ML20140A228

From kanterella
Jump to navigation Jump to search
Final ASP Analysis - Zion 2 (LER 304-91-002)
ML20140A228
Person / Time
Site: Zion File:ZionSolutions icon.png
Issue date: 05/19/2020
From:
NRC/RES/DRA/PRB
To:
Littlejohn J (301) 415-0428
References
LER 340-1991-002
Download: ML20140A228 (7)


Text

B-222 ACCIDENT SEQUENCE PRECURSOR PROGRAM EVENT ANALYSIS LER No.: 304/91-002 Event

Description:

Loss of offsite power with one diesel generator out of service Date of Event: March 21, 1991 Plant: Zion 2 Summary Multiple inadvertent deluge system actuations sprayed the station auxiliary transformer (SAT) at Zion 2 and resulted in a loss of offsite power (LOOP). One emergency diesel generator (EDG) was out of service for maintenance at the time of the event. Equipment rendered unavailable by the LOOP complicated recovery from the event. The conditional core damage probability for this event, based on the current Accident Sequence Precursor (ASP) models, is estimated to be 2.1 x 10-4 . The relative significance of this event as compared to other postulated events at Zion 2 is shown below.

LER 304/91-002 1E-7 1E-6 IE-5 1E-4 IE-3 1E-2 Trip LOW1J L 360 hEP I MTR AFWLDO precursor cutoff _.j 360 h AFW Event Description On March 21, 1991, Zion 2 was operating at full power. EDG 0, the common swing diesel for the two Zion units, was out of service to repair a jacket water leak.

Surveillance testing of the Unit 2 EDGs was in progress, as was Performance Test (PT)-

211, "Wet Pipe Sprinkler Test."

During the morning, three inadvertent deluges occurred on the main power transformer (MPT)/unit auxiliary transformer (UAT) and SAT. In each case, the operators confirmed that no fire had occurred. After the second deluge, the deluge isolation valve for the MPTIUAT was closed. A third deluge occurred while the operators were trying to reset the deluge valve and reopen the isolation valve.

B-223 At 1307 hours0.0151 days <br />0.363 hours <br />0.00216 weeks <br />4.973135e-4 months <br /> in the afternoon, another inadvertent deluge of the Unit 2 SAT occurred.

While the deluge flow was being isolated, the SAT tripped because of a phase-to-ground fault. Buses 243 and 244 supplied by the SAT were automatically transferred to the UAT, which is powered by the main generator. An arc strike was subsequently found on the C phase transformer bushing, and the deluge system spray nozzles were found to have been incorrectly aligned and tested.

Feedwater for Unit 2 was bein'g supplied by one turbine-driven pump and the motor-driven main feedwater (MFW) pump; the second turbine-driven pump was out of service for maintenance. When the SAT tripped, the motor-driven feedwater pump lost power.

Unavailability of the motor-driven feedwater pump caused a reduction in feedwater flow to the steam generators (SGs) and a consequent reduction in SG level, since steam flow had not changed. A bo-l SG level reactor trip occurred at 1310 hours0.0152 days <br />0.364 hours <br />0.00217 weeks <br />4.98455e-4 months <br />. Following the reactor trip, the UAT tripped as expected, resulting in a LOOP.

At the time of the SAT trip, surveillance testing was in progress on EDG 2A. The generator was running, paralleled to bus 248, and loaded to 1 MW. At the time of the UAT trip, EDG 2A output breaker tripped on reverse power but closed again on the LOOP undervoltage signal and repowered bus 248. EDG 2B automatically started and reenergized bus 249 essential loads. Since EDG 0 was out of service for maintenance, bus 247 was not repowered until the operators manually transferred it at 1405 hours0.0163 days <br />0.39 hours <br />0.00232 weeks <br />5.346025e-4 months <br /> (approximately 1 h after the LOOP) to Unit 1 vital bus 141, which is the backup emergency power source for the Unit 2 vital buses.

A number of other problems occurred during and following the LOOP that affected plant and operator response to the event.

1. The sequence of events recorder was powered from a nonvital bus that was lost following the LOOP. Because of this, events that occurred immediately following the reactor trip were not recorded. This lack of information complicated diagnosis of the event.
2. Prior to Unit 2 entering cold shutdown, both power-operated relief valves (PORVs) were stroke-tested to confirm operability for low-temperature overpressure protection. PORV 455C failed to open because of a failed air line. Inoperability of this valve impacted the unit's ability to remove decay heat using bleed and feed, if that had been required.
3. Component cooling water (CCW) pump OA was tripped by an operator after it was observed that there was no oil in the pump. The CCW system is a shared system between the two units, and four CCW pumps remained operable.

B-224

4. Following a loss of nonvital AC power at Zion, the SG relief valve controls fail as is.

The valves were nearly full-open, at the time of the LOOP because the operators were attempting to match feed and steam flow following loss of the motor-driven MFW pump. The valves had to be closed locally by bleeding control air. One of the relief valves failed open and the associated isolation valve had to be closed to terminate flow.

5. Some doors between the power block and the service buildings failed closed when power was apparently lost from the security inverter (reason unspecified). This delayed personnel outside the power block in responding to the event. Personnel inside the power block were not affected. Security personnel responded to the failure in an uncoordinated manner, and station personnel were unaware of which doors would be manned by security personnel in such a situation.

Additional Event-Related Information The Zion 2 emergency power system consists of three buses (247, 248, and 249), which provide essential AC power to safety-related equipment. EDGs 2A and 2B provide emergency power to buses 248 and 249, and swing EDG 0 provides power to bus 247 or Unit 1 bus 147. -In addition, power from the Unit 1 SAT can be manually aligned to supply power to Unit 2. In a similar manner, three batteries provide backup DC power for Unit 2. The two batteries that only provide power to Unit 2 are capable of supplying loads for at least 3 h.

If secondary-side cooling is unavailable, feed and bleed can provide decay heat removal at Zion. Based on the information provided in the NUREG-1 150 analysis for Zion (NUREG/CR-4550, Vol. 7, Rev. 1), feed and bleed success requires one-of-two safety injection (SI) pumps and two POR~s or one-of-two charging pumps and one PORV.

ASP Modeling Assumptions and Approach The event has been modeled as a plant-centered LOOP with one EDG unavailable.

Unavailability of EDG 0 resulted in unavailability of one charging,. service water, SI, and containment spray pump. Manual connection of the emergency buses to the Unit 1 feeder bus was not addressed, and therefore the analysis is somewhat conservative.

Nonrecovery probabilities for LOOP (short-term), electric power prior to battery depletion or core uncovery following a reactor coolant pump (RCP) seal loss-of-coolant accident (LOCA), and the probability of an RCP seal LOCA, were revised to reflect the observed plant-centered LOOP (see ORNL/NRC/LTR-89/1 1, Revised LOOP Recovery and PWR Seal.LOCA Models, August 1989).

The current ASP models do not address the use of the charging pumps as an alternate to

B-225 the SI pumps for high-pressure injection (HPI) and feed and bleed. The branch probabilities for HPI and feed and bleed were modified to reflect the potential use of the charging pumps, and these probabilities were used in a sensitivity analysis.

Because of the unavailability of EDG 0 and PORV 455C, only one charging pump, one SI pump, and one PORV were available for BPI and feed and bleed. Using the train-level screening probabilities typically employed in ASP calculations results in the following branch estimates for these functions:

SI or charging pumps Branch Current ASP models provide success HPI -8.4 x 10-3* -8.4 x 10-5*

Feed and bleed 1.0* -2.8 x 10-2*

  • conditional on unavailability of EDG 0 and PORV 455C Analysis Results The conditional core damage probability for this event, based on the current ASP models, is estimated to be 2.1 x 10-4 . The dominant core damage sequence, highlighted on the following event tree, involves a LOOP with emergency power failure, a resulting RCP seal LOCA, and failure to recover AC power prior to core uncovery.

The second most dominant sequence involves a postulated failure of auxiliary feedwater (AFW) and feed and bleed following emergency power success. The probability of this sequence is affected by assumptions concerning those systems that can provide BPI and feed and bleed, as discussed earlier. Considering the charging pumps as an alternate high-pressure source reduces the core damage frequency estimate for this event to 1.6 x104 Additional information concerning this event is included in Region III AIT inspection team report 50- 304/91006 (DRP), dated April 17, 199 1.

B-226 LOOP RT/LOOP SEQ END EP I F RV/ PRV/ SA EPC HP HPR PO V I IOE NO STATE CHALL RESEAT LOCA (LONG)

I OK OK 41 CO 42 CO OK OK 43 CD (1) 44 CO 45 CO OK 46 CD 47 CO 48 CO OK 49 CO 50 CO OK 51 CO 52 CO 53 CO OK 54 CO 55 CO 40 ATWS (1)0OK for Class D Dominant core damage sequence for LER 304/91-002

B-227' CONDITIONAL CORE DAMAGE PROBABILITY CALCULATIONS Event Identifier: 304/91-002 Event

Description:

LOOP with one EDG out of service (only SI for HPI)

Event Date: 03/21/91 Plant- Zion 2 INITIATING EVENT NON-RPCOVERABLE INITIATING EVENT PROBABILITIES LOOP 5 .OE-01 SEQUENCE CONDITIONAL PROBABILITY SUMS End State/Initiator Probability CD Loop 2 .1E-04 Total 2.1E-04 ATWS Loop 0 .OE+00 Total 0 .OE+00 SEQUENCE CONDITIONAL PROBABILITIES (PROBABILITY ORDER)

Sequence End State Prob N Rec**

53 LOOP -rt/loop EMERG.POWER -afw/ernerg.power -porv.or.srv.chall CD 1.2E-04 4.OE-0l SEAL.LOCA EP.REC(SL) 43 LOOP -rt/loop -EMERG.POWER afw -HPI(F/B) -HPR/-HPI PORV.OPEN CD 4.8E-05 1.3E-01 55 LOOP -rt/loop EMERG.POWER afw/emerg.power CD 1. 9E-05 1.4E-01 54 LOOP -rt/loop EMERG.POWER -afw/emerg.power -porv.or.srv.chall - CD 7.9E-06 4.OE-0l SEAL.LOCA EP.REC 48 LOOP -rt/loop EMERG.POWER -afw/emerg.power porv.or.srv.chall -. CD 5.1E-06 4.OE-01 porv.or.arv.reseat/emerg.power SEAL.LOCA EP.REC(SL)

    • non-recovery credit for edited case SEQUENCE CONDITIONAL PROBAB3ILITIES (SEQUENCE ORDER)

Sequence End State Prob N Rec**

43 LOOP -rt/loop -EMERG.POWER afw -14PI(F/B) -HPR/-IIPI PORV.OPEN CD 4.8E-05 1.3E-01 48 LOOP -rt/loop EMERG.POWER -afw/emerq.power porv.or.srv.chall - CD 5.1E-06 4.OE-01 porv.or.srv.reseat/emerg.power SEAL.LOCA EP.REC(SL) 53 LOOP -rt/loop EMERG.POWER -afw/emerg.power -porv.or.srv.chall CD 1.2E-04 4.OE-0l SEAL.LOCA EP.REC (SL) 54 LOOP -rt/loop EMERG.POWER -afw/emerg.power -porv.or.srv.chall - CD 7.9E-06 4.OE-Ol SEAL.LOCA EP.REC 55 LOUP -rt/loop EMERG.POWER afw/emerg.power CD 1.9E-05 1.4E-01 Snon-recovery credit for edited case SEQUENCE MODEL: c:\asp\1989\pwrbseal.cmp.

Event Identifier: 304/91-002

B-228 BRANCH MODEL: c:\asp\1989\zion.all PROBABILITY FILE: c: \asp\1989\pwr bsll .pro No Recovery Limit BRANCH FREQUENCIES/PROBABILITIES Branch System Non-Recov Opr Fail trans 1.5E-04 1.OE+00 LOOP 1.6E-05 > 1.6E-05 5.3E-01 >5.OE-0l Branch Model: INITOR Initiator Freq: 1. 6E-05 loca 2.4E-06 4.3E-01 rt 2.SE-04 1.2E-01 rt/loop o .OE+OO 1.OE+00 EMERG .POWER 5.4E-04 > 2.9E-03 G.OE-O1 Branch Model: l.OF.3 Train 1 Cond Prob: 5.OE-02 Train 2 Cond Prob: 5.7E-02 Train 3 Cond Prob: 1.9E-01 > Unavailable afw 3.8E-04 2.6E-01 afw/emerg .power 5.OE-02 3.4E-01 mfw 2.OE-0l 3.4E-01 porv.or. srv.chall 4 .OE-02 1.OE+00 porv.or. srv.reseat 2.OE-02 1.1E-02 porv~or. srv.reseat/emerg.power 2 .OE-02 1.OE+00 SEAL. LOCA 2.7E-01 > 2.4E-01 1. 05+00 Branch Model: l.OF.l Train 1 Cond Prob: 2.7E-01 > 2.4E-01 EP.REC (SL) 5.7E-01 > 4.8E-01 1.OE+OO Branch Model: l.OF.1 Train 1 Cond Prob: 5.7E-01 > 4.SE-O1 EP.REC 3.1E-02 > 9.7E-03 1.OE+400 Branch Model: l.OF.1 Train 1 Cond Prob: 3.1E-02 > 9.7E-03 HP I l.OE-03 > 1.OE-02 8.4Z-01 Branch Model: l.OF.2 Train 1 Cond Prob: 1.OE-02 Train 2 Cond Prob: 1.OE-Ol > Unavailable HPI (F/B) l.OE-03 > l.OE-02 8.4E-01 1.05-02 Branch Model: l.OF.2+opr Train 1 Cond Prob: l.OE-02 Train 2 Cond Prob: 1.09-01 > Unavailable HPR/ -HP I 1.5E-04 > 1.OE-02 1.OE+0O 1.05-03 Branch Model: l.OF.2+opr Train I Cond Prob: 1.OE-02 Train 2 Cond Prob: 1.5E-02 > Unavailable PORV.OPEN l.OE-02 > 1.0E+00 1.OE +00 4 .OE-04 Branch Model: 1.OF.l+opr Train I Cond Prob: 1.OE-02 > Failed

  • branch model file
    • forced Minarick 05-22-1992 1750:06 Event Identifier: 304/91-002