ML20147J034
| ML20147J034 | |
| Person / Time | |
|---|---|
| Site: | Satsop |
| Issue date: | 03/07/1988 |
| From: | Rubenstein L Office of Nuclear Reactor Regulation |
| To: | Mazure D WASHINGTON PUBLIC POWER SUPPLY SYSTEM |
| References | |
| NUDOCS 8803090158 | |
| Download: ML20147J034 (3) | |
Text
..
March 7, 1988 4
Docket No. 50-508 Mr. D. W. Mazure, Managing Director Washington Public Power Supply System 3000 George Washington Way P.O. Box 968 Richland, Washington 993-09f8
Dear Mr. Mazure:
SUBJECT:
WNP-3 GEOSCIENCES ISSUES This is in response to Mr. Sorensen's letter of February 10, 1988, in which he provided a proposed schedule for completion of the review of the Geosciences Issues for WNP-3. We iind the proposed schedule is acceptable and will make every effort, as resources. permit, to accomodate the review of the Geosciences Issues for WNP-3.
Sincerely, Driginal Signod By:
Lester S. Rubenstein, Director Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, V and Special Projects Office of Nuclear Reactor Regulation cc:
See next page DISTRIBUTION:
' Do:ket ; File 1 G. Visdng NRC & Local PDRs E. Hylton PDSNP Reading G. Bagchi L. Rubenstein PDSNP PDSNP //,
PD S '
LRubenstein:1s GViss,1(g
on GBagchi 02/zy/88 02gp/88 02
/88 g/[ /88 itQ 8803090158 880307 PDR ADOCK 05000500 A
pon
l *
- p na u"o,,
v UNITED STATES 1
8" NUCLEAR REGULATORY COMMISSION o
E WASHINGTON, D C. 20665
~s.,*...+/
March 7, 1988 Docket No. 50-508 Mr. D. W. Mazure, Managing Director Washington Public Power Supply System 3000 George Washington Way P.O. Box 968 Richland, Washington 993-0968
Dear Mr. Mazure:
SUBJECT:
WNP-3 GEOSCIENCES ISSUES This is in response to Mr. Sorensen's letter of February 10, 1988, in which he provided a proposed schedule for completion of the review of the Geosciences
~
Issues for WNP-3. We find the proposed schedule is acceptable and will make every effort, as resources permit, to accomodate the review of the Geosciences Issues for Wi!P-3.
Sincerely, uit Gb Lester
. Rubenstein, Director Standardization and Non-Power Reactor Project Directoraic Division of Reactor Projects III, IV, Y and Special Projects Office of Nuclear Reactor Regulation cc:
See next page
s*
1 Mr. D. W. Mazur WPPSS Nuclear Project No. 3 Washington Public Power Supply System (WNP-3) Docket No. 50-508 cc:
Mr. Charles B. Brinkman, Manager Mr. G. C. Sorensen, Manager Washington Nuclear Operations Regulatory Programs Combustion Engineering. Inc.
Washington Pubiic Power Supply 7010 Woodmont Avenue, Suite 1310 System Bethesda, Maryland 20814 Post Office Box 968 Richland, Washington 99352 Nicholas S. Reynolds, Esq.
DeBevoise & Liberman Regional Administrator, Region Y 1200 Seventeenth Street U.S. Nuclear Regulatory Comission Washington, DC 20036 1450 Maria Lane Suite 210 C. E. Doupe, Esq.
Walnut Creek, California 94596 Washington Public Power Supply System 3000 George Washington Way Richland, Washington 99352 Mr. Curtis Eschels, Chairman Energy Facility Site Evaluation Council Mail Stop PY-11 Olympia, Washington 98505 Mr. Douglas Coleman Washington Public Power Supply System P. O. box 1223 Elma, Washington 98541 Mr. William Ang Region Inspector /WPPSS 3/5 U.S. Nuclear Regulatory Comission 1450 Maria Lane - Suite 210 l
Walnut Creek, California 94596 Mr. Eugene Roso11e, Director Coalition for Safe Power 408 Southwest Second Avenue l.
Portland, Oregon 97204
.