Responds to IE Bulletin 80-13 Re Exam of Core Spray Sys Spargers.Visual Insp of Core Spray Spargers & in-vessel Core Spray Piping Completed on 880215.Insp Results Will Be Submited by 880330
ML20150D532
Person / Time
Site: Brunswick 
Issue date: 03/16/1988
From: Loflin L
CAROLINA POWER & LIGHT CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
IEB-80-13, NLS-88-071, NLS-88-71, NUDOCS 8803240321
Download: ML20150D532 (1)


Text

7 e

- 4 CML Carolina Power & Light Company 33 !"R le n 9: 0 NUR 16 H68 SERIAL: NLS 071 Dr. J. Nelson Grace, Regional Administrator United States Nuclear Regulatory Commission 101 Marietta Street, NW Atlanta, CA 30303 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-324/LICFNSE NO. DPR-62 l

L RESPONSE TO IE BULLETIN 80-13 I

EXAMINATION OF CORE SPRAY "YSTEM SPARGERS Gentlemen:

k IE Bulletin 80-13 requires that examinations of the core spray spargers and in-vessel core spray piping be made during each refueling outage.

The results of these inspections are to be submitted to the NRC within 30 days of completing the examinations.

In accordance with IE Bulletin 80-13, a visual inspection (Periodic Test 90.1) of the core spray spargers and in-vessel core spray piping of the s

Brunswick Steam Electric Plant Unit 2 was completed February 15, 1988.

Carolina Power & Light Company (CP&L) has not yet received a final copy of the contractor report evaluating the core spray piping inspections.

There fore, CP&L will submit the inspection results by March 30, 1988.

Please refer any questions regarding this submittal to Mr. Stephen D.

Floyd at (919) 836-6901.

Yours very trul,

\\

r l

J l

l L. I. Lof in Manager Nuclear Licensing Section i

i BAB/bab(doc \\cor) i cc:

NRC Document Control Desk Mr. W. H. Ruland i

Mr. E. D. Sylvester l

411 rayettev,He Street e P. O Box 1551

  • Roeigh. N C 27602 8803240321 880316 ID PDR ADOCK 05000324 O

DCD ten !

,