primarily involving with worker exposure, associated with each move of a recently rejected spent fuel assembly. This is true even if one assumed (contrary to fact) that there would have been adequate room in the pool to make these movements without the necessity of finding some temporary storage capacity for spent fuel assemblies. ,

(See the next paragraph below.) Consequently, Vermont Yankee concluded that, regardless of the outcome of the uncertain event, the path it elected eliminated the certainty of an additional environmental cost under one of the two possible resolutions of the uncertain event.

c. Re-racking a spent fuel pool requires that fuel assemblies be moved from old racks to the new rack as

~ , -

- ,- -.---..-.g.. - , - . - . - . . --

l

. each new rack is put in the pool, in order that empty old racks may be removed sufficient to free up floor space in the pool for the new racks. Because of the l

configurations of the racks and the number of empty cavities now in the pool, performing the re-racking prior to the next VYNPS refueling would permit this operation to be done without the necessity of temporari-ly storing spent fuel assemblies. On the other hand, were approximately 136 additional spent fuel assemblies (1 2., 1/3 of the core) to be placed in the pool prior to re-racking, then it would not be possible to perform the re-racking without such temporary storage capabili-ty. Vermont Yankee was (and is) uncertain as to how it would achieve this temporary storage capability, but it was certain that any such temporary storage would have additional economic and environmental costs associated with it. Consequently, Vermont Yankee determined that performing the re-racking prior to refueling eliminated the possibility of incurring these additional economic and environmental costs,

d. On account of the present unavailability of a means of accomplishing the offsite shipment of low level radioactive waste after December 31, 1988, and uncer-tainty as to whether such offsite shipment after that date will be possible, Vermont Yankee concluded that performing the re-racking prior the next refueling

-7 -

4 would eliminate the possibility that the old racks would be required to be retained on the VYNPS site after their removal from the pool.

15. In summary, Vermont Yankee performed a traditional cost / benefit uncertainty analysis. On each point, it determined that re-racking before refueling would incur no incremental economic, environmental or operational costs. On

~

the other hand, postponing the re-racking until after the ref teling would incur additional economic, environmental and operational penalties if the spent fuel pool exchange authorization were ultimately approved.

16. Vermont Yankee would have made the same decision even had it regarded each of the two possible outcomes of the uncertain event (f.e., approval of spent fuel pool expansion and denial of spent fuel pool expansion) equally probable.

However, Vermont Yankee was aware of the fact that numerous prior spent fuel pool expansion applications have been made, that none of these re-racking applications have been denied, that none have been found to have any significant environmen-tal costs, and that there is nothing unique about Vermont Yankee or its application. Consequently, Vermont Yankee concluded that the probability that the above-described economic, environmental and operational penalties would ensue were re-racking to be deferred until after refueling was significantly greater than 0.5.

. 7-JDL 077 is:53gopgsdcpayevcRMONT 4ie YANMOD POWDR < w 4. 2 c7- 7. se c4

17. For the reasons set forth above, e stay of the effectiveness of License Amendment 104, were~it to require that the rearacking now in'progrees not be completed, would produos substantial injury to vermont Yahkee, its .

employees, the ratepayers whos VYNPS serves, and the general public, in-cluding

~

s. The expenditure of significant unnecessary sums of moneys b .- The exposure of Vermont Yankee and contractor personnel to unneccesary -

radiations

c. The potential unnecessary generation of low level radioactive westes
d. The loss of a presently available offeite disposal solution for the PAR racks.

f Warrey'P. -fftsAf Murph --

Vice 9 resident Manager of oper s

. STATE OF Vf,RMONT)

)es WINOHAM COUNTY )

Then personally appeared Warren P. Murphy, before and personally known to me, who, being first duly sworn, made oath that the foregoing statements are true, this 7th of July, 1988.

'd DTane M. McCue ,

Notary Public My Commission Expires February 0, 1991 Of

+

\J+ auw)

~ ->--,-,4m,ye-w- ,,,--w---~-e,mm,.,-e_,,we,m-.r--n, --,,__m_wnne,w-e ,,,e-+w--,,-,----,,,w-,.

.m.,--- ---w.

,n,,,una r m,a,--o-o,-- - , r---

e VYN-123 ASLB - Reg. Mail RKGCOSR3.VY CERTIFICATE OF SERVICE _

I, R. K. Gad III, hereby certify that on July.7, 1988, I made service of the within document in accordance with the rules of the Commission by mailing a copy thereof postage prepaid to the following:

Charles Bechhoefer, Esquire, David J. Mullet, Esquire Chairman Vermont Department of Administrative Judge Public Service _

Atomic Safety and Licensing 120 State Street -

Board Panel Montpelier, VT 05602 U.S. Nuclear Regulatory Commission Washington, DC 20555 Mr. Glenn O. Bright Ellyn R. Weiss, Esquire Administrative Judge Harmon & Weiss Atomic Safety and Licensing Suite 430 Board Panel 2001 S Street, N.W.

U.S. Nuclear Regulatory Washington, DC 20009 Commission Washington, DC 20555 Mr. James H. Carpenter George B. Dean, Esquire Administrative Judge Assistant Attorney General Atomic Safety and Licensing Department of the Attorney Board Panel General U.S. Nuclear Regulatory One Ashburton Place Commission Boston, MA 02108 Washington, DC 20555 Adjudicatory File Ann P. Hodgdon, Esquire Atomic Safety and Licensing - Office of the General Counsel Board Panel Docket (2 copies) U.S. Nuclear Regulatory U.S. Nuclear Regulatory Commission Commission Washington, DC 20555 Washington, DC 20555 Atomic Safety and Licensing Geoffrey M. Huntington, Esquire Appeal Board Panel Office of the Attorney General U.S. Nuclear Regulatory Environmental Protection Bureau Commission State House Annex Washington, DC 20555 25 Capitol Street-Concord, NH 03301-6397

\ ,T ,- _

\

i A l R. K. Gad III / l 1

l