Forwards Detailed Justifications & Safety Evaluations for Power Ascension Test Mods,Including Test 10 Re APRM Calibr, Test 23A Re MSIV Functional Tests,Test 23B Re MSIV Full Isolation & Test 24 Re Relief Valves
Date released: 05/31/2020 Download: ML20138G467


Safety Evaluation:Deletion of Test 28D,Recirculation Pump Runback Test at Test Condition 3.
ML20138G513
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/01/1985
From:
Public Service Enterprise Group
To:
References
Download: ML20138G513 (3)
Safety Evaluation:Simplification of Test 32,Reactor Water Cleanup Sys.
ML20138G505
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/15/1985
From:
Public Service Enterprise Group
To:
References
Download: ML20138G505 (19)
Safety Evaluation:Simplification of Drywell Piping Vibration,Test 31.
ML20138G497
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/11/1985
From:
Public Service Enterprise Group
To:
References
Download: ML20138G497 (10)
Safety Evaluation:Simplification of Test 28E,Recirculation Sys Cavitation.
ML20138G493
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/15/1985
From:
Public Service Enterprise Group
To:
References
Download: ML20138G493 (6)
Safety Evaluation:Simplification of Test 24,Relief Valves.
ML20138G487
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/15/1985
From:
Public Service Enterprise Group
To:
References
Download: ML20138G487 (5)
Safety Evaluation:Msiv Full Isolation,Test 23B - Expansion of Test Window.
ML20138G479
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/07/1985
From: Mussel W
Public Service Enterprise Group
To:
References
Download: ML20138G479 (3)
Safety Evaluation:Simplification of Test 23A,MSIV Functional Test.
ML20138G474
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/15/1985
From:
Public Service Enterprise Group
To:
References
Download: ML20138G474 (5)
Safety Evaluation:Replace Power Ascension Test Program APRM Calibr Procedure W/Tech Spec Surveillance Procedures & Delete APRM Calibr During Heatup.
ML20138G468
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/09/1985
From:
Public Service Enterprise Group
To:
References
Download: ML20138G468 (4)
Forwards Detailed Justifications & Safety Evaluations for Power Ascension Test Mods,Including Test 10 Re APRM Calibr, Test 23A Re MSIV Functional Tests,Test 23B Re MSIV Full Isolation & Test 24 Re Relief Valves
ML20138G463
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/17/1985
From: Mittl R
Public Service Enterprise Group
To: BUTLER W
Office of Nuclear Reactor Regulation
References
Download: ML20138G463 (5)