Responds to NRC Re Violations Noted in Insp Rept 50-077/85-01.Corrective Actions:Alternate Reactor Administrator Appointed to Ensure Access at All Times to Records
ML20138R247
Person / Time
Site: 05000077
Issue date: 11/05/1985
From: Favret A
CATHOLIC UNIV. OF AMERICA, WASHINGTON, DC
To: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8511180505
Download: ML20138R247 (2)


Text

f..

i- .

DM La L THE CATHOLIC LINIVERSITY L OFAMERICA l

WASHINGTON D.C. 20064 SCHOOL OF ENGINEERING AND ARCHITECTURE, OFFICE OF THE DEAN 202 635-5160 Nov. 5, 1985 Edward C. Wenzinger, Chief ,

Projects Branch No. 3 Division of Reactor Projects U.S. Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, PA. 19406 Docket No. 50-77

Subject:

Inspection 50-77/85-01

Dear Sir:

This is in response to your letter dated July 23, 1985 and the report of the safety inspection conducted by Mr. Thomas Elsasser on June 4, 1985.

After my telephone conversation with Mr. Elsasser on June 21, 1985, I talked to Dr. William Kelnhofer, Chairman of the Mechanical Engineering Department, about my intention to appoint him as an Alternate Reactor Administrator so that someone would always be available to provide access to the official records of the facility.

He agreed to do so. I also notified Dr. John J. Murphy, Executive Vice President, on August 14, 1985 my intention to appoint Dr. Kelnhofer. I did not, in fact, make the official appointment at that time but I have now done so and I am attaching a copy of this notification.

As of now I think we are in full compliance and the official file should be available at all times even when the Reactor Administrator is away from the Campus.

For your information, on October 22, 1985, we submitted a request to change our facility status to " possession only". Further, it is our intent to de-commission the facility as soon as practical.

Si rely you s

/7 8511180505 851105 /

PDR ADOCK 05000077 G PDR a Andrew G. Favret Dean AGF/mgw(1)

Encl.: g cc: Dr. John J. Murphy Mr. Warren Keene

( p 8\

D

, e T H E C A T H O'L I C U N I V E R S I T Y O F A M E R I C A WASHINGTON O.C. 20064 INTERDEPARTMENTAL COM MUNICATION oATE Nov. 5, 1985 sus;EcT. Alternate Reactor Administrator FROM. Dr. Andrew G. Favret, Dean School of Engineering & Architecture TO. Dr. William Kelnhofer Chairman, Mechanical Engineering As I discussed with you last Summer I would like to officially appoint you as

~

the Alternate Reactor Administrator for our Nuclear Reactor. In order to be in full compliance with NRC requirements it is necessary that the records and logs be available for inspection at all times. Since Dr. Jordan, the Reactor Adminisra-tor, may not be'available during the summer months, it is essential t. hat an alternate be appointed.

Please coordinate with Dr. Jordan to insure that you are aware of the location of all logs and records anc can make them available if needed to an inspecting officer from the NRC.

l W

Andrew G. Favrei' Dean AGF/mgw