ML20148S232

From kanterella
Jump to navigation Jump to search
Insp Rept 50-289/97-04 on 970512-15.Violations Noted. Major Areas Inspected:Insp Evaluated Licensee Performance During Remedial EP Exercise
ML20148S232
Person / Time
Site: Crane Constellation icon.png
Issue date: 06/27/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20148S183 List:
References
50-289-97-04, 50-289-97-4, NUDOCS 9707080139
Download: ML20148S232 (67)


See also: IR 05000289/1997004

Text

.

.

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

Docket No:

50-289

Report No:

50-289/97-04

Licensee:

GPU Nuclear

Facility:

Three Mile Island Nuclear Generating Station

Location:

P.O. Box 480

Middletown, PA 17057

Dates:

May 12-15,1997

Inspectors:

J. Laughlin, Emergency Preparedness Specialist, Region i

J. Lusher, Emergency Preparedness Specialist, Region l

N. McNamara, Emergency Preparedness Specialist, Region i

D. Silk, Sr. Emergency Preparedness Specialist, Region i

W. Maier, Emergency Preparedness Specialist, NRR

S. Klementowicz, Health Physicist, NRR

M. Evans, Sr. Resident inspector, Three Mile Island

G. VanSickle, AEOD, TTD

R. Bores, Senior Project Manager, Division of Reactor Safety

Approved by:

James T. Wiggins, Director

Division of Reactor Safety

9707000139 970627

PDR

ADOCK 05000289

G

PDR

1

_

.

.

EXECUTIVE SUMMARY

Three Mile Island

Remedial Emergency Preparedness Exercise Evaluation

Inspection Report 50-289/97-04

This inspection evaluated the licensee's performance during its remedial emergency

preparedness (EP) exercise. The inspectors observed emergency response facility (ERF)

staffing, procedure implementation, effectiveness of mitigation actions, communications,

command and control, emergancy classification, offsite notifications, and protective action

recommendation (PAR) formulation. The inspectors also assessed licensee activity

pertaining to the four exercise weaknesses that were identified during the March 5,1997

full-participation exercise.

Overall exercise performance was good, and much improved over the March 5 exercise.

Event classifications were timely and accurate. Notifications to offsite officials and the

NRC were timely. The PAR was appropriate and transmitted to offsite agencies in a timely

manner. There was very good interaction between the EOF staff and Commonwealth of

PA staff, a noticeable improvement since the March exercise. Remediation of the four

weaknesses from the March exercise was adequately demonstrated during this exercise,

and two of them are closed. However, two of the weaknesses are still being considered -

for enforcement action (not declaring a General Emergency in a timely fashion, and not

considering a PAR outside 10 miles). The weakness (weak dose assessment) and

unresolved item (PAR methodology not conforming to federal guidance) from the 1995

exercise were closed as well.

The licensee's post-exercise critique was also much improved over the one in March,

identified most of the NRC independent findings, and was assessed as good.

Three issues identified during the inspection of the licensee's corrective actions taken for

the March exercise weaknesses, were determined to not be in compliance with NRC

requirements. First, there was no documentation of the continuous on-line assessment or

quick calculation computer codes, nor were there written procedures to aid dose assessors

in performing dose projection calculations. Secondly, the licensee assigned individuals to

its ERO duty roster whose qualifications had lapsed. Lastly, although the EP program

audits identified this ERO qualification issue and other deficiencies, the audit process was

inadequate to correct tho.se deficiencies. These issues are violations of NRC requirements.

Although the TSC staff was able to accurately use the new steam generator leakrate

,

calculation tool during this exercise, there was disagreement between ERO members

concerning its use. Additional guidance may be needed for 1) who should use the tool,

and when it should be used, and 2) the limitations of the tool related to damage class

estimates and use in differing scenarios.

ii

_

_ . _ _

.-. _ _ _ _

_ _ _ _

__

__

._

__ . _ _ _ _

_

d

1

.

TABLE OF CONTENTS

,

,

,

PAGE NO.

EX EC UTIVE S U M M ARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii

,

.

R e p o rt D e t a ils . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

l

P3

EP Procedures and Documentation

1

................................

P3.1

Review of Procedure Revision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

i

.

P3.2 Documentation of Dose Assessment Computer Codes and Associated

User Manuals

1

..........................................

P4

Staff Knowledge and Performance

2

~

................................

P4.1

Exercise Evaluation

2

......................................

P4.2 Operator Walkthroughs on the Dynamic Simulator . . . . . . . . . . . . . . . . 9

P4.3 Dose Assessment Team Walkthroughs

10

.......................

.

P5

Staf f Training and Qualification in EP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

P5.1

Dose Assessment Training . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

j

P5.2 ' Lapse in ERO Qualifications

11

j

...............................

,

!

P7

Quality Assurance in EP Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

i

P8

Miscellaneous EP Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

P8.1

(Closed) Weakness Observed During the April 12,1995 Full-

.

participation Exercise: Weak Ability to Rapidly Assess and Reliably

Predict Potential Offsite Radiological Consequences . . . . . . . . . . . . . . 14

P8.2 (Closed) Unresolved item (URI 50-289/95-05-01): PAR Logic

Methodology Not Conforming With Federal Guidance . . . . . . . . . . . . . 14

P8.3 (Open) eel 50-289/97-02-01: Failure to recognize and classify a GE . . 15

-

P8.4 (Closed) IFl 50-289/97-02-02: Inadequate technical analysis by TSC

staff . .. . .... . .. ... ... .. .. .. ....... ...... .. .. ..... ... 16

P8.5 (Closed) IFl 50-289/97-02-03: Incorrect analysis of steam generator

t u be le a k ag e . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

'

P8.6 (Open) eel 50-289/97-02-04: Failure to assess need for PAR beyond

10-mile EPZ

16

..........................................

P8.7 Updated Final Safety Analysis Report (UFSAR) Review . . . . . . . . . . . . 17

P8.8 in-Office Review of Licensee Procedure Changes . . . . . . . . . . . . . . . . 17

V. M anagement Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

X.1

Exit M e e t i ng . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

PARTI AL' LIST OF PERSONS CONTACTED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

<

INSPECTION PROCEDURES USED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

iii

m .... _ _ ._.

_ _ - - - _ . _ . _ _ _ _ _ _ . . _ _ _ _ _ _ . _ . _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ . _ . _ _ . _ . _ _ _ . . _ . _

,

,

!

i

b

l

-

I

TABLE OF CONTENTS

PAGE NO.

i

l

ITEMS OPENED, CLOSED, AND DISCUSSED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

LI ST OF AC RO NYM S U SED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

l-

.

l

l

ATTAC H M E NT 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23-

!

!

l

[i '

!

I

l

I

i

'

!

!

I

l

!

t

!-

!

i

!

!

i

I

!

l

l

.

(

.

4

.

.IV

'

l

'

t .

- . .

. . .-

_ . - .

.

. -

.

.

.

_ . . . . _ . .

. . _ __

_

.

.

Report Details

IV. Plant Support

P3

EP Procedures and Documentation

P3.1

Review of Procedure Revision

a.

Insoection Scope (92904)

'

The inspectors reviewed the licensee's reviser' emergency plan implementing

procedure (EPIP)-COM .44, " Thyroid Blocking," to determine if the appropriate

j

changes had been made to satisfy NRC concerns identified during the March,1997

exercise.

b.

Observations, Findinas and Conclusions

During the March 5-7,1997, inspection of the licensee's full-participation exorcise,

the inspector reviewed procedure EP!P-COM .44, " Thyroid Blocking," and found

that it directed the Radiological Assessment Coordinator (RAC) to perform an

- assessment of radiation workers' doses prior to authorizing the administration of

'

potassium iodide (KI) for thyroid blocking, but the procedure did not contain any

guidance on how to perform the assessment. The licensee agieed to review the

'

procedure and make the appropriate changes. During this exercise inspection, the

licensee provided the revised procedure which included specific guidance for the

RAC to use in determining if Kl should be administrated to workers. The inspectors

considered this guidance to be acceptable. No additional problems were noted.

P3.2 Documentation of Dose Assessment Computer Codes and Associated User Manuals

'

a.

Inspection Scone (92904)

The inspectors sought to review documentation of the continuous on-line

assessment (COLA) computer code, RAC computer code, and the quick calculation

computer code. They also reviewed the licensee's Emergency Dose Ca/cu/ation

Manual (EDCM) and various other dose assessment documentation to determine the

adequacy of that documentation for accident assessment.

b.

Observations, Findinas, and Conclusions

The inspector requested the documentation for the COLA computer code, the RAC

computer code, and the quick calculation computer code. No documentat;on was

available for the COLA or quick calculation codes, and the documentation for the

RAC code was minimal. The inspectors concluded that these computer codes

needed thorough verification and validation to ensure that licensee personnel are

knowledgeable on current system operation. Additionally, no user manuals were

available for any of the dose assessment computer codes. The licensee had

.

.

2

developed some informal guidance for use of the codes by dose assessment staff,

but this guidance had not been incorporated into procedures or a formal training

program. The inspectors also noted there was no reference to the use of these

computer codes in the EPIPs.

The inspector reviewed the EDCM, revision five, dated October 30,1995,and

Temporary Change Notice 1-97-0010 to the EDCM, dated February 26,1997. The

'

EDCM provides the basis for the calculations used in the RAC code, but does not

provide any consideration for radiciodine and radioactive particulate depletion under

various reactor accident conditions and for various release pathways. Though the

EDCM is referenced in the licensee's EPIPs, it was not apparent to the inspectors

that the information it contains is utilized for assessment. The inspectors concluded

through table-top walkthrough exercises with dose assessment staff and the

licensee's performance during the remedial exercise that the staff could adequately

use the computer codes for dose assessment calculations. However, the lack of

documentation and user manuals greatly hampered the consistency and quality

control of dose assessment training to ensure sustained good performance.

The licensee's Technical Specifications, Section 6.8.1 states, in part " Written

procedures shall be established, implemented and maintained covering the items

referenced below: ... f. Emergency Plan implementation." The licensee had no

written procedures to aid dose assessors in performing dose projection calculations.

l

As mentioned, there was no documentation for the COLA and quick calculation

computer codes. The inspectors concluded that dose assessment personnel were

'

dependent on training and informal mechanisms, rather than strutured procedures

and documentation to perform their assessment function. This resulted in a dose

,

assessment weakness during the April,1995 exercise and inaccurate assumptions

which led to excessively high dose projection calculations during the March,1997.

exercise. The lack of documentation of the dose assessment computer codes and

procedural guidance for their use is a violation (VIO 50-289/97-04-01).

P4

Staff Knowledge and Performance

P4.1

Exercise Evaluation

i

a.

Exercise Evaluation Scoce (82301)

During this inspection, the inspectors observed and evaluated the licensee's

remedial, emergency preparedness exercise, to verify the effectiveness of corrective

actions taken as a result of poor performance in the March 5,1997 full-participation

,

exercise, when four exercise weaknesses were identified. The NRC team observed

activities in the emergency control center (ECC) simulator, technical support center

(TSC), operations support center (OSC), and emergency operations facility (EOF).

The inspectors assessed licensee recognition of abnormal plant conditions,

classification of emergency conditions, notification of offsite agencies,

.

.

3

development of PARS, command and control, communications, and the overall

implementation of the Emergency Plan. In addition, the inspectors attended the

licensee's post-exercise critique to evaluate the licensee's self-assessment of the

exercise.

b.

Emeraency Resnonse Facility (ERF) Observations and Critiaue

b.1

Emeraency Control Center (ECC)

The Emergency Response Organization (ERO) staffed the ECC in a timely manner.

The facility was functional within thirty minutes of the Alert declaration.

The Emergency Director (ED) exhibited very strong command and control of the

ECC staff. He effectively directed the staff to accomplish diverse tasks

concurrently. He delivered clear, accurate briefings to the ECC staff at appropriate

intervals, and effectively consulted with his staff when collegial discussions we.a

needed.

All emergency event classifications were accurate and timely. The General

Emergency (GE) declaration was based on Emergency Action Leve! (EAL) G4.2, i.e.,

" loss of two fission product barriers with a potential loss of the third." The ED

declared the GE, with Emergency Support Director (ESD) concurrence, because the

reactor coolant system and fuel clad barriers were lost, and the containment was

challenged. The inspectors noted that the basis for EAL G4.2 provides some

guidance for determining whether barriers are challenged or breached, but does not

specify guidance for every possible situation. Therefore, the ED exercised -

judgement in determining that the containment barrier was challenged. The

inspectors concluded that the GE declaration was appropriate in this case for the e

existing plant conditions, which were degrading Therefore, the weakness

concerning the failure to recognize and classify a GE from the last exercise was

adequately demonstrated during this exercise. However, it is being considered for

enforcement action (See Section P8.3).

The inspectors reviewed the licensee's proposed Revision 5 to the classification

procedure, which is based on the NUMARC guidance contained in NUMARC/NESP-

007 and endorsed by the NRC in Revision 3 to Regulatory Guide 1.101. This

revision contains an explicit " judgement" EAL for GE conditions that is completely

!

separate from the fission product barrier EALs. Therefore, this revision, when

approved by the NRC, will provide a GE-level " judgement" EAL and remove the

{

potential arbitrariness of GE declarations based on the challenge to fission product

l

barriers.

l

l

Notifications made to offsite authorities and the NRC for the Alert and Site Area

Emergency were timely and accurate.

l

I

I

i

J

-

>

i

,

4

The ED and his staff appropriately considered the safety of onsite personnel. When

'

the release from the Reactor Building began, the ED consulted with the Radiological

Assessment Coordinator (RAC) concerning emergency dose authorizations for repair

teams, and also evaluated the need for administration of thyroid blocking agent to

those teams.

However, the ED was slow (delayed about one hour) in requesting a reactor coolant

sample after the trip of reactor coolant pump.1 A. This sample would have provided

information on potential fuel damage, as well as aided in quantifying primary-to-

secondary leakage, and any potential offsite doses.

The ECC staff effectively assessed plant conditions and initiated timely and

appropriate corrective actions. For example, the Operations Coordinator (OC) was

proactive in his efforts to reinstate Auxiliary and Fuel Building ventilation after it

was lost. He also provided timely background information to the ED to evaluate a

- 4

discrepancy between radiation monitoring channels in the Reactor Building. The

'

Shift Technical Advisor continuously monitored plant temperature and pressure and

reported these parameters' proximity to various thermal limits.

i

Throughout the exercise the operating crew effectively dealt with the challenges to

plant safety. The operators implemented the appropriate emergency operating

j

procedures in'a timely manner. Procedural adherence was evident. The crew

'

employed strong operating practices such as the initialing of procedural step

completion and the use of repeat-backs in communications.

One operating decision was made without explicit procedural direction. During the

latter stages of the exercise, with a reactor coolant system (RCS) leak of greater +

'than 2000 gpm, the operators throttled low pressure injection (LPI) flow to the RCS

- -

in order to maintain a desired RCS pressure. The licensee's small-break loss of

coolant accident cooldown procedure (in effect at the time) provides no guidance

relative to throttling LPI flow. This decision did not adversely affect plant safety, as

LPI flow adequately compensated for the RCS leakrate. The licensee's Operations

Department acknowledged this procedural weakness and is evaluating the issue

through its " Procedure Problem (s) Identified by. Training" process.

b.2 Dose Assessment in the ECC

Shortly after the Alert declaration, the Group Radiological Controls Supervisor

arrived at the ECC and activated the dose assessment function. He immediately

activated the automated dose assessment computer to obtain an initial dose

assessment and called for additional personnel.

The RAC arrived within 15 minutes of the Alert declaration and, after receiving a

-turnover, took charge of the dose assessment function. The RAC exhibited

excellent command and control of the dose assessment team. -Team members were

assigned positions and directed to review procedures to support dose

.

O

5

assessment activities. The RAC routinely briefed the team members on plant status

and his communications were clear and direct. The use of repeatbacks was

observed in communications and, in at least one case, prevented the

communication of erroneous information,

i

The RAC directed his staff to perform dose projection calculations based on existing

plant conditione using the continuous on-line assessment (COLA) computer code

and to perform "what if" calculations using the manual code. The personnel using

the codes appeared knowledgeable and used the appropriate correction factors

when using the manual code,

i

The field monitoring team (FMT) data were provided by onsite and offsite teams.

Communications between the RAC and the FMTs were good. The RAC positioned

the FMTs effectively based on the meteorological data so that they could measure

the radiation levels and obtain air samples. The RAC used the field data in

conjunction with the data from the Reuter-Stokes (R-S) area radiation monitors to

verify the accuracy of the dose projection calculations.

The inspectors observed effective coordination between the RAC and the

Radiological Controls Coordinator (RCC)in the OSC concerning the radiological

safety of radiation survey and repair teams. The RAC discussed the need for

radiation dose extensions with the ED in order to complete repairs of plant

equipment.

Overall, the inspectors noted effective coordination, teamwork, and communication

between dose assessment personnel and the ED concerning radiological conditions.

The RAC demonstrated excellent control of the dose assessment area and direction

of the FMTs. He had frequent interactions with his staff, the ED, and the operating

j

crew concerning radiological conditions, both onsite and offsite. He exhibited a

questioning attitude and continually anticipated the next course of action. Dose

assessment team members effectively performed their job functions.

A weakness from the April,1995 exercise concerning the licensee's ability to

rapidly assess and predict potential offsite radiological consequences was reviewed.

During this exercise, the licensee adequately demonstrated its ability to perform

effective dose assessment calculations and make protective action

recommendations. This exercise weakness is closed.

b.3 Technical Sucoort Center (TSC)

i

The TSC was staffed and activated in a timely manner. The TSC coordinator

(TSCC) exhibited good command and control throughout the drill. His staff briefings

were generally done at appropriate intervals. TSC priorities were properly identified,

matched ECC priorities, and were appropriately assigned for followup to the TSC

staff. Since the March 5,1997 exercise, a new status board was added to the

TSC, which presented event classification, status of fission product barriers, and

NRC fuel damage class. This information ensured that TSC staff members were

uniformly aware of important information.

.

l

'

6

The TSCC and his assistants effectively processed the available data to make

accurate assessments of plant conditions. The TSC staff was aware of plant

conditions shortly after events occurred and in some instances as they occurred.

The addition of a plant performance monitor (PPM) computer in the TSC was a

major enhancement. For example, through monitoring the computer, an engineer

l

identified the first RCS leak prior to being informed of the leak by the ECC. On

another occasion, an engineer identified a reduction in LPI flow shortly after it

occurred, and questioned the operators' basis for the reduction in flow. The new

staffing arrangement in the TSC, which provided the TSCC an assistant and

advisor, generally improved the operation of the TSC. However, occasionally the

roles of the coordinator and the assistant overlapped which appeared to cause some

difficulty in the flow of information. The coordinator addressed this problem on

several occasions by conducting briefings with his assistant and advisor.

The TSC staff effectively referenced plant procedures to maintain an understanding

of plant conditions. The EALs were reviewed and discussed with the ECC. The

TSC did not fully understand the basis for the GE declaration and appropriately

questioned the ECC. The TSC staff provided good identification and evaluation of

several "what if" scenarios. For example, they pursued writing a procedure for

starting a reactor coolant pump with no sealinjection flow assuming they could

potentially lose the only operating make up/high pressure injection pump. The TSC

staff appropriately calculated fuel damage class as needed during the drill.

The TSC staff appropriately used the RCS activity versus condenser off-gas monitor

readings, as well as discussions with the RAC, to calculate the primary-to-

secondary leakrate. Although, their calculation did not match the expected result

(they calculated between .1 and .5 gpm versus the actual 3.0 gpm leakrate on the

simulator), it was an appropriate calculation based on the radiation monitor data

available during the exercise.

The TSC staff also demonstrated that they could effectively deal with conflicting

,

information within the ERO. For example, while the TSC staff used the new

radiation monitor leakrate methods to calculate primary-to-secondary !eakrate, the

RAC used the new tool to estimate fuel damage class by assuming that the primary-

to-secondary leakrate had not changed. Therefore, the RAC considered the increase

in condenser off-gas reading to be due to increased RCS activity and thus a change

in fuel damage class. It was not clear to the inspector that the new leakrate

method was intended to be used in this manner. As a result, the TSC staff

unnecessarily expended additional resources to evaluate conflicting information on

damage class reported by the RAC early in the drill. The disagreement between the

RAC and the TSC staff conceming the use of the tool for estimating fuel damage

class demonstrated that additional guidance may be needed for: 1) how, who, and

when the tool should be used, and 2) the limitations of the tool related to damage

class estimates and use in differing scenarios (IFl 50-289/97-04-02).

--

_.

.

.. -

. ~ .-- -

-

. - - .

.

. .

. ~ - . .

--

..

!

'

.

.

7

In conclusion, the overall technical analysis of simulated accident conditions

,

provided to the ECC by the TSC staff during the exercise was excellent. Therefore,

the weakness concerning inadequate technical analysis by the TSC staff during the

March 5 exercise is closed (See Section P8.4). Additionally, the TSC staff was able

-

to use the new assessment tool to accurately calculate primary-to-secondary

leakage. The weakness related to the incorrect analysis of primary-to-secondary

1

leakage is also closed (See Section P8.5).

b.4 Operations Sucoort Center (OSC)

.

The OSC was staffed and activated within 15 minutes of the Alert declaration. The

OSC Coordinator exhibited excellent command and control, provided detailed

briefings and effectively utilized the expertise of his managers. Logs and status

boards were well-maintained and in-plant repair teams were effectively tracked.

,

i

Job priorities were established, tracked and adjusted when plant conditions

changed.

,

The licensee dispatched 15 in-plant repair teams. The emergency maintenance

<

coordinator ensured the teams were thoroughly briefed before dispatch. The

inspector observed one of the maintenance teams and found the team members to

be professional, knowledgeable, and capable of performing their assigned task. The

1

'

inspector observed very good teamwork and excellent discussions among the OSC

,

staff for deciding the process for closing the inboard reactor building purge valve.

Two TSC engineers provided their technical expertise, ERO staff thoroughly

evaluated plant diagrams, and a video picture was obtained to view the valve

location.

'

The Radiological Controls Coordinator was very good at ensuring radiological

conditions were discussed with the repair team members, alternative routes for

teams were discussed to ensure that doses were maintained as low as reasonably

'

achievable, and dose extension approvals were obtained in a timely manner.

Overall, the OSC performance was excellent.

b.5 Emeraency Operations Facility (EOF)

The command and control in the EOF demonstrated by the emergency support

,

director (ESD) was very good. The ESD maintained a professional environment by

keeping the noise level to a minimum and instructing his staff to not bring food into

the working area. The ESD held frequent and informative briefings via the public

address system to inform the EOF staff of current conditions. The ESD conducted

effective meetings with the EOF team leaders by eliciting input, discussing

mitigation strategies, and anticipating emergency classification escalation and the

acsociated PAR.

.

.

8

The EOF staff interfaced well with representatives from the Commonwealth of

Pennsylvania during the exercise. These representatives were included in the

licensee's team leader meetings where their comments and questions were well

received and appropriately addressed by the EOF staff. The staff kept the

Commonwealth representatives apprised of changing plant conditions. The

notification of the GE classification, and the associated PAR, was communicated to

Commonwealth and county officials in a timely manner. Plant and radiological

conditions were reviewed continuously with Commonwealth representatives to

assess the need to extend the PAR out to 10 miles or beyond. Overall, the

interaction between the licensee and offsite officials was very good.

The technical support staff in the EOF promptly and thoroughly assessed plant

conditions. Plant status and conflicting information was continuously verified for

accuracy. The technical support staff maintained contact with and worked closely

with TSC staff in assessing plant status and developing mitigation strategies. The

EOF staff closely tracked all assigned tasks to their completion. Overall, the

technical support function at the EOF was performed very well.

The inspectors attended the post-exercise debrief of players and observers at the .

EOF. The debrief was appropriately self-critical as the comments were balanced

with positive and negative observations.

Overall, the inspectors assessed the licensee's performance at the EOF to be very

good.

b.6 Dose Assessment - EOF

The performance of the Group Leader Radiological and Environmental Controls

(GLR &EC) was good. He was constantly aware of the radiological problems onsite

and offsite. He directed good discussion of the primary-to-secondary leakage issue

with his staff and the TSC staff. He also discussed at length the PAR decision with

the ESD and Commonwealth of PA representatives, and provided key input for the

final decision. The assistant GLR &EC performed several "what if" dose assessment

calculations prior to the release to determine potential offsite consequences,

including ones beyond the 10-mile emergency planning zone (EPZ).

However, the EOF staff did not establish a priority for obtaining a reactor coolant

sample to verify the radiological source term and the amount of primary-to-

secondary leakage. The inspector also noted that if the EOF dose assessment staff

had been limited to the minimum staffing levels prescribed in the emergency plan,

they may not have been able to effectively accomplish all tasks required of them.

Overall, the performance of the EOF dose assessment staff was good.

._

_ _ . _ _ _ _ _ _ _

  • -

.

9

b.7 Exercise Conduct

The licensee exhibited appropriate control of the exercise. Drill controllers

maintained minimalinteraction with exercise players and followed the scenario

scope and timeline. The inspectors observed no prompting of the players and all

cues given to the players were appropriate,

b.8 Licensee Exercise Critioue

!

Immediately following the exercise, the licensee began its critique process. Players

and controllers assembled in their assigned facilities and conducted a' critique of .

?

i

their exercise performance. The inspectors noted that these facility critiques were

very effective and provided an improved level of self assessment compared to the

i

ones following the March 5 exercise.

t

The NRC inspection team attended the licensee's formal critique on May 15,1997.

!

This critique was much improved over the previous formal critique. The licensee

{

discussed in detail whether the exercise objectives were met. Findings were

-i . characterized clearly for management, identified most NRC findings, and was

' assessed by the team as good.

c.

Overall Exercise Conclusions

I

Overall, the licensee's exercise performance was good, and showed much

improvement over the March 5 exercise. The ERFs were staffed in a timely manner.

- All ERF managers exhibited good command and control. The classification of

. simulated accident events were timely and accurate. Notifications to offsite -

,

officials and the NRC were timely. The PAR was appropriate and transmitted to ;~

. l

offsite agencies in a timely manner. The performance of the OSC staff was

excellent and the OSC coordinator demonstrated excellent command and control.

The four weaknesses from the March exercise were adequately demonstrated and

two were closed. However, two of the weaknesses are being considered for

enforcement action. The weakness and unresolved item from the April,1995

exercise were also closed. The licensee's post-exercise critique was much

improved, identified most NRC findings, and was assessed as good.

P4.2 Operator Walkthrouahs on the Dynamic Simulator

a.

Inspection Scooe (92904)

The inspectors observed three senior reactor operators (SROs) classify simulated

accident events during scenarios on the simulator in dynamic mode, to assess the

classification training provided to SROs.

l

.

4

_ ,

.

.-

..

..

.

. .

.

. _ . _ .

O

.

10

b.

Observations. Findinas, and Conclusions

All SROs observed (two shift supervisors and one shift foreman) correctly classified

the simulated events and made appropriate classification upgrades, as necessary.

Overall, the inspectors assessed the operators' training and ability to use the EALs

,

for event classification as good.

'

P4.3 Dose Assessment Team Walkthrouahs

a.

Insoection Scoce (92904)

The inspectors conducted table-top walkthrough exercises with two dose

assessment teams, each consisting of a Radiological Engineering Support Engineer

(RESE), a Radiological Assessment Coordinator (RAC), and a Group Leader-

Radiological and Environmental Controls (GLR &EC), to assess the adequacy of dose

assessment training,

j

b.

Observations. Findinos, and Conclusions

Both dose assessment teams observed performed wellin their understanding and

use of the dose assessment computer codes. They were knowledgeable of the

assessment process and understood the limitations / assumptions of the codes. They

were also familiar with the informal guidance recently provided for computer code

use. Inspectors concluded that although the licensee lacked computer code

documentation and user manuals for the codes, the training provided to team

members was adequate for . factive assessment of radioactive releases and their

consequences.

j

P5

Staff Training and Qualification in EP

i

PS.1

Dose Assessment Trainina

l

a.

Inspection Scoce (92904)

The inspector reviewed lesson plans and training examinations for 1995 and

1996, and interviewed training instructors and ERO personnel to determine

the adequacy of the dose assessment training,

b.

Observations, Findinos and Conclusions

The licensee provided extensive dose assessment training after the March,

1997 exercise. The inspector reviewed the lesson plans and procedures and

found them to include both classroom instruction and hands-on training.

Some of the topics discussed included review of the existing COLA screens,

.

.

11

situational analysis, and the PAR logic revision. The inspector reviewed the

examinations and determined the exams given to the EOF dose assessment team to

be somewhat abbreviated and nontechnical. The exams for the ECC dose

assessment teams were more challenging with some technical questions, and the

average grade was 99 percent.

The inspector discussed the dose assessment training with dose assessment

team members and they indicated that training was adequate and had

improved over the past two years. The remedial training that was provided

after the March,1997 exercise was excellent because it provided

discussions of the methodology for assessing releases and their

consequences when using the COLA or manual dose assessment models.

During the interviews, the dose assessment teams referred to a " dose

assessment committee." This was not a formal committee but it was

established to look into the maintenance of the dose assessment models and

respond to any dose assessment concerns. Dose assessment team members

acknowledged that the committee was an excellent idea, however, it did not

meet on a regular basis, and there were no formal procedures that described

the activities of the committee, such as handling suggestions for

improvements. The inspector assessed the committee as an excellent

initiative, which could assist the licensee in maintaining the dose assessment

program, and address identified concerns and problems.

1

P5.2 Laose in ERO Qualifications

a.

Insoection Scope (92904)

The inspector reviewed the 1995 and 1996 quality assurance audits to assess an

I

issue concerrdng the lapse in qualifications of some ERO personnel.

b.

Observations. Findinas and Conclusions

While reviewing the quality assurance audits of 1995 and 1996, the

inspector noted that the licensee identified several instances in which ERO

personnel had allowed their respirator training or whole body count to expire.

The EP staff was aware of this recurring problem and has been working to

establish effective tracking systems. As a result of improved tracking of

1

expired qualifications, the number of unqualified individuals has decreased in

I

the past three years. Although the tracking systems have improved the

process, the licensee plans to present this matter to site plant management

to gain support and endorsement in ensuring that all ERO personnel are

aware of their responsibilities to maintain their qualifications current.

The inspector determined that the licensee did not follow procedure TEP-

ADM-1300.02, " Emergency Pieparedn9ss Training," Section 4.0, Exhibit 1,

which states in part, "On-Shift Emergency Organization, initial Response

Emergency Organization and Emergency Support Organization must

!

i

l

.

4

.

12

satisfactorily complete and maintain EP training program requirements for the

position assigned and must satisfactorily maintain respirator qualifications

and General Employee Radiation Worker Training (Category ll) and must be

active in the dosimetry system." Therefore, the inspector concluded that the

licensee repeatedly, over a three year period, had individuals on the ERO

duty roster that were not qualified. This is a violation (VIO 50-289/97-04-

03).

P7

Quality Assurance in EP Activities

a.

Inspection Scoce (92904)

The inspector reviewed Nuclear Safety Assessment (NSA) EP program audit

reports, quality deficiency reports (ODRs), procedures and other

documentation tc assess the adequacy of the EP audits conducted in 1995

and 1996. The inspector also interviewed the 1996 audit team leader, EP

Manager, and EP staff members.

b.

Observations and :indinas

The NSA Dcortment conducts an annual EP program quality assurance

audit. The 19S5 and 1996 audits were conducted by the same two NSA

staff members wiih no EP technical experience. The audits consisted of an

audit plan and checkUst and were conducted over a three-month period. The

inspector reviewed the 1995 and 1996 audit reports and identified several

areas of concern.

The licensee's Emergency Plan, Section 8.2.1, required essential personnel

to reverify their assigned EP training every 12 to 15 months to maintain

current qualifications. A ODR, number 942005 was issued to the EP

Department as a result of a 1994 EP program audit for a number of

individuals on the ERO duty roster with incomplete training. As a result of

this deficiency, the EP staff implemented a computerized EP qualification

tracking system in late 1994 to monitor training qualification records.

However, during the 1995 EP program audit, nine individuals were identified

with expired qualifications, four of which were on duty. The audit report

indicated that an additional computarized tracking system was being

implemented and scheduled for completion by September 1,1995 and ODR

942005 remained open.

In February 1996, the QDR was closed by memorandum from the EP Manager to

the Director, Radiation Health and Safety, stating that the EP Department continued

to monitor EP qualifications and a new tracking system was in place. However,

during the 1996 EP program audit, an EP staff member stated that over a six-month

period, ten ERO personnel had their qualifications lapse, three of which were on

duty. The report stated, "since the actual error rate for expirod qualifications while

on duty is very low it will be considered a minor deficiency."

.

l

.

i

13

The NSA Audit Program Procedure 1110-ADM-7218.10 defines a minor

deficiency as one not being programmatic, not generic, does not compromise

quality, is not potentially reportable, and/or corrective action would not be

extensive. The independent safety reviewer who evaluated the 1996 audit

stated that "no significant safety conditions were identified, all findings were

properly characterized as QDRs or minor deficiencies and no undetected

trends were identified by this review." The inspector disagreed with the

decision to downgrade the ODR to a minor deficiency and the determination

that no trends were identified since ERO qualification problems had been

identified in the past three audits (one individual's qualifications had lapsed

as recently as March,1997). The audit team leader stated that the EP staff

identified the individuals and removed them from the ERO upon discovery.

Since the EP staff was addressing the ERO qualification problem, NSA

decided that a QDR was not necessary. Also, the auditor stated that NSA

did not do an independent assessment during the 1996 audit to verify that all

members of the ERO were qualified at that time.

Discussions with the EP Manager about this matter indicated that the

problem was not only poor tracking systems but also the lack of

management expectations regarding ERO personnel maintaining their

qualifications current, and the consequences for not doing so.

While reviewing the audit reports, the inspector noted other " minor deficiencies"

that were similar in nature in the 1995 and 1996 reports. For example, copies of

EPIPs, the Emergency Plan, and operating procedures and drawings located in

various ERFs were found to be out of date.

In 1996 it was identified that the equipment kits were insufficient and kit

inventories were not being prt arly conducted. Since these issues were

corrected during the audit, the ucensee included them as findings, but did

not assess them as deficiencies. The NSA did not trend these similar

findings and therefore had no historical reference of the EP Department's

performance in this area for identifying recurring issues.

In 1995 it was identified that Lancaster County officials were concerned

about the handling of false siren soundings. The EP staff informed the

auditors that only a few sirens had been inadvertently activated and a

system upgrade was expensive. The EP staff committed to evaluate the

siren system. The 1996 audit stated "there is still a problem with false siren

soundings" and that EP is getting contract bids for installation of a system to

identify faulty sirens and give feedback directly to the counties. Although

this was a repeat item, it was not made a deficiency in the 1996 audit

report. The OA team leader stated that since the EP staff had been

.

.

14

reviewing this concern for the past two years, and was in the process of making

additional corrective action decisions, the issue did not warrant a deficiency. The

licensee appeared to characterize the repeat audit finding as insignificant due to the

EP staffs' commitment to continue to review the issue. The NSA was

nonconservative in its characterization of findings as conditions adverse to quality,

c.

Conclusions

The inspector determined that the audits covered many areas of review but that

they appeared to be narrowly focused on compliance rather than substance. The

short-term corrective actions taken by the EP staff that were identified during the

audit were considered acceptable even though an in-depth review for determining

the adequacy of the corrective actions was not performed. Characterization of

audit findings appeared to be negotiated with the EP staff and minor deficiencies

were not trended for determination of recurrence. Overall, the inspector assessed

the NSA audit of the EP program to be perfunctory.

The licensee's Technical Specifications, Section 6.5.3.1, states, in part, " audits

shall be performed in accordance with the TMI-1 Operational Quality Assurance

Plan." The Operational Quality Assurance Plan requires that the audit system

provide for corrective action systems and management reviews for timely correction

of identified deficiencies and prevention of recurrent nonconformances. The

licensee did not provide effective prevention of recurring deficiencies nor review

corrective actions for deficiencies to determine their adequacy. This is a violation

(VIO 50-289/97-04-04).

P8

Miscellaneous EP lssues

P8.1

(Closed) Weakness Observed Durina the April 12.1995 Full-carticioation Exercise:

Weak Ability to Rapidiv Assess and Reliably Predict Potential Offsite Radioloaical

Censeauences

The inspection team reviewed this item during this exercise. The licensee

adequately demonstrated its ability to perform effective dose assessment

calculations and make protective action recommendations. This exercise weakness

is closed.

P8.2 (Closed) Unresolved item (URI 50-289/95-05-01): PAR Loaic Methodoloav Not

Conformina With Federal Guidance

The NRC inspection team for Inspection 95-05 concluded that the licensee's PAR

logic diagram methodology did not appear to conform with Federal guidance, in that

it relied on evacuation time estimates and release duration, without consideration of

radiation doses that could be received.

The team reviewed this issue during this inspection. The licensee had revised its

PAR logic diagram in a recent change to the EPIPs. The inspectors reviewed the

revised PAR logic diagram and determined that it satisfactorily follows NRC

---

.

.

15

guidance. While the NRC's guidance follows a sector approach, evacuating the EPZ

out to a two mile radius and five miles downwind (the " keyhole" concept), the

licensee's default PAR guidance relies on an evacuation out to a five mile radius.

The licensee chose this approach because topographical characteristics of the plant

caused frequent wind shifts, and to more closely coincide with the PAR

methodology used by offsite officials which prescribes protective actions uniformly

for all sectors. The inspectors concluded that this deviation from NRC guidance

was acceptable.

-The inspectors noted one other way in which the licensee's new PAR logic deviates

from NRC guidance. The licensee's PAR logic diagram recommends the default PAR

for all GE classifications, regardless of core damage severity, except when security

events or known release duration justify otherwise. The NRC guidance recommends

the keyhole evacuation only for severe core accidents. However, a review of the

licensee's EALs revealed that, except for the security events already considered, all

the GE conditions considered in the current scheme would be severe core accidents.

Therefore, the licensee's new PAR logic diagram conforms to NRC guidance, and

the previously: identified unresolved item is closed.

4

.P8.3 LQoen) eel 50-289/97-02-01: Failure to recoanize and classifv a GE

]

During the previous exercise, the ERO failed to recognize a condition .in which all

three fission product barriers were breached as one that required a GE declaration.

During this remedial exercise, the ERO accurately recognized the conditions that

constituted each level of emergency classification and declared the appropriate.

t

a

~ emergency classification in each case. The satisfactory performance of the GE w

classification adequately addressed this item from a performance standpoint.

l

The inspectors also reviewed the licensee's short-term programmatic corrective

actions taken to respond to the weakness, which included EAL training for ERO

j

staff for classification of emergency events and coaching drille held at the various

ERFs to discuss expectations for the principal decision-makers, as well as their

soliciting input from supporting staff members. The inspectors verified that these

short-term corrective actions had been completed.

The inspectors interviewed five ERO members who'had attended the EAL remedial

training. The inspectors noted varying degrees of retention of the information

covered in the training, but concluded that the training was generally effective.

Additionally, the licensee's performaace during the remedial exercise demonstrated

the adequacy of the remedial training, and the licensee incorporated the concepts

covered in the remedial EAL training into the EP continuing training program.

The inspectors concluded that the corrective actions taken for the above weakness

were effective and that the GE classification was adequately demonstrated during

this exercise. However, it is still under consideration for enforcement action.

_

- __

,

_

,

.

_.

,

'

.

16

P8.4 LQksed) IFl 50-289/97-02-02: Inadcauate technical analysis by TSC staff

The technical analysis of simulated accident conditions provided to the ECC by the

TSC staff during the March 5,1997 drill was inadequate, and was assessed as an

exercise weakness.

To address this weakness, the licensee made significant staffing, roles, and

expectation changes in the TSC. The staffing changes included the addition of two

individuals to directly support the TSC coordinator. For each duty section, one of

'

these individuals, the TSC Advisor, was a former STA in the control room. In

addition, the licensee provided additional training to the TSC staff regarding RCS

and primary-to-secondary leakrate calculations, the role of the TSC, expected

resource allocation, control of activities in the TSC, and communications.

Based on the changes made to TSC staffing, the training provided, the leakrate

calculation enhancements and the excellent TSC performance in this exercise, the

previous weakness related to the adequacy of technical analysis of simulated

accident conditions provided to the ECC by the TSC staff is closed.

P8.5 (Closed) IFl 50-289/97-02-03: Incorrect analysis of steam aenerator tube leakaae-

During the March 5,1997 exercise, the analysis of primary-to-secondary leakage by

the ERO was incorrect and assessed as an exercise weakness.

i

As a result, the licensee provided guidance and developed new methods to analyze

primary-to-secondary leakage. One of the new methods estimates the leakage

based upon condenser off-gas monitor readings'and RCS activity. The results are -

only as accurate as the estimate of the RCS activity and only when the entire

release is going through the condenser. Based on the estimate of RCS activity and

condenser off-gas readings, off-gas flowrate and a factor from a series of graphs is

used to estimate primary-to-secondary leakage. The licensee provided training on

ihe guidance and new methods for determining leakrates to members of the TSC

and other emergency response staff. The inspector attended the training on May 7,

1997 and found it to be very good and informative.

i

Based on the new leakrate determination methods and guidance, the training

provided to the ERO on these tools, and the performance of the TSC staff dunng

this exercise to use the tools in accurately calculating primary-to-secondary leakage,

this weakness is closed.

P8.6 (Open) eel 50-289/97-02-04: Failure to assess need for PAR bevond 10-mile EPZ

During the March 5,1997 exercise, the EOF staff did not assess and discuss with

offsite officials the need for PARS for residents outside the 10-mile EPZ when dose

projections appeared to indicate that the Environmental Protection Agency

j

protective action guidelines (PAGs) would be exceeded.

-

_ ._

_ _ _ _

_

_ _ . . _ _ _ _ . . _ ._ _ .. .. _ .__ . _ _ _ .. _ _ _ _ _ _ _

.m

_

.

.

4

!

17

,

i

The inspectors reviewed EPIP-TMl .27, " Emergency Operations Facility." This

procedure requires the GLR &EC to periodically brief Commonwealth representatives

on the current radiological and environmental conditions. The procedure was

revised to require the GLR &EC to immediately notify the ESD if dose assessment

calculations indicated that EPA PAGs would be exceeded anywhere offsite,

inclu ! g outside the 10-mile EPZ. The procedure included a note that clarified that

dose projections for areas from a 10 to 30 mile radius can be performed using a

computer code on the Emergency Information Network. The procedure provided

guidance on protective actions to be taken outside the 10-mile EPZ. The GLR &EC

must notify the.PA Bureau of Radiation Protection of any problems with the dose

,

assessment calculations.

l

in addition to the guidance contained in the procedure, an e-mail memorandum was

issued on March 12,1997, from Mr.'J. Grisewood to members of the ERO

concerning the importance of thorough communications with Commonwealth

representatives regarding plant conditions during an emergency. Coaching sessions

- were conducted with ERO members on March 27 and April 3,1997 to emphasize

this new guidance.

During this exercise,.the inspectors observed that ERO personnel communicated.

well with Commonwealth personnel on plant and radiological conditions. In

particular, there was good discussion on PAR formulation both within the 10-mile

EPZ and beyond (though a PAR was not necessary beyond the 10-mile EPZ for the

existing radiological conditions). Based on the licensee's improved guidance and

performance during this exercise, this item was adequately demonstrated.

However, it is still under consideration for enforcement action.-

'P8.7

Updated Final Safety Analysis Report (UFSAR) Review

A recent discovery of a licensee operating its facility in a manner contrary to the

UFSAR description highlighted the need for a special focused review that compares

j

plant practices, procedures, and/or parameters to the UFSAR or the emergency

)

plan'. During this exercise, the inspectors observed the licensee's compliance with

H

the emergency plan regarding ERO structure, facility activation and usage, and

classification of simulated events. No discrepancies were noted,

j

P8.8 in-Office Review of Licensee Procedure Chanoes

i

An in-office review of revisions to the emergency plan and its implementing

procedures submitted by the licensee was completed. A list of the specific

revisions reviewed are included in Attachment 1 to this report. Based on the

licensee's determination that the changes do wt decrease the overall effectiveness

i

of the_ emergency plan, and that it continues to mdet the standards of 10 CFR 50.47(b) and the requirements of Appendix E to Part 50, NRC approval is not

required for those changes. Implementation of those changes will be subject to

j

inspection in the future.

._

-

_

\\

.

l

i

,

!

-

i

.

i

18

i

!

V. Manaaement Meetinas

f

~i

'The NRC convened a meeting with GPU Nuclear management personnel in the Region 1

j

office on April 30,1997, to discuss the licensee's root cause evaluation of the March 5

4

exercise weaknesses. Mr. E. Frederick summarized the root cause evaluation findings and

- Mr. A. Rone summarized the licensee's short term and long term corrective actions, as well

as the senior management evaluation of the root cause evaluation findings (Enclosure 2).

Of particular note were the conclusions that management oversight and involvement in EP

- was not sufficient, and that management expectations for support of the EP program must

be clearly defined, communicated, and continuously reinforced.

X.1

Exit Meeting

The inspector presented the inspection results to members of licensee management at the

conclusion of the inspection on May 15,1997. The licensee was informed of the

following:

There were no exercise weaknesses identified and performance was much improved

  • -

over the March exercise performance.

The weakness identified during the April,1995 exercise concerning weak ability to

assess.and predict offsite radiological consequences was adequately demonstrated

and is closed.

The unresolved item identified during the April,1995 exercise concerning the PAR

logic methodology not conforming to Federal guidance, was reviewed and the

licensee's changes were satisfactory. Therefore, this item is closed.

"

The four weaknesses identified during the March,1997 exercise were adequately

demonstrated. However,-two were closed (inadequate technical analysis by TSC

staff and incorrect analysis of steam generator tube leekage) and two will remain

i

'

open pending possible enforcement action (failure to recognize and classify a GE,

and failure to assess the need for a PAR beyond the 10-mile EPZ).

The exercise critique was much improved over the March exercise critique,

. identified most NRC items, and was assessed as good.

The inspection team identified an EP audit inadequacy in that an ERO qualification

issue was identified in multiple audits, and not corrected. This item was

unresolved.

The licensee acknowledged the inspection findings.

..

- -.

<

1

~

1

19

A formal exit mereting was conducted on May 28,1997, at the Three Mile Island Training

Center, which was open for public observation. The NRC inspection team leader presented

the inspection findings to Mr. J. Langenbach and other members of the GPU Nuclear staff.

The licensee was informed that:

The four weaknesses identified during the March,1997 exercise were adequately

demonstrated from a performance standpoint. However, two of those weaknesses

'

were being considered for enforcement action (failure to recognize and classify a

4

GE, and failure to assess the need for a PAR beyond the 10-mile EPZ).

The issue concerning the EP audit inadequacy which was previously unresolved,

1

was, after further review, assessed as a violation.

i

l

The issue concerning the lapse in ERO qualifications was ongoing since 1994, and

is a violation.

The issue concerning inadequate documentation of dose assessment computer

codes and user manuals for those codes were impcrtant problems, and is

unresolved.

The licensee acknowledged these findings.

Mr. J. Grisewood, the Three Mile Island EP Manager, presented a summary of the

licensee's actions to close out Confirmatory Action Letter 1-97-011, dated March 12,

1997 (Enclosure 3). The licensee stated that it had also provided this information to the

NRC in writing.

The licensee was subsequently notified by telephone on June 18,1997, that the issue

concerning inadequate documentation of dose assessment computer codes is a violation.

. - _ .

.

.

20

PARTIAL LIST OF PERSONS CONTACTED

Licensee

N. Brown, Lead Emergency Planner

D. Ethridge, Acting Director, Radiological Controls / Occupational Safety

R. Finicle, Corporate Emergency Planner

E. Frederick, NSA/ Human Performance

R. Goodrich, Site Security Manager

J. Grisewood, Emergency Preparedness Manager

'

R. Hess, Manager, Training

l

L. Karinch, GPU Nuclear Spokesperson

i

A. Knoche, Senior Emergency Planner

J. Langenbach, Vice President and Director, TMI

i

A. Miller, Regulatory Affairs

'

J. Moore, Nuclear Safety Compliance Committee

W. Ressler, Manager, Environmental Affairs

M. Ross, Director, Operations and Maintv.ance

G. Skillman. Director, Configuration Control

M. Slobodien, Director, Radiological Health and Safety

C. Smythe, Manager, Nuclear Safety Assessment

J. Wetmore, Manager, Regulatory Affairs

J. Whitehead, Senior Emergency Planner

W. Wilkerson, Manager, System Engineering

Commonwealth of Pennsvivania

R. Janati, Bureau of Radiation Protection

S. Maingi, Nuclear Engineer, Bureau of Radiation Protection

l

J. Rives, Pennsylvania Emergency Management Agency

Federal Emeraency Manaaement Aaencv

A. Henryson, Region lli

NRC

D. Barss, EP Specialist, NRR

P. Eselgroth, Chief, Division of Reactor Projects Branch 7

S. Hansell, Resident inspector, TMI

M. Modes, Chief, Emergency Preparedness and Safeguards Branch

J. Wiggins, Director, Division of Reactor Safety

.-

.

l

~

'

l

l

.

L

<

l

i

21

'

INSPECTION PROCEDURES USED

82301:

Evaluation of Exercises for Power Reactors

82302:

Review of Exercise Objectives and Scenarios for Power Reactors

1

92904:

Followup - Plant Support

j

i

ITEMS OPENED, CLOSED, AND DISCUSSED

i

Ooened

!

l

50-289/97-04-01

VIO

Lack of computer code documentation and procedures for dose

assessment

50-289/97-04-02

IFl

Additional guidance necessary for steam generator leakrate

calculation tool

.

.

50-289/97-04-03

VIO

Personnel on ERO duty roster who were not qualified

1

50-289/97-04-04

VIO

EP audit program inadequate to correct deficiencies

Closed

l

50-289/95-05-01

URI

PAR logic methodology not conforming with federal guidance

l

No number

Weakness

inadequate off-site dose assessment and projection

50-289/97-02-02

IFl

inadequate technical analysis by TSC staff -

50-289/97-02-03

IFl

incorrect analysis of steam generator tube leakage

piscussed

1 -

50-289/97-02-01

eel

failure to recognize and classify a GE

50-289/97-02-04

eel

failure to assess need for PAR beyond 10-mile EPZ

j

.

I

i

i

l

_

_

.

!

-

22

l

LIST OF ACRONYMS USED

CFR

Code of Federal Regulations

EAL

Emergency Action Level

ECC

Emergency Control Center

ED

Emergency Director

EDCM

Emergency Dose Calculation Manual

,

eel

Escalated Enforcement item

I

EMC

Emergency Maintenance Coordinator

EOF

Emergency Operations Facility

EP

Emergency Preparedness

EPIP

Emergency Plan Implementing Procedure

,

'

EPZ

Emergency Planning Zone

ERF

Emergency Response Facility

ERO

Emergency Response Organization

ESD

Emergency Support Director

FMT

Field Monitoring Team

GE

General Emergency

)

,

GLR &EC

Group Leader Radiological and Environmental Controls

-

GPM

Gallons Per Minute

,

IFl

inspector Follow-up item

Kl

Potassium lodide

LPI

Low Pressure injection

j

NRC

Nuclear Regulatory Commission

i

NUMARC

Nuclear Management and Resources Council

OC

Operations Coordinator

OSC

Operations Support Center

PAG

Protective Action Guideline

PAR

Protective Action Recommendation

PDR

Public Document Room

PPM

Plant Performance Monitor

QA

Quality Assurance

QDR

Quality Deficiency Report

RAC

Radiological Assessment Coordinator

RCC

Radiological Controls Coordinator

RCS

Reactor Coolant System

RESE

Radiological Engineering Support Engineer

R-S

Reuter-Stokes

SAE

Site Area Emergency

SRO

Senior Reactor Operator

SS

Shift Supervisor

TMl

Three Mile Island

TSC

Technical Support Center

TSCC

TSC Coordinator

UFSAR

Updated Final Safety Analysis Report

URI

Unresolved item

VIO

Violation

_.

__

._

_ . . . . _ _

_

_

_-

.-

-

_ _ . . . _

. . . .

.. _ - - -

=

i

1

?

'

'

'

i

,

23

,

i

ATTACHMENT 1

,

i

Emergency Response Procedures Reviewed

a

'

Document

Document Title

Revision (s)

5

EPIP-TMI .02

Emergency Direction

10.

EPIP-TMI .03

Ernergency Notifications and Call Outs

21

EPlP-TMI .06

Aoditional Assistance and Notification

23,24

EPIP-TMI .27

Er.)ergency Operations Facility

3,10

EPIP-COM .44

Thyroid Blocking

2

'

i

EPlo-COM .45

Classified Emergency Termination / Recovery

1

'

d.

1

I

I

4

l

1

,

I

1

.

,

i

.

.

4

'

.

,

l

l

!

.

_

_._.__._ __._____

,

.

.

.

ENCLOSURE 2

TMI-1

EMERGENCY PREPAREDNESS

ROOT CAUSE UPDATE

.

AND

PROGRESS REPORT

GPU NUCLEAR

APRIL 30,1997

-

. . -. -.

.

- . -

-

_ - . -

- -

- - - -

- . - . - -

-

.

.

.

!

Agenda

'

,

Background

A. H. Rone

-

Short Term Corrective Actions

A. H. Rone

-

HPIP Root Cause Evaluation

E. R. Frederick

-

Senior Management Evaluation

A. H. Rone

-

and Long Term Corrective Actions

Conclusions

A. H. Rone

-

l

1

.

.

.

.

.

. .

.

.

.

.

.

.

.

.

.

.

.

. .

.

.

.

.

.

!

i

1

Background

Biennial, full participation, graded emergency

I

-

)

preparedness exercise conducted March 5,1997

e

Scenario Summary

-

- Exercise started with plant running followed by major

j

leak in reactor coolant system resulting in declaration of

S AE. This was accomplished successfully.

- Plant shut-down was followed by damage to fuel clad.

)

i

Damage class was correctly recognized

- Calculation in TSC indicated primary to secondary leak

> 50 gpm. This met EAL for declaration of GE.

i

i

- Calculation done in TSC was incorrect. Drill controller

l

!

~

halted GE declaration to maintain exercise time line

commitments for offsite participants

j

2

i

r

- - .

-

-

- - -

- - -

- -

-

-

- -

-

- -

.-- . -

-

-

_ . _ _ _ _ _

. _ _ _

.l

-

-

.

l

l

- Decay. Heat line rupture bypassed the containment

building, thus breaching the third fission product barrier.

'

This should have resulted in declaration of GE. ERO

did not recognize GE condition, resulting in Drill

Controller prompting to maintain exercise time line

l

commitments to offsite agencies.

- Manual offsite dose calculation resulted in estimate of

.

60 rem dose at EPZ boundary. Discussions of need for

expanding PAR beyond 10 mile EPZ was limited at

!

EOF

Exercise Results

!

-

!

- ERO failed to recognize and declare GE when

conditions warranted

i

i

- ERO staffincorrectly evaluated steam generator tube

-

leakage

i

'

t

3

i

!'

-

.

-

.

.

-

_ .

-

-

.

.

- Technical analysis of simulated-accident conditions was

inadequate in TSC

- The EOF staff did not adequately assess need for PAR

beyond the 10 mile EPZ

CAL of March 12 confirmed GPUN commitments to

j

-

remediate drill weaknesses and perform a root cause

j

i

evaluation (RCE)

- Initiate imme~diate corrective actions to address

weaknesses noted above

- Perform a root cause analysis by April 15 covering

I

weaknesses along with ERO training, scenario

development, simulator problems, controller activities,

j

exercise critique process, and changes in EP and ERO

(

t

staffing

l

- Conduct a remedial exercise by May 15,1997

l

- ._..- - - _ -.- -.- -.

- - . _ . - . -

- . _ . . - . . - - - . - . - - -

. -

_

,

.

.

.:

.

,

The purpose of this meeting is to advise you of the

-

following:

'

- Immediate corrective actions and their results

- Results of the Root Cause Analysis

l

,

- Future plans

t

[

t

I

!

Y

I,

i

i

,

>

5

l

_ - _ - - _ _

-

.

..

!

!

!

Short Term Corrective Actions

1

!

Root Cause Evaluation (completed April 15,1997)

-

TSC capability upgraded

-

- Additional computers added

l

- Tech Support Coordinators / Assistant position added

- Expectations document issued on support to ECC and

i

f

coordination with EOF

- TSC Engineer assigned as " big picture" advisor

(previous STA or SRO or equivalent qualification)

!

!

,

'

t

L

-

.

-

_

.

.

,

.

.

.

.

i

l

'

,

ERO Training

I

-

- Diagnosis of conditions and timely declaration

.

of emergency conditions [ED, ESD, ED

i

Assistant, ESD Assistant, RAC, Group Leader

R&EC]

- Use and limitations of analytical tools (on-

going)

- Diagnosis and analysis of primary to secondary

leakage in steam generators

- Intra-facility communications

- Methodology and need for analyzing population

doses beyond 10 mile EPZ and making oflong

,

range protective action recommendations

f

.

7

- - -

- - - -

-

- - - - -

-

-

.

.

- -

_

.

-

.

. _ _ _ _ _ _ _ _ _ _ _ - - _ _

-

.

.

.

i

.

Short Term Corrective Actions

'

!

Table top training for EOF, ECC, and TSC

Communicate expectations for ESD and facility

leaders

Procedure upgraded for better quantifcation of

1

primary to secondary leakage in steam generators

and RCS leak rates

,

t

Multi-disciplined team used to prepare and

validate remedial exercise scenario

!

!

8

. - - - - - _ _ _ _ _ - _ _ _ _ _ _ - - _ _ _ - - _

e

o

Short Term Corrective Actions

Enhance exercise critique process by providmg

observers with objective evaluation criteria to

,

'

use in assessing performance

Meeting with Commonwealth of Pennsylvania

and GPUN to review and clarify GPUN/ state

interface expectations, press releases at GE,

PARS beyond 10-miles completed on April 25,

j

1997

l

i

Mini drill scheduled for May 8,1997

l

.

Management Review of Root Cause Evaluation

conducted April 25,1997

Remedial Exercise scheduled for May 13,1997

l

9

i

!

I

. . -

- . - - . . . _ _ _ _

_ - _ _ _ _ - _ _ _ _ _ - _ . _ . _ - _ -

.-

>

.

.

.

.

'

l

f

I

.

-

>

i

HPIP

!

Root Cause Evaluation

I

of

t

h

March 5,1997 Emergency Plan Exercise

.

!

E.-R. Frederick

HPES Coordinator, T WI

<

i

!

I

10

!

.

-

-

-

-

- -

-

-

_

.

- -

_ _ _ _ _ _ _ _ _ _ _ _ _

-

_ _

.

.

.

.

.

HPIP Root Cause Evaluation

Team

E. R. Frederick, Root Cause Analyst (NSA) and Team Leader

-

T. Blount, Manager Emergency Preparedness, Oyster Creek NGS

a

R. Finicle, Corporate Emergency Planner

-

.

D. Wilt, Instructor IV, Operator Training Department

-

C. Husted, Simulator Analyst, TMI Training Department

l

-

R. Rolph, Radiological Engineer, Radiological Health and Safety

l

-

E. Showalter, Engineer Sr., System Engineering Department

l

-

Dann Smith, HPE Coordinator (NSA), Oyster Creek NGS

-

Don Smith, Senior Reactor Operator, PDMS Manager

-

!

.

i

l1

!

i

i

-

- .

- -

-

-

.

-

-

- - -

-

.

-

- - - - -

-

-

- - - -

-

-

- - - -

. _ . _ _ _ _ . _ _ . _ . _ _ _ _ _ _ _ _ _ _ . _ _ . . _ _ _ . . _ . _ _ . .

-

-

.

.

.

Weakness No.1: ERO Failed to Recognize a General

l

.

Emergency when Warranted by Plant Conditions

!

i

HPIP Root Cause

-

- Training content did not specifically address

job performance standards

<

Corrective Actions

- Train on methods for determining fission

product barrier status

- Develop expectations and priorities for ED and

ESD to evaluate Emergency Action Levels

l

12

.

.

.

.

- . .

-

.

.

- - . - . . - - ..

. .

- . _ - _ _ _

.y

-

.

.

i

!

!

- Provide more detail in ECC EPIP

j

procedure change deferred - NUMARC EALs will

,

resolve

3

l

- Develop expectations for ERF Leaders to solicit

input from ERO members

- Meet with Pennsylvania BRP

,

!

I

,

t

13

__

..

. - - - - . - .

.

.

l

!

i

Weakness No. 2: ERO incorrectly evaluated OTSG Tube

Leakage

,

HPIP Root Cause

,

- Training content did not specifically address

.

job performance standards

.

  • Corrective Actions

>

- hands-on training on TSC PC-based leak rate

program addressing limitations with voided

RCS and RCPs running

- Provide information on limitations to selected

i

!

ECC and EOF personnel

14

l

-

--

-

- - - - . -

- - -

- - - - .. - . - ._ - - - - _

-

.

.

..

.

!

,

Weakness No. 3: Technical Analysis Provided to ERO by

TSC was Inadequate

!

HPIP Root Cause

- Training content did not specifically address

job performance standards

j

Corrective Actions

- Ensure ERF drills and additional training

l

include the following:

j

role of TSC in emergency plan

expected resource allocations and control of

.

activities in the TSC

,

communication techniques

TSC activation and table top exercises

15

-

-

-

.

- --- -

-

- - - -

-

-

-

- - - - -

- - - - - -

-

,

.i

1

-

-

.

i

l

!

Weakness No. 4: EOF did not assess the need for PARS

outside the 10 mile EPZ

HPIP Root Cause

-

- Policy guidance / management expectations not well

defined or understood

Corrective Actions

-

- Ensure procedures direct cross-check ofin-plant survey

i

data, offsite data, COLA input, and RAC Code inputs

- Incorporate into RAC and Group Leader R&EC

expectations and procedures for the need for PARS

i

outside 10 mile EPZ

- Establish requirements for and tools to evaluate

I

performance of dose assessment before using data for

l

PARS

!

l

.

16

!

t

. .

.

-

-

-

-

- - -

-

-

- -

- -

-

- -

-

-

. - - -

-

-- -

-

- _ - _ - _ - - _ _

. _ - _

-

-

.

.

Scenario Development:

Insufficient input from Rad Con,

Engineering, and Operations to Prevent Deviation from

.

Time Line

!

!

HPIP Root Cause

-

- Insufficient manpower to support identified goal /

objective

Corrective Actions

i

-

t

- Use multi-disciplined team to develop / validate

scenario. Validate using sufficient resources to

i

effectively represent ERO. Protect confidentiality

l

- Develop method to understand how changes may

,

disrupt key factors. Ensure all changes undergo

j

adequate review and re-evaluation

.

17

l

!

.

u

.-

. -

--

- .

.

- -

- - .

.

-

-

.

-

.

-

-

. - -

-

- - -

.

.

- -

-

- - -

-

- - .

-

.

-

-

- -

--.----- - - _ _

-

-

.

.(

h

!

i

Simulator Problems and Usage Issues: Insufficient

,

attention given to warnings on avoidable problems.

,

'

Driving Simulator beyond its capabilities. Use of

uncontrolled software.

!

HPIP Root Cause

-

- Component not operated within its design parameters

l

Corrective Actions

-

- place auto offsite dose projection system within

j

configuration control

,

- move COLA assessment computer system to secure

i

area

- do not use real time meteorological data for drills and

j

.

exercises

,

- control simulation to minimize negative training

!

18

!

. -

.

-

.

.-

-.-

-

-

--

--

l

..

- - . - . _ - - - . - - . _ _ _ _ - _

.

.

.,

..

p

,

,

DrillController Activities: Controller activities can be

.

overwhelming when drill takes direction not predicted.

j

-Meeting the time line is very important.

j

l

-

HPIP Root Cause

i

'

-

- Too many concurrent tasks assigned to worker

f

Corrective Actions

- reduce intervention required to meet scenario

objectives

- provide properly validated scenario that minimizes

f

controller activities and has backup information so

t

controllers can respond during system malfunctions

,

l

!

19

t

-

- -

-

-

-

!

. - -.- - - - .. - - - . - . -. .- - - - - . - - - . - _ . -

.

-

-

.

.,

k

!

Critique Process was Unsatisfactory: Critique failed to

identify CAL items 3 and 4

HPIP Root Cause

-

- Problem identification methods didn't identify

l

f

need for change

l

Corrective Actions

i

- develop and implement a formal drill critique

!

process

i

i

!

[

!

t

20

!

._ _.

--

- --

-

- - - - - -

- - -

- - -

- - - - - - - - - - - -

- -

- - - - - - - - -

- - - - - - - - - -

- - _ - - _ _ - - _ - - - - _ _ - - - - _ _ - - - - - -;

. _ . - - . - - .

.. -

. - - _ - - - - _ . .. - . _ _ . - . - - . - - . . - -

.

- -

- . - -

-

-

.

.

Changes in Emergency Preparedness Staffing: Corporate

EP Manager position eliminated, EP Manager recently

replaced, Planning staff reduced

!

HPIP Conclusions

1

- no measurable effect on outcome

l

Corrective Actions

>

>

- none

l

'

,

-

i

k

.

,

21

!

,

-

-

.

.,

!

!

Changes in ERO Staffing: Role reversal of ED and Ops

)

Coordinator, GL R&EC, EAC, RESE, TSR, OSCC filled

-

by personnel not in previous exercises

.

.

HPIP Conclusions

l

- ED /OC role reversal may have had slightly

negative effect

)

- other positions: no noticeable effect

  • Corrective Action

'

<

- Do not deviate from established ~ duty roster

assignments for graded exercises

I

22

'

i

_ - - - - _ _ - . - - _ _ - - - . . - - - - . -

-

-

.

.

l

i

Effectiveness of Past Corrective Actions: Repeat items

1

not captured in trend. Critique process did not identify

j

some weaknesses

.

>

.

l

HPIP Root Cause

t

- Corrective action for previously identified

problem or previous event was not adequate to

prevent recurrence

  • Corrective Actions

- Utilize improved Critique Process m

conjunction with CAP system. This will

employ root cause evaluation and corrective

'

action development and tracking

23

<

-

.

- - .

.

- - .

-

- -

.

- -

- - -

. - -

-

.

-.

. - -

- _

-

_ - _ _

.. .

'

.

,

,

r

Management Evaluation Team

c

A.H. Rone, VP: Nuclear Safety and Technical Support (Chair)

-

J. Langenbach, VP TMI

i

-

i

M. B. Roche, VP. Oyster Creek

j

-

Gregory Kane, Independent General Office Review Board

-

Member

l

J. Curry, Acting Director Nuclear Safety Assessment

!

-

E.R. Frederick, HPES Coordinator, TMI

!

<

M.J. Slobodien, Director Radiological Health and Safety

i

-

I

i

l

l

24

!

!

.


__-

_

_

.;

.

Management Review Team

)

Conclusions

r

i

A)

The performance demonstrated by some members of

i

the Emergency Response Organization was weak.

!

B)

The emergency preparedness process for developing,

validating, controlling, and critiquing the exercise

i

scenarios and ERO performance requires a more

systematic and rigorous approach.

\\

i

i

25

- - - ..- - -

-

-

.

.

!

C)

Management expectations for support of the

l

!

Emergency Preparedness program to achieve excellent

performance must be clearly defined, clearly

{

communicated, and continuously reinforced as

indicated by the following weaknesses:

]

- Inadequate resources were applied to scenario

l

development and validation. Management failed to

detect this.

- Changes in ERO staffing and the reduction in

experience level in the Emergency Preparedness

organization may have contributed to some performance

weaknesses. Management oversight and involvement

i

i

was not sufficient

- Management did not take adequate actions to ensure

'

~

completion of and continued attention to previously

identified corrective action needs

26

!

- .

!

,

.

.

.

_

!

!

!

Long Term Corrective Actions

l

Reinforce management expectations for Emergency

-

Preparedness program support e.g.

- Number of resources devoted to EP program

)

- Qualifications of personnel assigned to the ERO

- Direct management involvement in evaluations of the

EP program, and participation in EP drills and exercises

to verify ERO member proficiency

Perform Emergency Preparedness program benchmark

i

study against known high quality performers

-

nyaluate ERO training against benclunark plants

27

1

i

i

. - . . - . - -

. - . -

. . _ . - . . - - - - . - . - - -

-.-- .- --. - . .

.

.

.

.

1

-

\\

i

Routinely use ERO for multi-disciplined scenario

-

development, validation, observation, and performance

assessment

i

Bring offsite emergency dose calculation software into

!

-

conformance with GPUN software configuration control

procedures

Utilize external resources to supplement self assessments

l

-

and internal QA audit efforts

i

!

!

!

[

,

[

!

!

!

-

28

l

!

-

---m-

--

-

-

-

-

-

_ _ _

.

,,

1

.

>

t

Conclusions

The full participation biennial emergency

preparedness exercise ofmarch 5,1997 revealed

~

weaknesses.in the following areas:

- Scenario development, validation, and exercise control

and performance assessment

- Emergency Response Organization knowledge

f

particularly in technical support and other analytical

areas

- Adequacy of GPUN management attention to the

)

TMI emergency preparedness program

~

- Internal self assessments of the quality of the

j

emergency preparedness program

i

29

-

,

- . - . - . - - - . . - -

_ . . . _ _ .

_ _ _

.,

O

Adequacy of the emergency preparedness program

-

oversight by management including communication of

expectations

Prompt remedial actions have been taken to ensure

-

effectiveness of the Emergency Preparedness program

Long term management actions will ensure the on-going

-

effectiveness of the Emergency Preparedness program

The lessons learned from the recent efforts-are being

-

applied to the Oyster Creek Nuclear Generating Station

emergency preparedness program

30

_-_

__

_

'

ENCWSURE 3

o

.j

'^

_

<

6

Response to:

.

i

Confirmatory Action

Letter 1-97-011

i

May 28,1997

by Jeff Grisewood

Emergency Preparedness Manager, TMI

%

\\

j

" " " "

s.eieo re 4

- -

- -

---

.

- - - -

-

--

-

'.

..

,

,

Confirmatory Action Letter

.

Item #1

Initiated immediate corrective actions

to address the Biennial Exercise

weaknesses and conducted training

for the entire Emergency Res,oonse

Organization.

,

E

!

!

!

E-Plan TP 2

l

-

-

-

-

-

-

-

-

-

-

- -

-

-

-

-

-

.

- _ _ _ _ - - .

- - - -

- - - - _ - . - - -

.

a

g

item #1

.

l

V

Conducted Emergency Action Level training for

all key positions

V

Improved Primary to Secondary leakrate calculation

j

methods

i

V

Re-assessed technical staffing and made

appropriate reassignments

V

Modified procedures to ensure consideration of

f

the Protective Action Recommendation process

j

outside the 10-mile radius

!

!

I

v

Conducted Emergency Response Facility coaching

l

drills

(dou

l

" "

"

E-Plan TP 3

[

.

I

'

!

-

-

-

.

_ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . . - _ - _

.~ -

,

e

Confirmatory Action Letter

Item #2

Pedormed a root cause analysis.

i

V

Used Human Performance Investigation Process

j

.

v

identified root causes associated with specific

weaknesses and other Emergency Preparedness

related issues

i

i

!

V

Conducted a management review of the

root cause analysis

j

i

V

Presented results to the NRC at a public meeting

on April 30,1997

(2pu

~

E-Plan TP 4

i

- _ . - ____ _

_ _ _ _ - _ . _ _ _ _ _ _ -

.

.

.

.

1

Confirmatory Action Letter

-

Item #3

i

Conducted a remedial onsite exercise

t

on May 13,1997.

1

!

.

V

Used a multi-discipline team to develop, validate,

and evaluate the exercise

t

!

V

Concluded that the corrective actions were effective

!

l

0

"#

I

E-Plan TP 5

.

-

-

-

-

- - - -

- - -

- - - - - -

- - - - -

- - - - - - - - - - - -

- - -

-

- - -

- -

L

'

.

.

-

.

6

Confirmatory Action Letter

,

.

Item #4

i

!

!

!

Discussed proposed corrective

l

actions in a formal exit meeting with

the NRC Staff on March 17,1997.

!

,

I

<

[

I

!

!

!

,

,

!

nuctuan

E-Plan TP 6

!

!

!

.

.

.

. .

l

_ _ _ . _ _ _ _ - _ _ _ _ _ _ _

.

.

...

.

.

Confirmatory Action Letter

!

Item #5

Provided GPUN's view on the

i

significance of the exercise

weaknesses and why the corrective

actions would be effective.

!

!

N

E-Plan TP 7

1

m

a

.

-a

m-.=

-

as

wJmm

-.mh4m

..-a

4

-

4

4-,ah>- - - . ,-,-

mJ4

a

AA

-_ma

e

h-aaa

-AA--A---

2

AM

Ja.

+-ae--

= m 3 4e 4-

A-

,__as-

A>V

.

-

s

<

E

L$1

i

.

C

'

O

._

.

)

!

O

!

C

'

OO

.

3

d

$

.

4

.

~

w

v

-

T

-- c -