ML20150B588

From kanterella
Jump to navigation Jump to search
Insp Rept 50-425/88-28 on 880509-13 & 23-26.Violations Noted.Major Areas Inspected:Readiness Review Module,App F, Inspector Qualification
ML20150B588
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 06/16/1988
From: Belisle G, Matt Thomas, Wright R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20150B558 List:
References
50-425-88-28, NUDOCS 8807120081
Download: ML20150B588 (9)


See also: IR 05000425/1988028

Text

.

. .

_

_ _ _ _ _ _ _ _ .

..

.

p&Y

%

,

,

O

'd

UNITEC STATES

' j

}

NUCLEAR REGULATORY COMMISSION

' * -

REGION 11

'

o

[

101 MARIETTA ST N.W.

e,,,,

ATLANTA, GEORGIA 30323

Report No.:

50-425/88-28

Licensee: Georgia Power Company

P. O. Box 4545

Atlanta, GA 30302

Docket No.:

50-425

License No.:

CPPR-109

Facility Name: Vogtle 2

Inspection Conducted: May 9-13 and 23-26, 1988

M

/#

Inspectors:

m

,,

R. W. Wright

/

Date Signed

""

e

tv) c -

MYlM

$< $

M. Thomat

g

-

Date Signed

b<[J

t/rs///'

Approved By:

G. A.-Belisle, Chief

Date Signed

Quality Assurance Programs Section

Operations Branch

Division of Reactor Safety

SUMMARY

Scope:

This special, announced inspection was conducted in the area of

Readiness Review Module Appendix F, Inspector Qualification.

Results:

Appendix F presents an accurate description and evaluation of the

Unit 2 inspector qualification and certification program with the following

exception.

One violation was identified in this area (Failure to utilize certified Field

Level III inspectors as required by ANSI N45.2.6 - 1978, paragraph 5).

hbh

DO

O

G

-

_ _ _ _ _ - _ - _ _ _ _ _

. 3

o

.

.

.

.

.

REPORT DETAILS

- 1.

Licensee Dnployees Contacted

  • D. M. Fiquett, Assistant Project Construction Manager II
  • A. B. Gallant, Project Compliance Coordinator, and Technical Support

Group Supervisor

  • L. R. Glenn, Quality Control Manager

E. D. Groover, Quality Assurance Site Manager - Construction

  • S. D. Halton, Quality Assurance Support Supervisor

D. C. McAffee, Technical Support Group Engineer and Appendix F Readiness

Review Member

  • R. W. McManus, Assistant Project Construction Manager II, and Readiness

Review Manager

  • P. D. Rice, Vice President, and Vogtle Project Director

-0ther licensee employees contacted during this inspection included various

disciplined GPC/ contractor technical and NDE QC inspection personnel.

  • Attended exit interview

2.

Introduction

The scope of this Appendix F assessment plan (submitted to NRC on

March 30, 1988) is to evaluate the acceptability of programs for

qualifying and certifying all GPC and site contractor QC personnel

involved in constructing Unit 2 after June 1985.

Unit l's RR Appendix F (submitted to NRC on February 7,1986) evaluated

the acceptability of programs and inspector qualifications for both Unit 1

I

and Unit 2 prior to June 1985.

VEGP was designed and constructed as an

integrate facility and construction personnel involved in the inspecting

Unit 1 alsc performed Unit 2 inspections.

NRC Inspection Report

No. 50-424/86-24 dated October 1,

1986, concluded that the Unit 1

Appendix F assessment of VEGP IQC programs was satisfactory.

The RR assessment program for evaluating the qualifications and

certifications of post June 1985 Unit 2 QC inspectors consisted of three

major activities.

These activities evaluated the project IQC procedures,

evaluated project training programs, and evaluated project QC inspector

certification records.

The RRT review used a specific checklist for each

assessment activity.

The ccmmitments assassed for implementation are

current through November 1,1987, and Amendment 34 of the FSAR.

T

'

A

- -

n

-

'

.

._

_

.

_ . .

i

i

imm

mim

u

i

psand

- - .

-

_ _ _ - _ - - _ - _ - - .

e

.

.

'

-

.

..

2

.

3.

. Methodology-

The-NRC Unit 2 technical Appendix F review and evaluation was conducted in -

the Region II office during May 2 - 6 and May 16 - 19 and was supported by

onsite inspection activity during May 9 - 13, and May 23 - 26, 1988.

The Region II inspection review effnrt for Unit 2's Appendix F consisted

of the following:

Reviewing all VEGP IQC licensing commitments to insure completeness

Reviewing all GPC and site contractor IQC procedures revised since

June 1985 to insure proper commitment implementation therein

Reviewing GPC or contractor QC inspector certification records to '

-

ascertain agreement with current project procedures and RG 1.58

Reviewing VEGP IQC training programs for acceptebility

Reviewing the Unit 2 NRC inspection program at VEGP for its adequacy

Interviews with severa'l contractur and GPC inspection personnel

concerning the adequacy of their IQC programs

Summary of conclusions

4.

Licensee Commitments And NRC Requirements

RR maintained the Unit 1 connitment matrix current for design and

construction by reviewing FSAR Anendments, responses to Inspection and

-

Enforcement Bulletins, and correspondence to the NRC.

Additionally,

during the Unit 1 RR assessment, the task force identified project

controls (construction procedures, etc.) that implemented the commitment

requirements and listed them on a document called the implementation

matrix.

The Unit 1 implementation matrix was reexamined by appropriate

project organizations for updating the matrix data to reflect the latest

implementing documents for Unit 2.

The RR group verified the updated

implementing matrix accuracy.

The RR group examined all audits conducted

by GPC QA and Bechtel Western Power Company QA.

They also examined NRC

inspection results performed in the area of IQC that were conducted

subsequent to the Unit 1 Appendix F date.

These audits resulted in four

-

findings which identified discrepancies in documentation requirements or

use of a wrong code edition.

The findings did not identify deficiencies

in inspector qualifications.

NRC violations were not identified.

The

above resulting findings applicable to this apperJix were factored into

'

the licensee's review and assessment of the Unt' 2 IQC program.

Additionally, former Unit 1 Appendix F findings wre evaluated to

determine if they were still applicable to Unit 2 and, if s), were they

r

!

being properly addressed in Unit 2 programs.

!

!

.

- _ - .

_ _ _ _

- _ _ _ _

_ _ _ _ _ _ _ _ _ _ _

.

.

'

.

.

.

3

.

As described in Section 3, the project is committed to ensure that GPC's

and the contractor's IQC programs conform to RG 1.58, R1-1980.

In

accordance with RG 1.58-1980, technical inspectors were qualified and

certified according to requirements established by ANSI Standard

N45.2.6-1978. NDT examiners are qualified and certified according to ASNT

Recommended Practice'No. SNT-TC-1A-1975.

3

The only-substantial change to the above mentioned commitments since the

Unit 1 Appendix F review appeared in Amendment 16 discussed in

Section 1.9.58.2 of the FSAR.

In lieu of SNT-TC-1A-1975, the licensee

elected to endorse SNT-TC-1A-1980 for qualifying GPC construction and

nuclear operations personnel performing nondestructive examinations.

Additionally, most of the "shoulds" contained in the 1980 edition were

replaced with "shalls" except for two instances which are clearly denoted.

This change applied only to GPC NDT personnel and did not affect VEGP site

contractors comitted to SNT-TC-1A-1975.

The inspectors reviewed all the commitments identified in the Appendix F

Commitment Matrix and confirmed they were the same as those in Vogtle FSAR

Amendment 34. The inspector's review of Generic Letters and NRC Bulletins

written since 1985, and examination of the Vogtle SER did not identify any

questions pertinent to the licensee's IQC program commitments.

The

inspectors ascertained that the Unit 2 IQC commitments satisfied

NUREG-0800 Guideline Areas 20, Provisions To Assure Adequacy Of Personnel

Qualifications, and 108, Organizational Responsibilities And Qualification

Established For Individuals Or Groups Performing Inspections.

The

inspectors concluded that the Unit 2 Appendix F Comitment Matrix as

submitted is correct, complete, and adequate for VEGP IQC programs.

5.

GPC Implementation Programs And Precedures Review

The NRC inspectors reviewed the Unit 2 Implementation Matrix contained in

Section 3 to ascertain if it reflected the current implementing documents

and to verify that the program and procedures established to implemeat the

requirements of the Comitment Matrix were identified and appeared

reasonable.

Additionally, the inspectors extmined the GPC/ Contractor

programs and implementing procedures described in Sections 4 and 6.4.1 to

determine that they conformed to the requirements of the matrix.

The RRT developed three comprehensive inspection checklists which included

all the rcquirements of ANSI N 45.2.6 SNT-TC-1A-1975 and SNT-TC-1A-1980

3

respectively.

These checklists were used in assessing GPC/ Contractor IQC

programs and for verifying procedure conformance to licensing commitments.

The- assessment resulted in three RR findings (2RRF-21F-001, 002, 003) for

procedures that lacked details or contained errors.

GPC's corporate NDE

Procedure GEN-12750, R3 did not reouire NDE personnel to have a high

school diploma or GED diploma, nor was that requirement present in NISCO

Procedure ES-116-2, R1, for Levels II and III technical inspectors.

Subsequent examination of certification files for the GPC NDE, and NISCO

Levels II and III technical inspectors confirmed that all personnel had

either high schoci diplomas or a GED diploma.

gg ,

~

~

_

.

.~

,

..

,.

.

'

4

.

Procedure GEN-12750, R3, also specified on Exhibit 01, that the required

training for leak testing Level II was 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> whereas tne 1980 edition of

SNT-TC-1A recomend- 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> of training.

The Project was found to be

giving c 16 hour1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> leak' test training course making this deficiency an

administrative type error.

PPPLProcedure II-2,= revision dated August 15, 1986, did not address the

SNT-TC-1A-1975 requirement to find at least 90 percent of the known

indications. . Although this specific requirement' was not specified by

procedure it was being adhered to by NDE examiners.

The NRC .. inspectors reviewed the' above RR findings .and verified that

affected procedures were revised to incorporate the above mentioned

requirements.

The NRC inspectors reviewed the subject check lists

(iontained in Section 8) to assure they contained all the requirements of

th. above mentioned ANSI Standard and ANST Recommended Practices.

The

inspectors- cross . referenced all (100 Percent) of the RRT checklist item

k

'results to the applicable GPC/ Contractor implementing IQC procedures to

ensure their findings were correct and that no conflicting procedural

revisions had been incorporated since the Appendix F review.

-Based on this 100 Percent NRC inspector review of all GPC/ Contractor

implementing procedures (described in Tables 4-1 and 6-2) that had been

revised since June 1985, the inspectors concluded that all the VEGP IQC

commitments and regulatory requirements were conteined within these

procedures with the following exception.

FSAR, Section 1.9.58, specifies that VEGP commits to RG 1.58, R1, which

endorses ANSI N45.2.6-1978 with a few exceptions that are discussed in

detail.

Procedure QC-A-01, Qualification and Certification of Techrfcal

Inspectors, is GPC's construction proc '>re for implementing of ANSI

N45.2.6-1978Property "ANSI code" (as page type) with input value "ANSI</br></br>N45.2.6-1978" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. requirements.

Procedure Qo-A-01, RS, (Sections 4.5 ed

Exhibit 15) allows an Administrative Level III person to pe rforra the

functions specified in ANSI N45.2.6-1978 (Petion 4 and Table :) as Field

Level III responsibilities although the administrator's education anc

experience qualifications may or may not be equivalent.

Level III

Administrators are appcf.;ted by the Manager of Quality Control by

memorandum.

Review of the FSAR exceptions to ANSI 45.2.6-1978 revealed

that GPC did not mention the use of an Administrative Level III position

in lieu of a Field Level III inspector to perform these functions.

Since

i

no exception was taken, a commitment to comply with the ANSI Standard

means the specific education and experience recomendation of the standard

has to be followed.

This item was identified as violation 425/88-28-01,

Failcre to Utilize A Field Le'rel III Inspector As Committed Per ANSI

N45.2.6-1978Property "ANSI code" (as page type) with input value "ANSI</br></br>N45.2.6-1978" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process..

This violation cnly applies to GPC technical inspectors and

does not affect GPC NDE nor any contractcr inspection personnel.

l

-

_

h

-

.-

.

.

'

.

5-

.

During the procedural inspection review, one other isolated deficiency of

no safety significance was identified. While reviewing Procedure QC-A-01,

R5, the inspector found that FPCN No. 7 was not _ incorporated as indicated

by the procedure's cover page.

Discussions with' cognizant personnel and

subsequent documentation reviews revealed that before Revision 5 was

issued, FPCN No. 7 was reviewed and modi fied.

The' personnel on the

approval cycle for Revision 5 were all_ familiar with the above

modification and approved it for issue on April 6,1987, but failed to

notice that the description of the revision on the cover page.had not been

corrected.

Prior to leaving the site the licensee issued a new cover page

to QC-A-01, RS, which stated it incorporated FPCN No. 7 as Modified.

6.

Inspector Certification Records

.The RRT examined 37-GPC/ Contractor QC inspector certification files which

contained a total of 235 certifications using the inspector certification

checklists found in Section 8.

The RRT identified three deficient record

findings (2RRF-21F-004, 005, 006), two of which involved GPC and WPS' QC

inspector personnel receiving physical eye examinations by persons for

which had no documented evidence of their quf ' rications or training in

'

this area. The third finding involved some k

inspecter certification

forms that were not entirely completed.

The

inspector examined the

remedial actions and actions taken to prevent recurrence for these

findings and found. them satisfactory.

NRC site verificatica activities performed included reviewing a sampling

of both the GPC and site contractor inspection certification files that

were examined by the RRT and the expansion of that sample to others not

examined by the RRT.

This NRC inspection effort resulted in one finding.

Examination of five PPP QC inspector certification files not previously

,

reviewed by the RRT revealed one that was missing a letter of certifica-

tion for UT Thickness Measurement.

NRC examination of other supporting

documentation (training, attendance, and testing records) verified the

i -

subject inspector was certified in the area but for some reason the letter

of certification was inadvertently left out of his certification file.

The PPP Training Officer corrected this oversite prior to the NRC

inssactor leaving the site.

7.

Evaluation Project Training Programs

During the Unit 2 RR assessment, the inspector training programs were

reviewed using a training program checklist (see Section 8) that addressed

nine issues.

Attributes for the evaluation checklist were based on broad

industry issues that were extracted from the concerns expressed in NRC

L

Construction Assessment Team Inspection Reports from different facilit*es

under construction.

The NRC inspectors examined the above completed checklists and supporting

procedural evidence and ascertained that VEGP IQS program was not affected

by the above industry training issues.

u

--

___- ___-

.,

.

.-

.-

.

.

6

8.

NRC Inspection Prograin And Inspection Reports

The NRC inspectors examined the NRC's Construction Inspection Program

implemented for Unit 2 since June 1985, and concluded that the VEGP IQC

activities and programs have continued to be sat ';factorily covered and

generally in accordance with requirements.

This was accomplished by

examining a random sample of Hegion II Inspection Reports covering

procedures ending in xxx53 and xxx55 (work observatf or and records

review), procedure 35061 (QA inspection of work activities) and resident

inspection reports.

The inspector examined previous NRC inspection findings as of April 4,

1988; for Unit 2 in the area of IQC. This examination disclosed that one

Severi ty Level V violation was issued since June 1985.

Violation

425/86-45-02 was issued for failure to provide training for electrical

engineers and QC staff on the - use of Raychem Products.

However,

subsequent NRC followup of this violation (NRC Inspection Report No.

425/87-06) disclosed that the training deficiency only applied to Project

Field Engineers and not to QC personnel. Consequently, no IQC violations

have been identified since June 1985.

Review of the above mentioned

inspection reports and previous findings indicated that no adverse trends

existed in Unit 2 IQC program.

9.

Inspection Personnel Interviews

The NRC inspector conducted interviews with several Contractor (3-PPP,

2-WPS, 1-NISCO, 1-P/K-F) and GPC (5) inspection / testing oersonnel

concerning:

their training, education and qualifications

the capabilities and qualifications of their fellow inspector type

co-workers

their opinion of the adeqJacy of the inspection procedures in the

areas they are certified to inspect

how problems are identified and handled

their opinion of management's handling of problems identified

their opinion of management's attitude toward quality

The NRC inspector received generally positive and favorable responses to

all of the above questions asked.

There were no negative comments or

opi. dons expre; sed concerning their inspection programs, and no one was

aware of any existing plant hardware problems that had not been adequately

addre; sed.

All inspectors felt their co-workers (both present and past)

were teli qualified to handle their respective inspection responsibilities

and continue to do so. Several inspectors stated that some inspectors may

be more conscientious and do their job better than others, but all

_

___

. . ~ .

.

V-

- ..

-

7

.

J

inspection requirements are enforced and inspected prope'rly by everyone.

-The crafts go beyond minimum acceptable construction requirements to

ensure their work task receives QC acceptance.'

They stated that their

inspection programs (implementing procedures) have been continually-

revised, generally for the better as construction progressed to the point

that they- are now rather fine tuned.

They stated that the. training

inspectors.have received has been good, more than adequate to handle their

l Job and may be useful in securing another line of work when Unit 2 construc-

tion is completed.

They .also stated that management is understanding and

attentive to the problems they identify, takes time to explain differences

of opinion on issues, and appears to have

'avorable attitude toward

quality.

10. Conclusions

The Appendix F executive summary states, "RR concludes that adequate.

programs exist to ensure that the quality of inspector certifications and-

' the licensing cow 'tments within the scope of this appendix have been

implemented." Section 6.3 further states, "The review team found that

project programs as implemented meet licensing ccmmitments.

Inspector

certifications were acceptable and records were la good order with the

exception of a few record keeping, or administrative errors."

As'a result of the NRC verification activities conducted and discussed in

this report, the inspectors concluded that Appendix F (including-the above

summary statements) reflect an accurate description and evaluation of the

Vogtle Unit 2 IQC program with the one exception taken as noted in

paragraph 5.

Subsequent examination of the GPC QC Manager appointed

Level III Administretors disclosed that most met the education and

experience requirements of a Field Level III inspector or were college

,

engineering graduates with conalderable engineering experience.

GPC

currently has and has had a viable working IQC program.

The NRC also

concluded that Unit 2, Appendix F.is adequate.

11.

Exit Interview

The inspection scope and results were summarized on May 26, 1988, with

those persons indicated in paragraph 1.

The inspector described the areas

inspected and discussed in detail the inspection results . listed below.

Proprietary information is not contained in this report.

Dissenting

comments were act received from the licensee.

Violation 50-425/88-28-01, Failure to utilize certified Field Level III

inspectors as committed per ANSI N45.2.6-1978, paragraph 5.

.

.

.

.. .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _

__

_ _ _ _

_-

_

A

_

h [.

--

..

.

-

.

8

, , ,

~ 12'.- Acronyms And Initialisms -

ANSI

American National Standards Institute

-

American Society for Nondestructive Testing

t

ASNT

-

Field Procedure Change Notice

.FPCN

-

Final Safety. Analysis Report

FSAR

-

General Education Development -

GED

-

Georgia Power Company

GPC

-

Inspector _QualificeAion and Certification

L

IQC

-

Nondestructive Testing

L

NDT'

.-

Nuclear Installation Services Company-

NISCO

-

Nuclear Regulatory Commission

NRC

-

Pullman Construction Industries /Kenith-Fortson, Inc.

P/K-F

-

L

PPP

-

Pullman Power Products

Quality Assurance

QA

-

Quality Control

QC

--

Regulatory Guide

RG

-

Readiness Ret'ew

RR

-

l

RRT

Readiness Review Team

-

,

Safety Evaluation Report

i

SER_

-

Ultrasonic

'UT

-

Vegtle Electric Generatirg Plant

VEGP

-

Williams Power Services

WPS

-

.

.

. _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - _ - _ - - _ _ _ -

-