ML20147G767

From kanterella
Jump to navigation Jump to search
Insp Repts 50-445/88-05 & 50-446/88-04 on 880105-0202. One Violation & Deviation Noted.Major Areas Inspected: Assessment of Allegations,Followup on Violations/Deviations, & Corrective Action Program for Small Bore Piping
ML20147G767
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 03/02/1988
From: Livermore H
NRC OFFICE OF SPECIAL PROJECTS
To:
Shared Package
ML20147G651 List:
References
50-445-88-05, 50-445-88-5, 50-446-88-04, 50-446-88-4, NUDOCS 8803080311
Download: ML20147G767 (22)


See also: IR 05000445/1988005

Text

.

.

APPENDIX C

U.

S. NUCLEAR REGULATORY COMMISSION

OFFICE OF SPECIAL PROJECTS

NRC Inspection Report:

50-445/88-05

Permits: CPPR-126

50-446/88-04

CPPR-127

Dockets: 50-445

Category: A2

50-446

Construction Permit

Expiration Dates:

Unit 1: August 1,

1988

Unit 2: Extension request

submitted.

Applicant:

TU Electric

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas

75201

Facility Name:

Comanche Peak Steam Electric Station (CPSES),

Units 1 & 2

Inspection At:

Comanche Peak Site, Glen Rose, Texas

Inspection Conducted:

January 5 through February 2, 1988

Inspection conducted by NRC Consultants:

J. Dale - EG&G (paragraph 6.c)

K. Graham - Parameter (paragraphs 2.e, 4, 5, and 6.a)

P. Stanish - Parameter (paragraphs 2.a-d, 3, and 6.b)

,

Reviewed by:

144(#7tM

$-2-- V

H. H.

Livermore, Lead Senior

Date

Inspector

8803000311 880302

PDR

ADOCK 05000445

o

PDR

- -

,

.-

_

._

___

..

TU Electric

2

!

Inspection Summary:

Inspection Conducted: January 5 through February 2, 1988 (Report

'

50-445/88-05; 50-446/88-04)

Areas Inspected: Unannounced, resident, safety inspection of

applicant actions on previous inspection findings; follow-up on

.

violations / deviations; assessment of allegations; Comanche Peak

Response Team (CPRT) issue-specific action plan (ISAP) V.a; and the

corrective action program (CAP) for small bore piping and pipe

supports, conduit supports for A and B trains and C train greater

than 2 inches, and HVAC.

Results:

Within the areas inspected, the NRC inspectors identified

no significant strengths or weaknesses during this inspection.

One

violation failure to identify a minimum wall violation, paragraph

6.c) and one deviation (failure to trend a nonconformance report

(NCR), paragraph 2.0) was identified.

t

.

%

TU Electric

3

DETAILS

1.

Persons Contacted

  • J.

C. Aldridge, Engineering Assurance (EA), Stone & Webster

Engineering Corporation (SWEC)

  • R. P. Baker, EA Regulatory Compliance Manager, TU Electric
  • J.

L. Barker, Manager, EA, TU Electric

  • D. P. Barry, Manager, ESG, SWEC
  • D. N. Bize, EA Regulatory Compliance Supervisor, TU Electric
  • M. R. Blevins, Manager, Technical Support, TU Electric
  • J. T. Conly, Lead Licensing Engineer, SWEC
  • J.

C. Finneran, CPE-PSE, TU Electric

  • K.

M. Fitzgerald, HVAC Program Manager, Ebasco

  • P.

E. Halstead, Manager, Quality Control (QC), TU Electric

  • T.

L. Heatherly, EA Regulatory Compliance Engineer,

TU Electric

  • C.

R. Hooten, CPE-Civil Engineering Unit Manager, TU Electric

  • J. J. Kelley, Manager, Plant Operations, TU Electric
  • 0. W. Lowe, Director of Engineering, TU Electric
  • F. W. Madden, Mechanical Engineering Manager, TU Electric
  • D.

M. McAfee, Manager, Quality Assurance (QA), TU Electric

  • D.

E. Noss, QA Issue Interface Coordinator, TU Electric

  • E.

Odar, Project Engineering Manager, Ebasco

  • M.

D. Palmer, Plant Evaluation, Nuclear Operations,

TU Electric

  • B.

L. Ramsey, Project Manager Civil / Structural, TU Electric

  • D.

M. Reynerson, Director of Construction, TU Electric

  • M.

J. Riggs, Plant Evaluation Manager, Operations, TU Electric

  • A.

B. Scott, Vice President, Nuclear Operations, TU Electric

  • C.

E. Scott, Manager, Startup, TU Electric

  • J.

C. Smith, Plant Operations Staff, TU Electric

  • M.

R. Steciman, CPRT, TU Electric

  • P. B. Stevens, Manager, Electrical Engineering, TU Electric
  • J. F.

Streeter, Director, QA, TU Electric

  • C

L. Terry, Unit 1 Project Manager, TU Electric

  • R.

D. Walker, Manager of Nuclear Licensing, TU Electric

The NRC consultants also talked to other applicant and

contractor employees during this inspection period.

  • Denotes personnel present at the February 2, 1988, exit

meeting.

.

.

TU Electric

4

2.

Applicant Action on Previous Inspection Findings (92701)

a.

(Closed) Open Item (445/8601-0-03):

This item involves

an apparent error on Drawings GHH-CC-1-SB-027,

Revision 6; GHH-CC-1-SB-040, Revision 12; and

2323-MI-0229, Revision CP-4.

The error concerned the

location of Valves ICC-137 and ICC-145.

The NRC

inspector, during an inspection of the Unit #1 Safeguards

building, noticed that the valves were reversed from the

locations on the piping isometrics.

Since the valves are

identical and will perform their intended function as

installed, the applicant committed to correct the

drawings.

In this inspection period, the NRC inspector

verified that Drawings MI-0229, Revision CP-5; and

BRP-CC-1-SB-027, Revision 6, now accurately depict

existing field conditions.

This item is now closed,

b.

(Open) Unresolved Item (446/8602-U-23):

This unresolved

item dealt with the fact that the stated program did not

appear to provide positive assurance that all required

grouting of conduit support base plates would be

accomplished.

In this inspection period, the NRC

inspector reviewed Brown and Root Procedure Number

CEI-25, Revision 7, which provides instructions for

grouting of base plates, equipment bases, and shear lugs.

This procedure in paragraph 1.2.1.1 states, in part,

determination of which base plates requito

" . . .

grouting shall be made by the .

. craft

.

" and in paragraph 3.1.2 states, in part,

support

. . . ,

".

epoxy grouting .

. will be documented on a

. .

.

bearing inspection report

Also, a note under

"

. . . .

this paragraph of the procedure appears to imply that an

operational traveler is acceptable in lieu of the QC

inspection report.

This procedure does not address

documentation for base plates which the craft determines

to have adequate bearing area and, therefore, do not

require grouting.

Also, reviewed was TUGCO Instruction

QI-QP-11.0-15, Revision 10, which states in

paragraph 2.2, ".

inspection identified in this

, .

instruction will be performed only on components that do

not require grout in accordance with References 1-A

and 1-B.

This is indicated by a "SAT" craft bearing

inspection report for that base plate / member .

."

. .

Reference 1-A is the general specification for concrete,

and Reference 1-B is Procedure C-25 which, as stated

above, does not specifically require a bearing inspection

report to be generated for a base plate that does not

-

-

-

TU Electric

5

require grouting.

Therefore, this item will remain open

until positive assurance is demonstrated that the

inspection of all baseplates will be documented and

satisfactorily dispositioned.

c.

(Closed) Unresolved Item (445-8622-U-05):

This item

dealt with the validity of using an NIS-2 form (a form to

document an ASME Section XI repair / replacement) to

document an as-installed component as stated in the

disposition of NCR M-23175 N, Revision 1.

The NCR in

question was written to document an apparent lack of

traceability for a specific valve bonnet.

This NCR was

subsequently dispositioned based on revised documentation

from the vendor (ITT) which does provide traceability for

the part in question.

As for the generic use of an NIS-2

form as a stand-alone document for this type of problem,

TU Electric has stated in office me,morandum NE-16479 that

the only way to document nonconforming as-installed

components or conditions is through an NCR.

While an

NIS-2 form may have been used in the past as backup

documentation for an NCR, this practice has been

discontinued.

Furthermore, TU Electric indicated that

the NIS-2 form was never used as a stand-alone use-as-is

document.

This item is closed.

d.

(Closed) Open Item (445/8706-0-11; 446/8705-0-05):

This

item addressed the CPRT recommended changes to

Gibbs & Hill Specification 2323-MS-100 and Brown and Root

Procedure CP-CPM-6.9E concerning temporary supports,

specifically limiting or prohibiting the use of certain

materials for temporary supports and "less desirable

temporary support practices."

The NRC jnspector reviewed

Brown and Root Procedure CP-CPM-6.9E, Revision 10, "Pipe

Fabrication and Installation," TU Electric Construction

-

Department Procedure CPS-101, Revision 0, and DCA 62786,

Revision 0.

Based on this review the NRC inspector is

satisfied that these items have been adequately addressed

by invoking the requirements of Specification MS-100 for

temporary supports, which through DCA 62786 specifically

prohibits the use of specific undesirable materials and

provides more definitive requirements for temporary

supports; therefore, this item is now closed,

e.

(Closed) Open Item (445/8716-0-11):

While the NRC

inspectors were interviewing craftsmen performing work on

Pipe Support DO-1-067-708-S53R and prior to the

inspector's review of the associated work package, a QC

+

.

.

>

h

!

TU Electric

~6'

!

inspector arrived ~and reviewed the work package.

Upon~

,

'

completion of.the QC review, work was stopped due to algc

hold point being bypassed on'a repair. process sheet by a

craftsmen.

NCR 87-A00491, Revision 1, was initiated. ~

This situation was documented as an open item pending

q

' review of the-applicant's NCR disposition and. processing.

The NRC inspector contacted the TU Electric QA issue'

interface coordinator to evaluate the applicant's NCR

dispositioning and processing.

The subject NCR had been

>

'

closed based upon rework of the weld repair. area. 1The

.

NRC inspector verified, by review of training records

,

dated August 14, 1987, that the responsible craft

i

personnel had been reinstructed to the appropriate

.

'

procedural requirements for weld documentation usage and

observance of hold points.

.

'

The NRC inspector requested that TU Electric identify the

trend codes assigned to the Revision 1 disposition of

NCR 87-A00491.

TU Electric FSAR Section 17.1.15 requires

,

trending of NCRs to identify trends adverse to quality.

NRC inspection revealed that_the NCR had'not been

assigned a trend code.

As a. result of the NRC finding,

the applicant performed a broadness review and issued

-

Deficiency Report (DR) P-88-00595 which documented that

between July 11, 1987, and October 5, 1987,.2,024 NCRs

were issued per Project Procedure AAP 16.1 and were not

a

l

trended.

The failure to assign a trend code prevents an

evaluation for adverse trends.

The failure to trend the

4

!

subject NCR 87-A00491 for bypassing a QC hold point is

'

4

considered a deviation from FSAR Section 17.1.15,

Amendment 65 dated November 20, 1987, which states that

procedures shall require trending of deficiencies

l

reported on inspection reports, deficiency reports, and-

nonconformance reports in order to identify trends

<

]

adverse to quality (445/8805-D-01).

3.

Follow-up on Violations / Deviations (92702)

3

(closed) Deviation (445/8622-D-06):

This deviation dealt with

1

)

the fact that valves supplied by Westinghouse under their

l

Purchase Order 546-CCA-191000-XN were certified to the Summer

'

'

1972 Addenda to the 1971 edition of Section III of the ASME

i

Code; however, the FSAR in Table 3.2-1, Section 3,

j

Amendment 56, requires that Class 2 and 3 valves meet the

l

requirements of the 1974 edition of Section III of the ASME

,

Code.

TU Electric in their response to this deviation stated

4

i

<

,

i

'

i

9

.

.

.

TU Electric

7

,

that the deviation was caused by an error in the FSAR.

The

FSAR commitment failed to recognize that the Westinghouse

Contract No. Q202 invoked an earlier code edition and addenda.

Based on the above, DR C-87 1980 was generated to initiate a

change to the FSAR.

Review of the FSAR by the NRC inspector

revealed that the committed change was included in FSAR

Amendment 64. -Therefore, this deviation is closed.

4.

Assessment of Allegations (99014)

(Closed) Allegation (OSP-87-A-0103):

An allegation was

received by the NRC that contained five concerns relating to

the CAP for HVAC.

These concerns have been assessed and

documented below.

Two of the concerns were substantiated

resulting in violations issued in a previous NRC inspection

report.

The other three concerns were not substantiated.

All

five concerns are considered to be closed.

Concern No. 1

QC personnel are not technically cognizant enough to identify

potentially nonconforming conditions which are outside the

scope of the inspection procedures.

Review

The NRC inspector interviewed the QC supervisor responsibic

for inspection of HVAC duct segments and seismic duct supports

in order to evaluate the responsibilities of QC personnel.

The QC supervisor stated that HVAC inspection personnel's

scope of responsibility is to identify problems with hardware

and documentation associated with the construction traveler

which has been presented to him for inspection.

Furthermore,

QC inspectors for HVAC, as a part of their training /cortifi-

cation program, have been instructed to identify and document

any nonconforming condition that they become aware of in

accordance with the requirements of project procedures.

Currently, a total of 76 certified QC inspectors are assigned

to inspection of HVAC CAP work activities.

NRC inspections of ISAP I.d.1, "QC Inspector Qualifications,"

have determined that the current QC inspector training /certi-

fication program meets the requirements of ANSI N45.2.6.

The NRC inspector selected the names of 10 of the 76 QC

inspectors who are certified to perform HVAC inspections, from

a list of all certified inspectors, and performed a review of

.

.

TU~ Electric

8

each individual's training / certification file.

Evidence of

training and certification for the following procedures and

specifications was evaluated:

NQA-3.09-10.01, Requirements for Visual Weld Inspection

NQA-3.09-M-6.01, QC Inspection of Safety-related HVAC

Systems

NQI-3.09-M-006, verification / Inspection of Seismic HVAC

Systems

NEO 3.05, Reporting and Control of Nonconformances

NEO 3.06, Reporting and Control of Deficiencies

2323-MS-85, Appendix J, Ductwork and Miscellaneous

Details

]

2323-MS-85, Appendix K, Quality control Inspection

j

Requirements

Based upon a satisfactory review of training / certification

'

!

records, the NRC inspector concluded that QC personnel should

i

be technically cognizant enough to identify and document

nonconforming conditions within their scope of responsibility.

Conclusion

1

QC inspectors have been trained to identify and document any

potentially nonconforming condition within their scope of

'

responsibility.

The NRC inspector was unable to identify any

i

requirement to document nonconforming conditions outside the

scope of the individuals responsibility.

However, project

nonconformance reporting procedures require any individual to

'

document concerns about safe operation of the plant or

procedural inadequacios that they become aware of, on a

nonconformance or deviation report.

Based upon the NRC

a

inspector's evaluation of procedural requirements,

,

training /cortification records, scope of responsibility for QC

personnel, and lack of specifics, this concern could not be

j

substantiated and is therefore closed.

1

i

i

l

1

.

.

TU Electric

9

Concern No. 2

Due to conflicting requirements, it is possible that the

documentation packages for safety-related HVAC supports ...ay

incorrectly be designated as non-nuclear safety, thus, not

receiving the required level of inspection.

Review

The NRC inspector reviewed Comanche Peak Engineering

Specification 2323-MS-85, Appendix D,

"Classification

Summary-Ductwork, Louvers, and Accessories," Revision 5 dated

September 15, 1987, and noted that three seismic category

designations, Category I, Category II, and None, were listed.

Project HVAC engineers assign safety class designations based

upon the data contained in Appendix D.

The NRC inspector contacted the senior project engineer

responsible for implementation of the HVAC CAP and was

informed that all non-nuclear safety Seismic Category II

supports are inspected to the more stringent requirements of

Seismic Category I safety-related supports.

The seismic

category "None" is applicable only for nonsafety HVAC systems.

A copy of Ebasco Interoffice Correspondence HV-0409 dated

October 16, 1987, documents Ebasco's decision to inspect

non-nuclear safety supports to the more stringent requirement.

This memorandum was determined to provide adequate instruction

to personnel preparing documentation packages for inspection.

In addition to the above review, NRC inspectors have reviewed

,

HVAC documentation packages while performing CAP inspections

and found that the required level of inspection was being

performed.

Reference NRC Inspection Reports 50-445/87-31,

50-446/87-23; and 50-445/87-35, 50-446/87-26.

The NRC inspector interviewed five working level engineering

personnel to determine their knowledge of establishing safety

class designation.

These personnel were cognizant of the

applicable requirements.

Conclusion

Based upon the review of the applicable engineering

specification and review of project correspondence, concern

Nc. 2 was not substantiated.

Furthermore, previous NRC

i

t

-

.

i-

j

TU Electric

10

inspections of the CAP concluded that the safety class

designation of documentation packages was correct for all

l

items inspected.

This concern is closed.

,

Concern No. 3

i

.

'

l

Procedure CHV-106, Revision 1, has been marked up and used in

the field; however, no formal revision has been made.

'

l

Review

The NRC inspector performed a review of TU Electric frocedure

CHV-106, "Qualitative Walkdown of HVAC Supports and ducts,"

i

Revision 1, dated October 12, 1987, and noted that

paragraph 2B.2 of of Figure 7.6 contained wording which could

have created confusion as to what the intent of the

verification step was.

This concern was evaluated as a part of the NRC inspection of

the HVAC CAP. Duct segment documentation package B-1-658-016,

for which final field inspection by QC had been performed, was

reviewed and found to contain a copy of Figure 7.6 on which

the unclear wording had been resolved by a revision of the

form.

Revision of Figure 7.6 had been made outside the scope

of the project procedures which is a violation of Criterion V

!

of Appendix B to 10 CFR Part 50.

NRC Inspection Report

50-445/87-35 documents this violation.

!

l

Conclusion

,

NRC inspection of the applicants HVAC CAP substantiated that

project engineering personnel were documenting the results of

engineering walkdowns on a form that had been revised without

,

a formal revision in accordance with the procedures that

control use of the form.

Notice of Violation 445/8735-V-02

documents the NRC inspection finding.

This part of the

,

allegation (Concern No. 3) is closed.

>

Concern No. 4

There are inconsistencies identified in construction operation

'

traveler instruction, e.g.:

'

a.

Status sheets state:

"Remove paint from all

[

safety-related welds."

b.

Scope sheets state:

"Remove paint from all welds."

,

[

i

)

!

.

- .

.

. - .

.

.

.

. .

.

. .

__ ..

_ _ .

.

'

,

!

'

TU Electric

11

c.

Construction Operation Travelers state:

"Remove coating

-

from existing safety-related welds."

i

!

i

Review

This concern was previously evaluated during NRC inspection of

!

the applicants HVAC CAP.

In Inspection Report 50-445/87-35,

,

50-446/87-26, the NRC inspector performed field inspections

,

'

and documentation reviews of four HVAC seismic duct support

L

construction operation travelers (Cots) which were field

j

complete by construction and for which final field QC

acceptance inspection had been performed.

The NRC. inspector

4

i

noted that the alleged inconsistencies existed in the COTS

l

reviewed, and it was unclear as to whether or not coatir:gs

'

should be removed from nonsafety welds.

NRC inspection of

seismic duct hanger packages DH-1-844-1K-WP13, Revision 1, and

.

,

j

DH-1-844-lK-1R, Revision 1, revealed that construction work

forces had removed galvanized coatings from both safety and

-

nonsafety welding to allow for a qualitative visual inspection

'

of welding by QC inspectors in accordance with HVAC CAP

4

'

commitments.

The NRC inspector identified that five welds

located on Seismic Duct Hanger DH-).-844-1K-WP13 and portions

.

of welds located on Seismic Duct Hanger DH-1-844-1K-1R did not

,

'

have the galvanized coating required by Comanche Peak

i

Engineering (CPE) Specification 2323-Ms-85.

Engineering

i

personnel confirmed that all planned HVAC CAP inspections of

.

these items were complete and that these bare spots had not

,

,

been identified.

The applicant was cited for this previously

'

>

(example 7 of 445/8735-V-02).

Conclusion

l

NRC inspection of the applicants HVAC CAP substantiated that

inconsistencies in instruction for removal of paint do exist.

!

These inconsistencies created confusion as to what

construction work requirements were and what QC personnel were

'

required to inspect during final acceptance inspection.

As a

result, galvanized coating was not reapplied to several welds.

This was documented as an example of a violation in NRC

i

Inspection Report 50-445/87-35.

This part of the allegation

(Concern No. 4) is closed.

{

'

1

{

Concern No. 5

'

The information/ question request form may be incorrectly used

in lieu of NCRs for documenting nonconforming conditions,

i

(

,

r

.

!

'

-

.-.

m

.

.

.

.

. .

-

m

.

.

.-

. .

.

m..

.

.

,.

TU Electric

12

f

' eview

1

!

NRC evaluation of Concern No. 5 revealed that the information

i

and question request form is an informkl document provided to

.

HVAC engineering personnel as a result of an interoffice

correspondence, HV-C0042, dated October 12, 1987.

This-

correspondence documents that the form is to be used to

,

document procedural questions asked and answers given.

The

respective lead and/or supervisor answers the question and

'

,

returns a copy of the form to the individual asking the

question.

A note on the bottom of the form states, "This form

,

is to be used only for requesting clarification of procedural

i

intent."

!

?

The NRC inspector interviewed Ebusco engineering personnel

I

responsible for the implementation of the HVAC CAP

'

requirements and discussed the use of the information and

question request-form.

These individuals were aware of the

i

requirement to document nonconforming conditions on an NCR

form.

The NRC inspector reviewed a log book documenting these

,

requests for clarification and performed a detailed review of

nine forms which had been completed.

The NRC review

.

determined that these forms were being used to ask questions

!

about the intent of procedures and were not being used to

document nonconferming conditions.

l

Conclusion

i

The NRC inspector was unable to substantiate Concern No. S

based upon a review of the usage of the forms by project

'i

personnel.

The NRC review determined that the information and

i

question request form was being used in accordance with the

i

intent of Interoffice Correspondence NV-C0042.

This item is

closed,

j

5.

CPRT ISAPs

!

Inspection for Certain Types of Skewed Welds in NF Supports

(ISAP No. V.a) (57050)

I

Third Party to Evaluate the Physical Significance of any

Procedural Changes (NRC Reference OS.a.02.04)

The third party determined that historical revisions to

!

inspection procedures for Type-2 skewed welds, QI-QAP 11.1-28

l

and QI-QAP 11.1-26, had no physical significance and did not

!

!

_ _ - ___-__ - _.

-

.

t

TU Electric

13

impact any previous QC inspection result, with the exception

of those documented by TU Electric Design Deficiency Report

(TDDR) PS-86-1973.

This TDDR describes an error in the scribe

line inspection technique which requires corrective action by

the project and will be overviewed by CPRT in accordance with

Appendix H of the CPRT program plan.

The NRC inspector agrees

with the CPRT conclusions reached during the CPRT review of

procedural changes.

This item is closed.

Determine the Need for Additional Inspection (NRC Reference

05.a.03.05)

The NRC inspector reviewed the results of all inspections and

reviews performed by the third parties that were contained in

the ISAP working file and identified the need to perform a

more extensive evaluation of the need for additional

inspections.

A formal request for additional information (NRC

letter dated September 16, 1987, Grimes to Counsil) was

submitted to the applicant.

The applicant responded

(TV Electric Letter TXX-6858 dated December 30, 1987) with an

additional evaluation of inspection results and design

requirements.

The NRC inspectors review of the additional

information concluded that additional inspection of the Type-2

skewed weld population is not required since design

requirements were met or exceeded for all population items

which were inspected.

This item is closed.

Identify Corrective Actions Required (NRC Reference

05.a.05.03)

The reinspections and documentation reviews performed under

this action plan provided reasonabic assurance that the Type-2

skewed welds located on pipe supports are within the ASME

allowable stress levels.

A third-party evaluation of design

margin based on the measured weld size indicates that the

Type-2 skewed welds in the plant will not exceed ASME limits.

The NRC inspector has reviewed the ISAP working file and

concurs with the third-party conclusion.

The project is

developing a corrective action plan to resolve TDDR-PS1973, an

error in the scribe line inspection technique, which will be

overviewed by the third party in accordance with Appendix H of

the CPRT program plan.

This item is closed.

'

i

i

>

-

.

. - -

-

.

.

.

.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . __

.

.

TU Electric

14

I

Third Party Will Oversee and Verify the Review Program (NRC

Reference 05.a.06.00)

The NRC inspector has reviewed documentation of third party

activities contained in the ISAP working file.

For those

activities performed by the project during tmplementation of

the ISAP (i.e., Historical Chronology of Inspection Procedures

!

I

for Skewed Welds, Sample Selection Criteria, Evaluation of

Inspection Results, etc.), independent third parties (TERA

Corporation and Jack Benjamin and Associates) verified

accuracy and completeness.

Project personnel associated with

implementation of procedural requirements were interviewed by

the NRC inspector and design calculations were verified.

The

i

third party issued two discrepancy / issue resolution reports

I

(DIRs), D-0130 and D-0133, to document discrepancies in

'

project calculations related to the evaluation of twelve

'

j

random sample selections in regard to undersize welds.

These

-

DIRs were classified as observations since conclusions reached

l

by the project based on those calculations were correct.

All

i

third-party conclusions are complete and the NRC inspector

considers third-party oversight of project actions to have

been effective in identifying any significant errors.

This

item is closed.

6.

Corrective Action Program (CAP)

a.

Small Bore Piping and Pipe Supports (50090)

,

EU Electric has prepared a project status report (PSR)

for small bore piping and pipe supports.

TU Electric

Letter TXX-6846 dated November 2, 1987, formally

submitted this information to the NRC.

The purpose of the project status report is to

l

demonstrate that the safety-related small bore piping and

l

pipe supports in Unit 1 and Common (portions shared by

,

both units) are in conformance with the CPSES licensing

commitments, satisfy the design criteria, and will

satisfactorily perform their safety-related functions.

The small bore piping and pipe supports PSR represents a

road map of the validation effort from the early stages

of design criteria development through the establishment

,

and implementation of the detailed design and design

l

l

control procedures.

The report traces the updating of

design / installation specifications, construction and QC

procedures, the implementation of the post-construction

!

.

-

. - -

. -

.

- - .

- -

- .

.

. -

.

- . _ _ _ _

- - _ _ _ - - - - - -

^

.

i

TU Electric

- ' 15

.

l

l

'

'

l

hardware validation program.(PCHVP)'to validate the

as-built piping and pipe support design, and the

completion of the Unit 1 and Common small bore pipe

stress analysis packages and pipe support calculations.

L

The NRC inspector performed a review of the PSR and

f

developed an NRC inspection plan to evaluate the CAP for

1

'

small bore piping and supports.

The NRC inspection plan

when implemented is intended to accomplish the following:

I

i

l

(1)

Determine whether technical requirements have been

'

adequately addressed in PCHVP CAP specifications and

l

work procedures.

(2)

Detennine through direct observation and independant

,

evaluation of work, whether the applicant's work

control system is functioning properly and whether

the installation of safety-related pipe supports and

restraints are in compliance with NRC requirements,

i

applicant commitments, and applicable codes.

(3)

Provide assurance that the field installation of

[

pipe support hardware is sorrect and will function

i

in a manner that will allow safe operation of the

associated plant system.

i

This inspection plan will be implemented and reported in

subsequent inspection reports,

b.

Conduit Supports A & B Train and C Train > 2" (48053)

During this inspection period, the NRC inspector selected

a sample of 13 conduit walkdown packages to verify the

accuracy and correctness of the Ebasco collected data.

,

The following is a list of the NRC inspected packages:

i

I

$

i

!

!

t

,

I

I

$

!

1

.

-

-

- -

.

-

-

- - - -

-

-

-

-

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ , _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

l.

TU Electric

16

!

Conduit

Site

Room

  • Area
    • Supports

C13G10289

1"

174

AUX

-9

CO2G11960

2"

174

AUX

10

i

C13G05377

2"

77S

SG1

9

l

C13G08392

1 1/2"

100A

-SG1

9

C12G19660

1 1/2"

85D

SG1

14

l

C12K12472

3"

95

SG1

6

C13K30712

2"

94

SG1

7

'

C13010207

2"

94

SG1

7

C14KCJ106

3"

94/100A

SG1

6

C14020426

3/4"

77S

SG1

10

C15Y15296

1"

133

ECB

3

C13016494

3/4"

155A

art

5

C12008110 1 1/2" ~154/155A

- )

16

.

  • SG1 - Unit 1 Safeguards Bu

ag

  • AUX - Auxiliary Building
  • ECB - Electrical / Control Building
  • RB1 - Unit 1 Reactor Building
    • Number of supports includos conduit, junction i a and

pull box supports.

The NRC inspector's walkdowns were performed while

adhering to the criteria of Field Verification Method

(TVM) CPE-EB-TVM-CS-033, Revision 2, and resulted in the

identification of the following discrepancies:

(1)

on Conduit Support C13G10289-05,-the walkdown

engineer reported the location of one of the four

anchor bolts used to attach the support base plate

to the wall, incorrectly.

The location, for the

bolt designated by the letter "A" on the detail

drawing was reported as 1 1/2" up from the bottom

edge of the base plate and 2 1/16" right of the left

edge of the base plate.

The NRC inspector measured

the location to be 2 1/2" up from the bottom edge

and 1 1/2" right of the left edge.

(2)

on Drawing 2323-s-0910 SH.05377 SK01 which is the

l

'

isometric drawn to depict the Conduit Run C13G05377,

the walkdown engineer reported a dimension of

4' 7 3/8" for the "saddle" type section of the

I

vertical run.

The NRC inspector measured this

,

section of conduit at 3' 3 1/2".

The tolerance for

j

this type of measurement is plus or minus

3".

i

.

_ _ _ _ _ _ _ _ _ _ -

.-

,

TU Electric

17

(3) 'For Conduit Support C13G05377-08, the letter stamp

on one of;the Hilti Kwik bolts (HKB) was' reported,

!

by the walkdown engineer, to be'the letter

"E".

The

'

NRC. inspector, during his walkdown of this support,

found that the. letter stamp was actually an

"H".

I

SinceL he letter stamp on the-HKB designates the

!

t

length of.the bolt, the error outlined above.would

'

effect the embedment length and allowable loads used

in the evaluation of the support.

(4)

On' Conduit Support Cl3G05377-01, the walkdown

engineer reported the length of the support base

plate to be 8 11/16".

The NRC inspector measured

this dimension ~at 9 3/4".

Also, on this support the

thickness of the shim plate between the conduit and

the support bracket was reported by the walkdown

engineer as two different thicknesses, in the body

of the sketch it is reported as 3/8" and in the

tabulated data it is reported as 1/4".

The NRC

(

inspector found the shim to be 1/4" thick.

(5)

on Conduit Support C13G08392-01, the walkdown

engineer failed to note that there was a violation

of the minimum spacing requirement for HKB.

The NRC

inspector, during his walkdown of this support,

found two 1/2" .9KB that were 4 1/4" apart; the FVM

calls for a minimum spacing of

5".

l

(6)

on Conduit Support C02G11960-03, the location of the

HKB, designated as Bolt "E" on the detail drawing,

!

was reported by the walkdown engineer as being 2

(

3/4" from the edge of the unistrut member.

During

i

the NRC inspector's walkdown, this dimension was

k

measured at 2 3/8".

Errors such as the six examples cited above while not

individually significant could have a cumulative effect

which could cause the calculation of incorrect stress

levels in the structural members (i.e., baseplates and

unistruts) and, also, incorrect anchor bolt loading and

load interactions.

The above findings (six examples) are similar to other

examples cited in NRC Inspection Reports 50-445/87-31,

50-446/87-23; and 50-445/87-35; 50-446/87-26.

Since the

current six examples occurred in the time period of the

other examples (before corrective actions for the

__

. '

.

- TU Electric

18

previous _ citations were, implemented), a violation will

not be issued.

These examples have been discussed with

Ebasco who has generated DRs to resolve them.

Also,-the-

above findings were detected during the NRC inspector's

walkdown of 13. conduit walkdown packages.

In each

walkdown package there are in excess of 200 attributes

that require inspection / documentation; therefore, the

examples cited. represent errors of less than 1% of the

total. required inspection points.

In regard to the remaining conduit runs, the results of

the NRC walkdown revealed certain data that did not match

that recorded by Ebasco; however, it was determined to be

acceptable since the difference in the recorded

dimensions was still within the tolerances specified in

the applicable FVM.

This is not considered to be a

problem.

On January 28, 1988, meetings were held between

representatives of the NRC, TU Electric, Ebasco, and

Impell to discuss the discrepancies identified as

deviations and violations in recent NRC inspection

reports:

50-445/87-18, 50-446/87-14; 50-445/87-25,

50-446/87-19; 50-445/87-31, 50-446/87-23; and

50-445/87-35, 50-446/87-26.

Both Ebasco and Impell

offered the results of their analysis of discrepancies

found during reinspection of a significant amount of work

previously performed.

Their analysis revealed similar

discrepancy rates with Ebasco reporting 1.8% and Impell

reporting 1.9% which is slightly higher than NRC

findings.

These discrepancy rates were present:ed by both

companies as rates similar or less than those found

throughtout the industry for similar activities.

Impell

took their analysis one step further; they factored the

discrepancies into their design verification calculations

and found that none of the discrepancies caused the

calculated stress to exceed 75% of the allowable.

This

indicates that none of these discrepancies were

significant to the design of either the conduit or the

conduit supports; therefore, there is no adverse impact

on safety.

Also, in performing these reviews, both

Ebasco and Impell determined that certain procedural

changes affecting how attributes are to be evaluated

would reduce the possibility of future discrepancies;

therefore, they have made these changes.

In addition,

both Impell and Ebasco discussed the NRC findings with

their walkdown engineers, reviewed procedures, regularly

l

t

.

.

.

TU Electric

19

do independent checks of their walkdown engineers work,

and held training sessions.

TU Electric reported that

the error rates reported were consistent with the error

rate for the Corrective Action Program of a Region III

utility which was calculated to be 1.9%.

Results

Based on NRC inspection and review of the applicant's

walkdown of conduit supports for Trains A.and B and

Train C greater-than 2" diameter and due to the numerical

error rate and the fact.that the findingsLwere not safety

significant, it appears.that the applicant's program in

this area is providing adequate input data for the design

verification phase of the corrective action program.

c.

Heating Ventilating and Air-Conditioning (HVAC) (50100)

NRC inspectors performed field inspections and

documentation reviews of the following documentation

packages.

These packages were generated as a result of

construction, engineering, and inspection activities

related to HVAC CAP implementation.

Seismic Duct Hanger

Unit

Room

DH-1-844-lK-4E

1

99B

Seismic Duct Segment

Unit

Room

B-1-658-015

1

99B

NRC inspection of HVAC Duct Support DH-1-844-lK-4E,

Revision 1, identified a fillet weld as a 3/16" by 3 5/8"

(i.e., Weld 4 nearside documented in the construction

traveler).

CPE-EB-FVM-CS-029, Revision 5, requires that

welding "

. shall be identified for type of weld

. .

. weld length, and weld size."

The NRC inspector

. .

identified that this weld had been incorrectly documented

by walkdown engineering personnel as a 1/4" fillet weld

and the same had been accepted by QC.

This is another

example of a discrepancy missed by a walkdown engineer.

It is not being cited as a violation for the reasons

'

given in paragraph 6.b.

The NRC inspection of RVAC Duct F;gment B-1-658-015

identified a depression which tppeared to have been

.

-

._

.-.

4

.

O

TU Electric-

20

caused by grinding.

This depression exceeded 1/32" in

depth-(a minimum wall violation).

project Specification

2323-MS-85, Revision 5,Section I.6.C, states, in part,

"Depressions produced by grinding-will not exceed the

following: Sheet metal: 1/32"~for 18 gauge sheet metal

An ultrasonic digital thickness

and thicker .

"

. . .

report indicated that the section of duct with'the

grinding depression was fabricated with 16 gauge sheet

metal which is thicker than 18 gauge metal.

The NRC

inspector could find no indication of an engineering

evaluation or QC identification of this minimum wall

violation.

The preceding example is a violation of Criterion V

,

(445/8805-V-02).

NRC inspection of Seismic Duct Segment B-1-658-015

revealed that construction had removed the protective

coating for QC inspection and subsequently the coating

had not been reapplied.

The NRC inspector identified an

additional 10 examples where the protective coating had

not been reapplied.

See paragraph 3, Concern No. 4'in

NRC Inspection Report 50-445/87-35; 50-446/87-26 and

Example 7 of 445/8735-V-02.

NRC inspection of Duct

segment B-1-658-015 also revealed several areas on the

hem flange between segment B-1-658-015 and segment

B-1-658-014 where the gasket material, Tremco 440, had

been squeezed out from between the flange.

This

condition was identified by Ebasco on CAR 87-079 and

subsequently Stop Work order No. 88-02.

This problem was

also previously identified in an NRC inspection and is

being tracked as open item 445/8735-0-04.

i

The NRC inspector has identified an increased awareness

by TU Electric and Ebasco management to problems

identified in HVAC and feels that this will help improve

the work efforts in this area.

7.

Exit Interview (30703)

l

On January 29, 1988, R.

F. Warnick, H. H. Livermore and

J.

S. Wiebe met with L.

D.

Nace and A. B. Scott to

'

discuss January inspection findings and other matters of

interest.

(See NRC Inspection Report 50-445/88-06,

paragraph 5.)

,

--

,

r

y

-

._

_.

-

.

TU Electric

21

An exit interview was conducted February 2, 1988, with

the applicant's representatives identified in paragraph 1

of this report.

No written material was provided to the

applicant by the inspectors during this reporting period.

The applicant did not-identify as proprietary any of the

materials provided to or reviewed by the inspectors

during this inspection.

During this interview, the NRC

inspectors summarized the scope and findings of the-

inspection.

The applicant acknowledged the finding.

,

. l

i

--

.

.

-

. . - t

-

l 1, G-

I'

,

50-445/89-055 50-446/89-0 9

l

l

DISTRIBUTION:

NE5tSIU52$I50IAIO44ih

NRC PDR

Local PDR-

OSP Reading-

CPPD-LA.

CPPD Reading (HQ)

  • Site Reading File-

AD for Projects

.

  • Sr. Lead Insp. - CONST.

'

  • Concurrence
  • MIS System, RIV
  • RSTS Operator, RIV

DRP, RIV

RIV Docket File

  • LShea,-ARM /LFMB

JTaylor

SEbneter/JAxelrad

'

CGrimes

--

'

PMcKee

JLyons

.

JWilson

JMoore, OGC

JGilliland, RIV

,

'

FMiraglia

EJordan

JPartlow

'

,

BHayes

  • w/766

.

T

i

!

l

I

l

..

..-.

._

. , _ . _ .

. - . . _ _ , _ _

- . - .

.

.