Application for Amend to License NPF-3,clarifying Boron Concentration Requirements for Refueling Conditions, Specifically Requirements Not Applicable When Reactor Vessel Completely DefueledML20149E038 |
Person / Time |
---|
Site: |
Davis Besse ![Cleveland Electric icon.png](/w/images/7/78/Cleveland_Electric_icon.png) |
---|
Issue date: |
01/04/1988 |
---|
From: |
Shelton D TOLEDO EDISON CO. |
---|
To: |
|
---|
Shared Package |
---|
ML20149E031 |
List: |
---|
References |
---|
1459, NUDOCS 8801130205 |
Download: ML20149E038 (9) |
|
|
---|
Category:OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING
MONTHYEARML20216E6051999-09-0707 September 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20210H0631999-07-28028 July 1999 Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, by Allowing Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G4131999-07-27027 July 1999 Application for Amend to License NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G8831999-07-26026 July 1999 Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrumentation - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5251999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G4631999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumention & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20195F9121999-06-10010 June 1999 Application for Amend to License NPF-3,changing TS 3/4.6.4.4 Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20207E7861999-05-21021 May 1999 Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capability ML20205E4961999-03-19019 March 1999 Application for Amend to License NPF-3,requesting Withdrawal of Proposed New Action B to TS 3.6.5.2,previously Submitted in 981027 Application ML20204F1691999-03-0909 March 1999 Application for Amend to License NPF-3,adopting Changes in Frequency & Scope of Volumetric Exams Justified by W TR WCAP-14535A ML20196F3791998-11-30030 November 1998 Supplemental Application for Amend to License NPF-3, Proposing Changes to License Conditions 2.C(6) & 2.E by Transferring Operating Authority for DBNPS from Toed & Centerior Svc Co to Firstenergy Nuclear Operating Co ML20155E3181998-10-28028 October 1998 Application for Amend to License NPF-3,revising Various Sections of TS 6.0, Administrative Controls, Including Relocation of Contents of 6.11 to Plant Ufsar,Per NUREG-1430,Rev 1 ML20155E0701998-10-27027 October 1998 Application for Amend to License NPF-3,revising TSs 3/4.3.1.1 Re RPS Instrumentation & 3/4.3.2.3 Re ARTS Instrumentation by Providing Potential Reduction in Spurious Trip Rate to Provide Cost Savings in Excess of $50,000 ML20155D7731998-10-27027 October 1998 Application for Amend to License NPF-3,relocating Existing TS SR 4.6.5.1.d.4 Re Evs Negative Pressure Testing to TS 3/4.6.5.2,deleting TS Definition 1.24 & Making Related Changes Associated with Deletion of Subject Definition ML20155D8481998-10-27027 October 1998 Application for Amend to License NPF-3,revising Existing TS SRs 4.8.2.3.2.d,4.8.2.3.2.e,4.8.2.3.2.f & Table 4.8-1 Re Testing of 125 Volt DC Station Batteries & Applicable TS Bases ML20151W2811998-09-0808 September 1998 Application for Amend to License NPF-3,permitting Use of Framatome Cogema Fuels M5 Advanced Alloy Fuel Rod Cladding & Fuel Assembly Spacer Grids ML20151W2851998-09-0808 September 1998 Application for Amend to License NPF-3,revising TS Section 3/4.7.6, Plant Systems - CREVS & Associated Bases ML20236G6461998-06-29029 June 1998 Application for Amend to License NPF-3,transferring Operating Authority for DBNPS from TE & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Marked Up License,Safety & Environ Assessments Included ML20236R2301998-06-29029 June 1998 Resubmitted Application for Amend to License NPF-3, Transferring Operating Authority for DBNPS from Teco & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Safety Assessment & EA Included ML20217P8671998-04-24024 April 1998 Application for Amend to License NPF-3,modifying Existing TS 3/4.3.1.1,3/4.3.2.1,3/4.3.2.2 & Associated Bases by Relocating Tables of Response Time Limits from TS to Plant USAR Technical Requirements Manual ML20217P8251998-04-24024 April 1998 Application for Amend to License NPF-3,clarifying Discussion of Margin Between RPS High Pressure Trip Setpoint & Lift Setting for Pressurizer Code Safety Valves ML20203L0861998-02-26026 February 1998 Application for Amend to License NPF-3 to Revise TS 3/4.4.5 & TS 3/4.4.6.2,incorporating New Repair Roll Process for SG Tubes W/Defects in Upper Tube Sheet ML20197J2511997-12-23023 December 1997 Application for Amend to License NPF-3.Amend Changes TS Definitions 1.12,TS 3/4.9.5 & New TS 3.0.6 ML20197J5861997-12-23023 December 1997 Application for Amend to License NPF-3,revising TS Surveillance Requirements for ISI Requirements of Internal Auxiliary Feedwater Header,Header to Shroud Attachment Welds & External Header Thermal Sleeves ML20217R2801997-08-26026 August 1997 Application for Amend to License NPF-3,clarifying LCO 3.6.1.3.a & Revising Surveillance Requirement 4.6.1.3.c ML20217R2831997-08-26026 August 1997 Application for Amend to License NPF-3,modifying TS 3.2.5 Action Statement to Require Power Reduction to Less than 5% of Rated Thermal Power within Four Hrs If RCS Flow Rate Is Less than Specified Limit for Greater than Two Hrs ML20217G5931997-07-29029 July 1997 Suppl 950929 to Application for Amend to License NPF-3, Change TS 3/4.4.3 Re Safety Valves & Pilot Operated Relief valve-operating & Associated Bases 3/4.4.2 & 3/4.4.3 ML20141F1051997-06-24024 June 1997 Application for Amend to License NPF-3,deleting Requirements for Safety Features Actuation Sys Containment High Radiation Monitors ML20138A3201997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Conversion to 24-month Fuel Cycle ML20138C3131997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Rev to TS 3/4.7.6 to Include New Required Actions in Event That One or Both Channels of Radiation Monitoring Instrumentation Becomes Inoperable ML20137M1061997-03-31031 March 1997 Application for Amend to License NPF-57,revising TS to Improve Consistency Between TS & Plant Configuration, Operation & Testing & Complete Required CA to Resolve TS Discrepancies Identified in CA Program ML20138M1251997-02-14014 February 1997 Application for Amend to License NPF-3,requesting Delay of Heat Removal Sys Valve Pit Surveillance Requirements ML20134D7461997-01-30030 January 1997 Application for Amend to License NPF-3,revising SR Intervals from 18 to 24 Months Based on Results of DBNPS Instrument Drift Study & TS 2.2, Limiting Safety Sys Settings, Based on Results of Revised Framatome RPS Instrument String Error ML20134B0561997-01-20020 January 1997 Application for Amend to License NPF-3,involving TS 3/4.5.3 Re ECCS Subsystems ML20132C7771996-12-13013 December 1996 Application for Amend to License NPF-3,authorizing Transfers of Control ML20132B6871996-12-11011 December 1996 Application for Amend to License NPF-3,revising TS Definitions,Instrumentation TS & ECCS TS for Conversion to 24 Month Fuel Cycle ML20134F1851996-10-28028 October 1996 Application for Amend to License NPF-3,requesting Revisions to 3/4.8.1.1,3/4.8.1.2,3/4.8.2.3,3/4.8.2.4 & 3/4.8 Re Electrical Power Systems ML20117P5301996-09-17017 September 1996 Application for Amend to License NPF-3,supporting Conversion of DBNPS from 18 Month to 24 Month Fuel Cycle ML20117N8441996-09-12012 September 1996 Application for Amend to License NPF-3,revising Reactivity Control Systems & Emergency Core Cooling Systems ML20117M1971996-09-0404 September 1996 Application for Amend to License NPF-3,App A,Modifying TS 6.2.3 by Removing Specific Overtime Limits & Working H from TS Consistent W/Nrc Recent Determination,On Generic Basis, That Limits Need Not Be Specified ML20116K2601996-08-0707 August 1996 Application for Amend to License NPF-3,changing Tech Specs 1.0, Definitions, Bases 3/4.0, Applicability & 3/4.6.2.1, Containment Sys - Depressurization & Cooling Sys - Containment Spray Sys ML20117K1871996-05-28028 May 1996 Application for Amend to License NPF-3,revising TS 3/4.3.1.1 RPS Instrumentation & TS 3/4.3.2.2 - Anticipatory RTS Instrumentation to Increase Trip Device Test Interval ML20107L3541996-04-18018 April 1996 Application for Amend to License NPF-3,requesting NRC Review & Approval to Use Alternate Electrical Lineup.Station Blackout DG as Standby Emergency Power Source to Supply Loads Normally Supplied by EDG 1,while Being Reworked ML20101M1601996-03-29029 March 1996 Application for Amend to License NPF-3,App A,Re Surveillance Requirements for Charcoal Filter Lab Testing to Revise Testing Methodology Used to Determine Operability of Charcoal Filters in ESF Air Handling Units ML20101C6911996-03-0606 March 1996 Application for Amend to License NPF-3,revising TS 3/4.5.2 to Allow Deferment of SR 4.5.2.b for ECCS Flowpath Containing HPI 1-2 Pump Until 10th Refueling Outage, Scheduled to Begin 960408 ML20100E0051996-02-0505 February 1996 LAR 93-0003 to License NPF-3,revising Table 3.3-3 of TS 3/4.3.2.1 Re Safety Features Actuation Sys Instrumentation to More Accurately Reflect Design & Actuation Logic of Plant Sequencers & Undervoltage Relays ML20095F5861995-12-12012 December 1995 Application for Amend to License NPF-3,revising TSs Re Containment Sys ML20098C5131995-10-0202 October 1995 Application for Amend to License NPF-3,revising TS Section 5.0,design Features & Adopting Improved STS for B&W Plants Format & Content ML20098C1071995-09-29029 September 1995 Application for Amend to License NPF-3,modifying TS 3.4.3 & Associated Bases for Pressurizer Code Safety Valve Lift Setpoint Tolerances ML20098C3931995-09-29029 September 1995 Application for Amend to License NPF-3,revising Tech Spec 3/4.1.2.8, Reactivity Control Sys - Borated Water Sources - Shutdown, Tech Spec 3/4.1.2.9, Reactivity Control Sys - Operating & TS 3/4.5.1, ECCS - Core Flooding Tanks 1999-09-07
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML20216E6051999-09-0707 September 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20210H0631999-07-28028 July 1999 Application for Amend to License NPF-3,revising TS 3/4.7.5.1, Ultimate Heat Sink, by Allowing Plant Operation in Modes 1-4 with Water Temp Less than or Equal to 90 F ML20210G4131999-07-27027 July 1999 Application for Amend to License NPF-3,changing TSs 6.4, Training, 6.5.2.8, Audits, 6.10, Record Retention, 6.14, Process Control Program & 6.15, Odcm ML20210G8831999-07-26026 July 1999 Application for Amend to License NPF-3,revising TSs 3/4.3.3.1, Radiation Monitoring Instrumentation, 3/4.3.3.2, Instrumentation - Incore Detectors & 3/4.3.3.9, Instrumentation - Waste Gas Sys Oxygen Monitor ML20210G5251999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs for Implementation of 10CFR50,App J,Option B for Type B & C Containment Leakage Rate Testing ML20210G4631999-07-26026 July 1999 Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1, Safety Features Actuation Sys Instrumention & Associated Bases 3/4.3.1 & 3/4.3.2, Reactor Protection Sys & Safety Sys Instrumentation ML20195F9121999-06-10010 June 1999 Application for Amend to License NPF-3,changing TS 3/4.6.4.4 Hydrogen Purge Sys, TS 3/4.6.5.1, Shield Bldg Emergency Ventilation Sys & TS 3/4.7.6.1, Crevs ML20207E7861999-05-21021 May 1999 Application for Amend to License NPF-3,allowing Use of Expanded Spent Fuel Storage Capability ML20205E4961999-03-19019 March 1999 Application for Amend to License NPF-3,requesting Withdrawal of Proposed New Action B to TS 3.6.5.2,previously Submitted in 981027 Application ML20204F1691999-03-0909 March 1999 Application for Amend to License NPF-3,adopting Changes in Frequency & Scope of Volumetric Exams Justified by W TR WCAP-14535A ML20196F3791998-11-30030 November 1998 Supplemental Application for Amend to License NPF-3, Proposing Changes to License Conditions 2.C(6) & 2.E by Transferring Operating Authority for DBNPS from Toed & Centerior Svc Co to Firstenergy Nuclear Operating Co ML20155E3181998-10-28028 October 1998 Application for Amend to License NPF-3,revising Various Sections of TS 6.0, Administrative Controls, Including Relocation of Contents of 6.11 to Plant Ufsar,Per NUREG-1430,Rev 1 ML20155E0701998-10-27027 October 1998 Application for Amend to License NPF-3,revising TSs 3/4.3.1.1 Re RPS Instrumentation & 3/4.3.2.3 Re ARTS Instrumentation by Providing Potential Reduction in Spurious Trip Rate to Provide Cost Savings in Excess of $50,000 ML20155D7731998-10-27027 October 1998 Application for Amend to License NPF-3,relocating Existing TS SR 4.6.5.1.d.4 Re Evs Negative Pressure Testing to TS 3/4.6.5.2,deleting TS Definition 1.24 & Making Related Changes Associated with Deletion of Subject Definition ML20155D8481998-10-27027 October 1998 Application for Amend to License NPF-3,revising Existing TS SRs 4.8.2.3.2.d,4.8.2.3.2.e,4.8.2.3.2.f & Table 4.8-1 Re Testing of 125 Volt DC Station Batteries & Applicable TS Bases ML20151W2811998-09-0808 September 1998 Application for Amend to License NPF-3,permitting Use of Framatome Cogema Fuels M5 Advanced Alloy Fuel Rod Cladding & Fuel Assembly Spacer Grids ML20151W2851998-09-0808 September 1998 Application for Amend to License NPF-3,revising TS Section 3/4.7.6, Plant Systems - CREVS & Associated Bases ML20236G6461998-06-29029 June 1998 Application for Amend to License NPF-3,transferring Operating Authority for DBNPS from TE & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Marked Up License,Safety & Environ Assessments Included ML20236R2301998-06-29029 June 1998 Resubmitted Application for Amend to License NPF-3, Transferring Operating Authority for DBNPS from Teco & Centerior Svc Co to New Operating Company Called Firstenergy Nuclear Operating Co.Safety Assessment & EA Included ML20217P8671998-04-24024 April 1998 Application for Amend to License NPF-3,modifying Existing TS 3/4.3.1.1,3/4.3.2.1,3/4.3.2.2 & Associated Bases by Relocating Tables of Response Time Limits from TS to Plant USAR Technical Requirements Manual ML20217P8251998-04-24024 April 1998 Application for Amend to License NPF-3,clarifying Discussion of Margin Between RPS High Pressure Trip Setpoint & Lift Setting for Pressurizer Code Safety Valves ML20203L0861998-02-26026 February 1998 Application for Amend to License NPF-3 to Revise TS 3/4.4.5 & TS 3/4.4.6.2,incorporating New Repair Roll Process for SG Tubes W/Defects in Upper Tube Sheet ML20197J2511997-12-23023 December 1997 Application for Amend to License NPF-3.Amend Changes TS Definitions 1.12,TS 3/4.9.5 & New TS 3.0.6 ML20197J5861997-12-23023 December 1997 Application for Amend to License NPF-3,revising TS Surveillance Requirements for ISI Requirements of Internal Auxiliary Feedwater Header,Header to Shroud Attachment Welds & External Header Thermal Sleeves ML20217R2801997-08-26026 August 1997 Application for Amend to License NPF-3,clarifying LCO 3.6.1.3.a & Revising Surveillance Requirement 4.6.1.3.c ML20217R2831997-08-26026 August 1997 Application for Amend to License NPF-3,modifying TS 3.2.5 Action Statement to Require Power Reduction to Less than 5% of Rated Thermal Power within Four Hrs If RCS Flow Rate Is Less than Specified Limit for Greater than Two Hrs ML20217G5931997-07-29029 July 1997 Suppl 950929 to Application for Amend to License NPF-3, Change TS 3/4.4.3 Re Safety Valves & Pilot Operated Relief valve-operating & Associated Bases 3/4.4.2 & 3/4.4.3 ML20141F1051997-06-24024 June 1997 Application for Amend to License NPF-3,deleting Requirements for Safety Features Actuation Sys Containment High Radiation Monitors ML20138A3201997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Conversion to 24-month Fuel Cycle ML20138C3131997-04-18018 April 1997 Application for Amend to License NPF-3,requesting Rev to TS 3/4.7.6 to Include New Required Actions in Event That One or Both Channels of Radiation Monitoring Instrumentation Becomes Inoperable ML20137M1061997-03-31031 March 1997 Application for Amend to License NPF-57,revising TS to Improve Consistency Between TS & Plant Configuration, Operation & Testing & Complete Required CA to Resolve TS Discrepancies Identified in CA Program ML20138M1251997-02-14014 February 1997 Application for Amend to License NPF-3,requesting Delay of Heat Removal Sys Valve Pit Surveillance Requirements ML20134D7461997-01-30030 January 1997 Application for Amend to License NPF-3,revising SR Intervals from 18 to 24 Months Based on Results of DBNPS Instrument Drift Study & TS 2.2, Limiting Safety Sys Settings, Based on Results of Revised Framatome RPS Instrument String Error ML20134B0561997-01-20020 January 1997 Application for Amend to License NPF-3,involving TS 3/4.5.3 Re ECCS Subsystems ML20132C7771996-12-13013 December 1996 Application for Amend to License NPF-3,authorizing Transfers of Control ML20132B6871996-12-11011 December 1996 Application for Amend to License NPF-3,revising TS Definitions,Instrumentation TS & ECCS TS for Conversion to 24 Month Fuel Cycle ML20134F1851996-10-28028 October 1996 Application for Amend to License NPF-3,requesting Revisions to 3/4.8.1.1,3/4.8.1.2,3/4.8.2.3,3/4.8.2.4 & 3/4.8 Re Electrical Power Systems ML20117P5301996-09-17017 September 1996 Application for Amend to License NPF-3,supporting Conversion of DBNPS from 18 Month to 24 Month Fuel Cycle ML20117N8441996-09-12012 September 1996 Application for Amend to License NPF-3,revising Reactivity Control Systems & Emergency Core Cooling Systems ML20117M1971996-09-0404 September 1996 Application for Amend to License NPF-3,App A,Modifying TS 6.2.3 by Removing Specific Overtime Limits & Working H from TS Consistent W/Nrc Recent Determination,On Generic Basis, That Limits Need Not Be Specified ML20116K2601996-08-0707 August 1996 Application for Amend to License NPF-3,changing Tech Specs 1.0, Definitions, Bases 3/4.0, Applicability & 3/4.6.2.1, Containment Sys - Depressurization & Cooling Sys - Containment Spray Sys ML20117K1871996-05-28028 May 1996 Application for Amend to License NPF-3,revising TS 3/4.3.1.1 RPS Instrumentation & TS 3/4.3.2.2 - Anticipatory RTS Instrumentation to Increase Trip Device Test Interval ML20107L3541996-04-18018 April 1996 Application for Amend to License NPF-3,requesting NRC Review & Approval to Use Alternate Electrical Lineup.Station Blackout DG as Standby Emergency Power Source to Supply Loads Normally Supplied by EDG 1,while Being Reworked ML20101M1601996-03-29029 March 1996 Application for Amend to License NPF-3,App A,Re Surveillance Requirements for Charcoal Filter Lab Testing to Revise Testing Methodology Used to Determine Operability of Charcoal Filters in ESF Air Handling Units ML20101C6911996-03-0606 March 1996 Application for Amend to License NPF-3,revising TS 3/4.5.2 to Allow Deferment of SR 4.5.2.b for ECCS Flowpath Containing HPI 1-2 Pump Until 10th Refueling Outage, Scheduled to Begin 960408 ML20100E0051996-02-0505 February 1996 LAR 93-0003 to License NPF-3,revising Table 3.3-3 of TS 3/4.3.2.1 Re Safety Features Actuation Sys Instrumentation to More Accurately Reflect Design & Actuation Logic of Plant Sequencers & Undervoltage Relays ML20095F5861995-12-12012 December 1995 Application for Amend to License NPF-3,revising TSs Re Containment Sys ML20098C5131995-10-0202 October 1995 Application for Amend to License NPF-3,revising TS Section 5.0,design Features & Adopting Improved STS for B&W Plants Format & Content ML20098C1071995-09-29029 September 1995 Application for Amend to License NPF-3,modifying TS 3.4.3 & Associated Bases for Pressurizer Code Safety Valve Lift Setpoint Tolerances ML20098C3931995-09-29029 September 1995 Application for Amend to License NPF-3,revising Tech Spec 3/4.1.2.8, Reactivity Control Sys - Borated Water Sources - Shutdown, Tech Spec 3/4.1.2.9, Reactivity Control Sys - Operating & TS 3/4.5.1, ECCS - Core Flooding Tanks 1999-09-07
[Table view] |
Text
.
Docket No. 50-346 !
License No. NPF-3 Serial No. 1459 Enclosure APPLICATION FOR AMENDMENT TO FACILITY OPERATING LICENSE NO. NPF-3 FOR DAVIS-BESSE NUCLEAR POWER STATION UNIT NO. 1 Attached are requested changes to the Davis-Besse Nuclear Power Station, Unit No. 1 Facility Operating License No. NPF-3. Also included are the Safety Evaluation and Significant Hazards Consideration.
The proposed changes (submitted under cover letter Serial No. 1459) concern:
Technical Specification 3.9.1.
\
By: bl f \\
D. C. Shelton, Vice Presiderit'Ntidlear Sworn and subscribed before me this 4th day of January, 1968.
uA / 4A I Notar Public, State of Ohio My commission expires Ifi T I SM"iBBR BSE@#
P t
Docket No. 50-346 License No. NPF-3 Serial No. 1459 Enclosure The following information is provided to support issuance of the requested changes to the Davis-Besse Nuclear Power Station, Unit No. 1 Operating License No. NPF-3, Appendix A, Technical Specifications.
A. Time Required to Implement: This change will be implemented immediately.
B. Reason for Change (DCR No. 87-0013): Clarify the boron c.oncentration requirements, in Technical Specification 3.9.1, for refueling conditions. Specifically, this revision clarifies that the boration requirements are not applicable when the reactor vessel is completely defueled.
C. Safety Evaluation: See attached Safety Evaluation (Attachment No. 1).
D. Significant Hazards Consideration: See attached Significant Hazards Consideration (Attachment No. 2).
Docket No. 50-346 License No. NPF-3 Serial No. 1459 Attachment 1 Page 1 SAFETY EVALUATION DESCRIPTION The purpose of this safety evaluation is to review proposed changes to the Davis-Besse Nuclear Power Station, Unit No. 1 Operating License, Appendix A, Technical Specifications. The changes are being made to clarify the statement in Technical Specification Limiting Condition for Operation (LCO) 3.9.1, which sets the requirements for boron concentration in all filled portions of the Reactor Coolant System (RCS) and the refueling canal during refueling operations.
The proposed changes to the Technical Specifications are:
- 1. Delete the asterisked footnote to the Applicability Statement of LCO 3.9.1, that reads: "The reactor shall be maintained in MODE 6 when the reactor vessel head is unbolted or removed." This footnote is being removed because it is an incomplete, unnecessary and misleading re-statement of the definition of Mode 6 in Technical Specification Table 1.1, Operational Modes.
- 2. Delete the parenthetical phrase "With the reactor vessel head unbolted or removed," at the beginning of LC0 3.9.1. This phrase is being removed because it is an incomplete, unnecessary and inappropriate re-statement of the Applicability Statement of LCO 3.9.1.
DISCUSSION Technical Specification Limiting Condition for Operation 3.9.1 requires that in Mode 6 (refueling), the boron concentration of the water in the reactor vessel and of all the water volumes that connect directly with the reactor vessel meet the more restrictive of the following two reactivity conditions:
-K eff is 0.95 or less.
- Boron concentration is greater than or equal to 1800 ppm.
This requirement guarantees an adequate shutdown margin during Mode 6 operations. It also makes a return to criticality accident in Mode 6 not credible, i.e., fuel cannot reach criticality as a consequence of fuel assembly or control rod assembly mishandling, or of a makeup system malfunction accident (reference Davis-Besse Updated Safety Analysis Report).
LCO 3.9.1 only applies when the plant is in Mod.e 6, refueling. According to Technical Specification Table 1.1, Operaticnal Modes, the following conditions must all be satisfied to be in Mode 6:
(1) -< 0.95 (2) RaK [ d thermal power (%) = 0 (3) Average coolant temperature < 140*F (4) Reactor vessel head unbolted or removed (5) Fuel in the vessel
Docket No. 50-346 License No. NPF-3 Serial No. 1459 Attachment 1 Page 2 Therefore, when the vessel head is unbolted or removed and fuel has been removed from the core, the vessel is no longer in Mode 6 and LCO 3.9.1 does not apply.
The asterisked footnote to the LCO applicability statement states: "The reactor shall be maintained in MODE 6 when the reactor vessel head is -
unbolted or removed". To avoid confusion, this footnote should be deleted. This footnote is an incomplete and and an unnecessary re-statement of the definition of Mode 6 in Technical Specification Table 1.1. Since -
it does not mention the provision of the Mode 6 definition, that there be fuel in the reactor, it could lead to the erroneous conclusion that boration of the RCS is required even when the reactor vessel is defueled.
To avoid confusion, the parenthetical phrase "With the reactor vessel l head unbolted or removed," which appears at the beginning of LCO 3.9.1, should also be removed. Given the applicability statement for LCO 3.9.1, !
and the definition of Mode 6 in Technical Specification Table 1.1, this phrase is also incomplete and inappropriate since it could be misinterpreted to assert applicability of LCO 3.9.1 when the reactor vessel is defueled.
The phrase and footnote in question are therefore not needed and potentially confusing. They can be removed without changing the intended applicability of LCO 3.9.1.
SYSTEM AND COMPONFNTS AFFECTED Reactor Coolant System / Reactor Vessel, e Refueling Mechanism / Refueling Canal. j DOCUMENTS AFFECTED l L
Davis-Besse Nuclear Power Station, Unit No. 1 Operating License, Appendix A Technical Specifications '
SAFETY FUNCTION OF SYSTEMS AND COMPONENTS AFFECTED i
Normally the RCS provides the mechanical piping, pressure boundary, and motive force to circulate reactor coolant through the reactor core for the ;
purpose of cooling the core. The reactor vessel is an integral part of the pressure boundary of the RCS. During refueling, the RCS is vented l because the reactor vessel head is removed. The RCS and reactor vessel '
then provide a watertight boundary for the borated water that ensures !
control of fuel reactivity, protection from radiation, and removal of !
decay heat.
The Refueling Mechanism provides a path and the necessary equipment to ,
remove spent fuel and enntrol components from the reactor core and add new and previously used fuel and control components during refueling operations. The refueling canal is a watertight connection between the opened reactor vessel and the fuel transfer tubes that allows the movement of spent and new fuel assemblies and control components underwater, for protection from radiation, control of fuel reactivity and removal of decay heat.
1 I
Docket No. 50-346 License No. NPF-3 Serial No. 1459 Attachment 1 Page 3 EFFECTS ON SAFETY The proposed changes to the Davis-Besse Technical Specification Limiting Condition for Operation 3.9.1, clarify this LCO by eliminating one phrase and a footnote that are unnecessary and potentially misleading from the text of the LCO. Elimination of the phrase and the footnote does not change in any way the requirements and applicability of LCO 3.9.1; boron concentration requirements will continue to be observed, when required to prevent _ criticality. However with no fuel in the reactor vessel, there is no concern for criticality and therefore boron requirements are not applicable. In conclusion, the proposed changes have no effect on the safety functions of any plant equipment and system.
UNREVIEWED SAFETY QUESTION EVALUATION The proposed changes to Davis-Besse Technical Specification Limiting Condition for Operation 3.9.1:
Do not increase the probability of an accident previously evaluated in the Updated Safety Analysis Report (USAR) because they have no effect on any system or equipment (10CFR50.59(a)(2)(i)).
Do not increase the consequences of an accident previously evaluated in the USAR because they do not change any assumptions made in previous accident analyses. An adequate shutdown margin will always be available when required (10CFR50.59(a)(2)(i)).
Do not increase the probability of a malfunction of equipment important to safety previously evaluated in the USAR because they do not affect any equipment (10CFR50.59(a)(2)(i)).
Do not increase the consequences of a malfunction of equipment important to safety previously evaluated in the USAR because they do not affect the safety function of any equipment, and an adequate shutdown margin will always be available when required (10CFR50.59(a)(2)(i)).
Do not create the possibility of an accident of a different type than any evaluated previously in the USAR because they have no effect on i any system, equipment or procedure. The requirements for ensuring an ,
adequate shutdown margin when needed remain unchanged; when the '
reactor vessel is defueled there is no concern for criticality and the requirements are not needed (10CFR50.59(a)(2)(ii)). ,
l Do not create the possibility of a malfunction of equipment of a l different type than any evaluated previously in the USAR because no l equipment functions are affected in any way (10CFR50.59(a)(2)(ii)).
I Do not reduce any margin of safety as defined in the basis for any j Technical Specification because they do not modify in any way the i basis for reactivity control and adequate shutdown margin during I refueling operations (10CFR50.59(a)(2)(iii)). !
l In conclusion, no unreviewed safety question exists. ,
l i
i i
Docket No. 50-346 License No. NPF-3 Serla! No. 1459 Attechment 2 Page 1 SIGNIFICANT HAZARDS CONSIDERATION DESCRIPTION The purpose of this License Amendment Request is to review proposed changes to the Davis-Besse Nuclear Power Station, Unit No. 1"Operating License, Appendix A, Technical Specifications. The changes are being made to clarify the statement in Technical Specification Limiting Condition for Operation (LCO) 3.9.1, which sets the requirements for boron concentration in all filled portions of the Reactor Coolant System (RCS) and the refueling canal during refueling operations.
The proposed changes to the Technical Specifications are:
- 1. Delete the asterisked footnote to the Applicability Statement of LCO 3.9.1, that reads: "The reactor shall be maintained in MODE 6 when the reactor vessel head is unbolted or removed." This footnote is being removed because it is an incomplete, unnecessary and misleading re-statement of the definition of Mode 6 in Technical Specification Table 1.1, Operational Modes.
- 2. Delete the parenthetical phrase "With the reactor vessel head unbolted or removed," at the beginning of LCO 3.9.1. This phrase is being removed because it is an incomplete, unnecessary and inappropriate re-statement of the Applicability Statement of LCO 3.9.1.
DISCUSSION Technical Specification Limiting Condition for Operation 3.9.1 requires that in Mode 6 (refueling), the boron contentration of the water in the reactor vessel and of all the water volumes that connect directly with the reactor vessel meet the more restrictive of the following two reactivity conditions:
-K egg is 0.95 or less.
- Boron concentration is greater than or equal to 1800 ppm.
This requirement guarantees an adequate shutdown margin during Mode 6 operations. It also makes a return to criticality accident in Mode 6 not credible, i.e., fuel cannot reach criticality as a consequence of fuel assembly or control rod assembly mishandling, or of a makeup system malfunction accident (reference Updated Safety Analysis Report).
LCO 3.9.1 only applies when the plant is in Mode 6, refueling. According to Technical Specification Table 1.1, Operational Modes, the following conditions must all be satisfied to be in Mode 6:
(1) -< 0.95 (2) K (bd R$ thermal power (%) = 0 (3) Average coolant temperature < 140 F (4) Reactor vessel head unbolted or removed (5) Fuel in the vessel
. .- .. . . . . - - = -. - - - - - - _ - -
Docket No. 50-346 License No. NPF-3 Serial No. 1459
, Attachment 2 2
Page 2 1
Therefore, when the vessel head is unbolted or removed and fuel has been removed from the core, the vessel is no longer in Mode 6 and LCO 3.9.1 does not apply.
"The-The asterisked footnote to the LCO applicability statement states:
reactor shall be maintained in MODE 6 when the reactor vessel head is unbolted or removed". fo avoid confusion, this footnote should be 4
deleted. This footnote is incomplete in that it does not state fuel is in the reactor vessel and is an unnecessary re-statenent of the definition of Mode 6 in Technical Specification Table 1.1. Since it does not mention the provision of the Mode 6 definition, that there be fuel in the reactor, it could lead to the erroneous conclusion that boration of the RCS is required even when the reactor vessel is defueled.
To avoid confusion, the parenthetical phrase "With the reactor vessel head unbolted or removed," which appears at the beginning of LCO 3.9.1, should also be removed. Given the applicability statement for LCO 3.9.1, and the definition of Mode 6 in Technical Specification Table 1.1, this phrase is also incomplete and inappropriate since it could be misinterpreted to assert applicability of LCO 3.9.1 when the reactor i vessel is defueled.
The B&W Standard Technical Specifications, NUREG-0103, Revision 4 utilizes a footnote, however the footnote states that it applies when fuel is in the reactor vessel. This footnote is also redundant to the defintion of Mode 6 in Table 1.1 of NUREG 0103, Revision 4.
The phrase and footnote in question are therefore not needed and potentially confusing. They can be removed without changing the intended applicability of LCO 3.9.1.
SYSTEM AND COMPONENTS AFFECTED Reactor Coolant System / Reactor Vessel.
Refueling Mechanism / Refueling Canal.
SAFETY FUNCTION OF SYSTEMS AND COMPONENTS AFFECTED Normally the RCS provides the mechanical piping, pressure boundary, and motive force to circulate reactor coolant through the reactor core for the purpose of cooling the core. The reactor vessel is an integral part of the pressure boundary of the RCS, During refueling, the RCS is vented because the reactor vessel head is removed. The RCS and reactor vessel then provide a watertight boundary for the borated water that ensures control of fuel reactivity, protection from radiation, and removal of decay heat.
The Refueling Mechanism provides a path and the necessary equipment to remove spent fuel and control components from the reactor core and add new and previously used fuel and control components during refueling i operations. The refueling canal is a watertight connection between the 3
a J
- m. , . , - . _ - - - - . - - - - . _ - _ _ - - - . -.
_ __ ._ - ~ , ., . - - - . - - _ - -
Docket No. 50-346 License No. NPF-3 Serial No. 1459 Attachment 2 Page 3 opened reactor vessel and the fuel transfer tubes that allows the movement of spent and new fuel assemblies and control components underwater, for protection from radiation, control of fuel reactivity and removal of decay heat.
EFFECTS ON SAFETY The proposed changes to the Davis-Besse Technical Specification Limiting Condition for Operation 3.9.1, clarify this LCO by eliminating one phrase and a footnote that are unnecessary and potentially misleading from the text of the LCO. Elimination of the phrase and the footnote does not change the requirements and intended applicability of LCO 3.9.1; boron concentration requirements will continue to be observed, when required to prevent criticality. However with no fuel in the reactor vessel, there is no concern for criticality and therefore boron requirements are not applicable. In conclusion, the proposed changes have no effect on the safety functions of any plant equipment and system.
SIGNIFICANT HAZARDS CONSIDERATION The proposed changes do not involve a significant hazards consideration because the operation of the Davis-Besse Nuclear Power Station, Unit No. 1, in accordance with these changes would not:
Involve a significant increase in the probability or consequences of an accident previously evaluated because the proposed change does not modify the basis for reactivity control. In addition, require-ments to maintain an adequate shutdown margin remain unchanged. Boron concentration requirements will still be required during refueling (Mode 6) and any time there is fuel in the vessel. The proposed change clarifies that boration requirements are not applicable when the reactor vessel is completely defueled and therefore, not a criticality concern (10CFR50.92(c)(1)).
Create the possibility of a new or different kind of accident from any accident previously evaluated because the proposed change has no effect on any system, equipment or procedures. The requirements to maintain an adequate shutdown margin remain unchanged; when defueled, there is no criticality concern and therefore boron concentration requirements are not needed (10CFR50.92(c)(2)).
Involve a significant reduction in a margin of safety because the proposed change does not modify the basis for reactivity control.
In addition, requirements to maintain an adequate shutdown margin remain unchanged. Boron concentration requirements will still be required during refueling (Mode 6) and any time there is fuel in the vessel. The proposed change clarifies that boration requirements are not applicable when the reactor vessel is completely defueled and therefore, not a criticality concern. (10CFR50.92(c)(3)).
CONCLUSION On the basis of the above, Toledo Edison has determined that the amendment request does not involve a significant hazards consideration.
Docket No. 50-346 License No. NPF-3 Serial No. 1459 Attachment 2 Page 4 REFERENCES
- 1. Davis-Besse Nuclear Power Station Updated Safety Analysis Report.
- 2. Bechtel Drawing No. 7749-C-193, Revision 5.
- 3. Davis-Besse Nuclear Power Station, Plant Procedure PP 1501.01, Revision 8.
- 4. Davis-Besse Nuclear Power Station, Written Safety Evaluation for FCR 87-0134.
- 5. Davis-Besse Nuclear Power Station, Fuel Handling Manual.