ML20147E395
| ML20147E395 | |
| Person / Time | |
|---|---|
| Site: | Catawba |
| Issue date: | 11/30/1978 |
| From: | Murphy C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Dail L DUKE POWER CO. |
| Shared Package | |
| ML20147E387 | List: |
| References | |
| NUDOCS 7812210061 | |
| Download: ML20147E395 (2) | |
See also: IR 05000413/1978011
Text
,
.
_.
.
.
_
..
..
l.
'
en Ric
UNITED STATES
[
oq(o
NUCLEAR REGULATORY COMMISSION
g
R EGloN 11
{
3 ..c.
g
101 MARIETTA STREET, N.W.
r
~ [
ATLANT A. GEORGI A 30303
o
I
- % * * * * * /
NOV 3 01978
In Reply Refer To:
RII:CRM
50-413/78-11
50-414/78-10
.
.
Duke Power Company
ATTN: .Mr. L. C. Dail, Vice President
Design Engineering
Post Office Box 33189
Charlotte, North Carolina 28242
Gentlemen:
This refers to the inspection conducted by Messrs. C. R. McFarland and
J. J. Blake of this office on October 31 through November 3, 1978, of
activities authorized by NRC License Numbers CPPR-116 and CPPR-117 for
the Catawba Nuclear Station facility, Units 1 and 2 and to the discussions
of our findings held with Mr. W. H. Bradley in the Charlotte offices,
and Mr. D. L. Freeze at the site, at the conclusion of the inspection.
i
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report. Within these areas, the inspection
,
consisted of selective examinations of procedures and representative
records, interviews with personnel, and observations by the inspectors.
i
l
Within the scope of this inspection, no items of noncompliance were
.]
I
disclosed.
l
In acco'rdance with Section 2.790 of the NRC's " Rules of Practice",
Part 2, Title 10, Code of Federal Regulations, a copy of this letter and
the enclosed inspection report will be placed in the NRC's Public
Document Room.
If this report contains any information that you (or
)
your contractor) believe to be proprietary, it is necessary that you
make a written application within 20 days to this office to withhold
l
such information f rom public disclosure.
Any such application must
!
include a full statement of the reasons on the basis of which it is
claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained
in a separate part of the document,
If we do not hear from you in this
regard within the specified period, the report will be placed in the
Public Document Room.
78122100M
l
,
.
.
NOV 3 01978
.
Duke Power Company
-2-
4
!
.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
,
'
Charles E. Murphy, Chief
Reactor Construction and
~
Engineering Support Branch
Enclosures:
Inspection Report Numbers
50-413/78-11 and 50-414/78-10
cc w/ enclosures:
Mr. D. G. Beam, Project Manager
Catawba Nuclear Station
Post Office Box 223
Clover, South Carolina 29710