Discusses Results of Insp of FPC Implementation of Engineering Program at Plant,Unit 3 & as Discussed at 970124 Predecisional Enforcement Conference
ML20147G414
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/04/1997
From: Reyes L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Richard Anderson
FLORIDA POWER CORP.
References
CAL-2-97-01, CAL-2-97-1, FACA, NUDOCS 9703280112
Download: ML20147G414 (4)


Text

. . . - ~. . . - . _ - - . - - . - . - . . - _ - - . . . -.

March 4,1997 CAL No. 2 97-001 Florida Power Corporation Crystal River Energy Complex Mr. Roy A. Anderson (SA2A)

Sr. VP, Nuclear Operations ATTN: Mgr., Nuclear Licensing 15760 West Power Line Street Crystal River FL 34428 6708

SUBJECT:

CONFIRMATORY ACTION LETTER

Dear Mr. Anderson:

This refers to the results of NRC inspections of Florida Power Corporation's (FPC) implementation of the Engineering program at Crystal River Unit 3 as discussed in a predecisional enforcement conference conducted in the Region II office on January 24, 1997 and a management meeting conducted at the Crystal River site on February 12, 1997. At these meetings, FPC described its  !

corrective actions taken and planned to address deficiencies in the 1 engineering program and to assure FPC's readiness to restart Crystal River j Unit 3.~ These actions included: (1) completion of a comprehensive '

restructuring of management: (2) completion of indepth reviews and corrective actions to ensure compliance with the licensing and design bases of the facility; and (3) implementation of broad and indepth engineering program

! changes. The specific inspection findings were formally transmitted to FPC by letters dated November 4, 1996 and January 7, 1997.

Pursuant to a telephone conversation between you and Mr. Johns P. Jaudon.

Director, Division of Reactor Safety, on March 4,1997, it is our understanding that FPC will take the following actions before restart of Crystal River Unit 3:

1). Resolve the eight design issues delineated in FPC's letter of October 28, 1996: -

2) Conduct extent of condition reviews to assure that safety related systems are in compliance with the licensing and design bases of j the facility:
3) Satisfactorily resolve any additional safety or licensing questions including those identified as a result of system and engineering reviews in item 2) above;
4) Meet with the NRC to discuss FF"'s acceptance criteria for and

. achievement of satisfactory pr' x on the actions described in

FPC's Management Corrective Acs , Man (MCAP), Phase II, forwarded by FPC's letter of November 12, 1996:

4

5) Obtain concurrence in writing from the NRC Region II Regional l Administrator prior to entering Mode 2.

Sk 9703280112 970304 0FFICIAL COPY k PDR ADOCK 05000302 O PDR h) se' es'

FPC 3 '

cc-John P. Cowan,'Vice President Bill Passetti l Nuclear Production (SA2C) Office of Radiation Control  :

Florida Power Corporation Department of Health and l Crystal River Energy Complex

.lehabilitative Services 15760 West Power Line Street 1317 Winewood Boulevard Crystal River, FL 34428 6708 Tallahassee, FL 32399 0700 l

B. J. Hickle, Director Joe Myers, Director .

Nuclear Plant Operations (NA2C) Division of Emergency Preparedness l Florida Power Corporation Department of Community Affairs Crystal River Energy Complex 2740 Centerview Drive '

15760 West Power Line Street Tallahassee, FL 32399 2100 Crystal River FL- 34428 6708 Chairman  !

David F. Kunsemiller, Director Board of County Commissioners i (SA2A)- Citrus County i Nuclear Operations Site Support 110 N. Apopka Avenue t Florida Power Corporatior. Inverness FL 34450 4245 Crystal River Energy Complex  ;

15760 West Power Line Street Robert B. Borsum i Crystal River, FL 34428-6708 Framatome Technologies l 1700 Rockville Pike. Suite 525  !

R. Alexander Glenn Rockville, MD 20852-1631  :

Corporate Counsel Florida Power Corporation  !

MAC - ASA  !

P. O. Box 14042 i St. Petersburg, FL 33733 4042 Attorney General Department of Legal Affairs-The Capitol 1 Tallahassee, FL 32304 t t

i i

1 l

a FPC 2 i

I l Pursuant to Section 182 of the Atomic Energy Act. 42 U.S.C. 2232, you are i required to:

1) Notify me immediately, and provide subsequent written i notification, if your understanding differs from that set forth  !

above:

2.1 Notify me if for any reason you cannot complete the actions and l

{

advise me in writing, prior to the change or deviation, if you intend to change, deviate from or not complete the plans described j above: and

3) Notify me in writing when you have completed the actions addressed j in this Confirmatory Action Letter.

Issuance of this Confirmatory Action Letter does not preclude issuance of an

! order formalizing the above commitments or requiring other actions on the part

! of the licensee; nor does it preclude the NRC from taking enforcement action

for violations of NRC requirements that may have prompted the issuance of this i

letter. In addition, failure to take the actions addressed in this Confirmatory Action Letter may result in enforcement action.

I In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of i i this letter and your response will be placed in the NRC Public Document Room J (PDR). To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be placed in the PDR without redaction. If aersonal privacy or proprietary information is necessary to provide an accepta)le response, then please provide a bracketed copy of your response that identifies the information that should be protected 1 4 and a redacted copy of your response that deletes such information. If you

, request withholding of such material, you must specifically identify the

, portions of your response that you seek to have withheld and provide in detail

the bases for your claim of withholding (e.g., explain why the disclosure of i information will create an unwarranted invasion of personal privacy or provide '

the information required by 10 CFR 2.790(b) to support a request for with-holding confidential commercial or financial information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.

Sincerely, Luis A. Re Regional ,dm) istrator j Docket No. 50 302 l License No. DPR 72 i cc: (See page 3) 4 l

.I

' FPC 4 Distribution:

PUBLIC JCallan, EDO EJordan, DEDR HThompson, DEDO GTracy. OEDO LReyes, RII i LChandler, OGC '

JGoldberg, OGC RZimmerman. NRR EJulian, SECY BKeeling, CA i Enforcement Coordinators  !

RI, RIII, RIV JLieberman, OE OE:EA File (BSummers) (2 letterhead)

MSatorius, OE JDixon Herrity, OE EHayden, OPA GCaputo, 01 Dross, AE0D l HBell, 0IG CEvans, RII Buryc, RII JJohnson, RII JJaudon, RII KLandis RII CCasto, RII LRagahaven. NRR FHebdon, NRR LMellen, RII 1 KClark, RII I RTrojanowski, RII l NRC Resident Inspector U.S. Nuclear Regulatory Commission 6745 N. Tallahassee Road Crystal River, FL 34428 A

SEND TO Pult1C DOCUMrNT ROOM?k D l W l l

(\ OFFICE RII:DRP Ril:DRh Ril:RC RII:F,1 RII:DRA i k INITIALS M \ W '

Tye - ams9 0[ aa- mos %e a;C , tNtasCn0r, DATE 02/18(/97 01/1k/97 ,9f 24 /97 02 / 97 02 / / 97 cnm /?re m /Qm re G l) GL vre m 0FFICIAL RECORIrf0PY DOCUMEhHt44E: H\1960 PEN.ENF\96465 .btf(\ CAL