  • November 8, 1996 l

Mr. John F. Conant l Combustion Engineering, Inc. l 2000 Day Hill Road Windsor, Connecticut 06095-0500

SUBJECT:

AMENDMENT REQUEST TO D0WNGRADE SNM LICENSE (TAC N0. L30875) j

Dear Mr. Conant:

This refers to your application dated April 23, 1996, requesting an amendment 4 to Materials License SNM-1067 to delete the Windsor laboratory buildings and operations, to reduce the SNM possession limits and to delay the decommission-ing underway on Building 17.

4 Our review of your application has identified additional information that is

needed before final action can be taken on your request. The additional 4 information, specified in the enclosure, should be provided with 45 days of the date of this letter. Please reference the above TAC No. in future correspondence related to this request.

If you have any questions regarding this matter, please contact me at (301) 415-8155.

Sincerely, l

Original signed by.  ;

l Sean Soong Licensing Section 2 Licensing Branch ,

Division of Fuel Cycle Safety I and Safeguards, NMSS l Docket 70-1100 License SNM-1067

Enclosure:

As stated Distribution: w/encls. (Control No. 8COS)

Docket 70-Il00 PUBLIC-- < File Center NMSS R/F '

FCSS R/F FCLB R/F Region I -

JKottan, RI Madams r

G:\cewadd.ss] (4) l OFC FCLB 2[ FCLB Lf FCLB b FCLB C.

NAME SSoong ( 6 MAdamsNk/ PShea 76M MTokar N M )

DATE 11/ 4 /96 11///96 11/ b /96 11/$/96 C = COVER E = COVER & ENCLOSURE N = NO COPY OFFICIAL RECORD COPY 9611140309 961108 PDR MDOCK 07001100 C PDR ~

1301%3 NRC Fil.E CENTER COPY

l

  • p Ffog g-
  • Ig UNITED STATES NUCLEAR REGULATORY COMMISSION f WASHINGTON, D.C. 2055!MXc1 November 8, 1996

?g . . . . . j/

Mr. John F. Conant Combustion Engineering, Inc.

2000 Day Hill Road Windsor, Connecticut 06095-0500

SUBJECT:

l AMENDMENT REQUEST TO DOWNGRADE SNM LICENSE (TAC N0. L30875)

Dear Mr. Conant:

This refers to your application dated April 23, 1996, requesting an amendment to Materials License SNM-1067 to delete the Windsor laboratory buildings and operations, to reduce the SNM possession limits and to delay the decommission-ing underway on Building 17.

Our review of your application has identified additional information that is ,

needed before final action can be taken on your request. The additional l information, specified in the enclosure, should be provided with 45 days of  !

the date of this letter. Please reference the above TAC No. in future correspondence related to this request.

If you have any questions regarding this matter, please contact me at (301) 415-8155.

Sincerely,

^

Sean Soong esv['

Licensing Section 2 Licensing Branch Division of Fuel Cycle Safety and Safeguards, NMSS Docket 70-1100 License SNM-1067

Enclosure:

As stated

~

Request for Additional Information Application Dated April 23, 1996 Combustion Engineering, Inc.

Docket 70-1100

)

Please provide the.following information:

Pagg Comments 1-2 During a telephone conversation held on October 17, 1996, between Mr. John Conant of CE and NRC staff, Mr. Conant indicated that item (6) in Section 1.4 for 25 Kg U of natural and/or depleted uranium was mistakenly added. CE will delete the item 6 in the next revision.

In Section 1.5 delete Words "but are not limited to."

1-3 Definition of " Windsor Site" is inadequate and should be redefined to reflect its meaning.

Second sentence in the definition of " Windsor Site" should be removed and ,

incorporated into Section 1.6.1.

Section 1.6.1 should be revised to exclude all buildings.

2-1 Section 2.1 should indicate that CE management is responsible for safe operation under this license.

3-2 CE's annual report should include the review of radioactive effluents release and environmental monitoring data. l Current environmental monitoring program should be retained in the downgrade I 4-2 license. j 6-9 Figure 6-3 should be revised to indicate boundary of the Windsor Site.

ENCLOSURE

-