Interim Deficiency Rept (55(e)-84-54) Re Diesel Generator Voltage Profile Study for 600-volt Class 1E Sys.Initially Reported on 841121.Investigation in Progress.Next Rept Will Be Submitted on 850225
ML20140E368
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 12/20/1984
From: Mangan C
NIAGARA MOHAWK POWER CORP.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
(55(E)-84-54), (NMP2L-0304), (NMP2L-304), NUDOCS 8501100798
Download: ML20140E368 (2)


Text

.

NMitM

~

NIAGARA MOHAWK POWER CORPORATION /300 ERIE BOULEVARD WEST. SYRACUSE. N Y.13202/ TELEPHONE (315) 4741511 December 20, 1984 (NMP2L 0304)

. Mr. R. W. Starostecki, Director U. S. Nuclear Regulatory Commission Region I Division of Project and Resident Programs 631 Park Avenue King of Prussia, PA 19406 Re: Nine Mile Point - Unit 2 Docket No. 50-410

Dear Mr. Starostecki:

Enclosed. is an interim report in accordance with 10CFR50.55(e) for the problem concerning the diesel generator voltage-profile study for the 600-V Class 1E system.

This problem was reported via tel-con to T. Silko of your office on Novenber 21,-1984.

Very truly yours, C. V. Mangan Vice President Nuclear Engineering and Licensing i

CW4/GG:csb

( 0614H) xc: Director of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, DC 20555

\\

R. A. Gram, NRC Resident Inspector Project File (2) 8501100798 841220 PDR ADOCK 05000410 B

pop l E- ** ~)

-s 4

d 4-NIAGARA M0HMK POWER CORPORATION NINE MILE POINT - UNIT 2 DOCKET NO. 50-410 Interim Report for a Problem Concerning the Diesel Generator Voltage Profile Study for the 600-V Class IE System

( 55(e)-84-54)

Description of the Problem The Institute of Nuclear Power Operations inspection of Nine Mile. Point - Unit 2 identifled the need for additional justification for an assumption made in the Diesel Generator Voltage Profile Study for the 600-V Class lE System.

An investi gation is being made to determine the maximum kVA required from the diesel generator at time t = 0 after closure of the diesel generator breaker.

A final report will be submitted by February 25, 1985.