MONTHYEARML20211M6651999-09-0101 September 1999 Errata Page 4-45,reflecting Proposed Changes Requested in ML20211D1551999-08-20020 August 1999 Proposed Tech Specs Pages,Revising Degraded Voltage Relay as-left Setpoint Tolerances ML20210J1261999-07-29029 July 1999 Proposed Tech Specs Revising ESF Sys Leakage Limits in post-accident Recirculation Surveillance TSs ML20195E6201999-06-0404 June 1999 Proposed Tech Specs,Modifying Conditions Which Allow Reduction in Number of Means for Maintaining Decay Heat Removal Capability During Shutdown Conditions ML20206R1171999-05-13013 May 1999 Proposed Tech Specs Section 3.1.1,incorporating Administrative Updating & Changing Bases Statement ML20205H0781999-04-0101 April 1999 Proposed Tech Specs Adding LCO Action Statements,Making SRs More Consistent with NUREG-1430,correcting Conflicts or Inconsistencies Caused by Earlier TS Revs & Revising SFP Sampling ML20203B0511999-02-0202 February 1999 Proposed Tech Specs Expanding Scope of Systems & Test Requirements for post-accident RB Sump Recirculation ESF Systems & Increasing Max Allowable Leakage of TS 4.5.4 for Applicable Portions of ESF Systems Outside of Containment ML20196H5361998-12-0303 December 1998 Proposed Tech Specs Reflecting Decrease in RCS Flow Resulting from Revised Analysis to Allow Operation of Plant with 20% Average Level of SG Tubes Plugged Per SG ML20196G4861998-12-0303 December 1998 Non-proprietary Proposed Tech Specs,Consenting to Transfer & Authorization for Amergen to Possess,Use & Operate TMI-1 Under Essentially Same Conditions & Authorizations Included in Existing License ML20196F8661998-11-25025 November 1998 Proposed Tech Specs Revised Pages for TS Change 277 Changing Surveillances Specs for OTSG ISI for TMI Cycle 13 RFO Exams Which Would Be Applicable for One Cycle of Operation Only. with Certificate of Svc ML20154Q6271998-10-19019 October 1998 Proposed Tech Specs Adding Operability & SRs for Remote Shutdown Sys Similar to Requirements in NUREG-1430, Std Tech Specs - B&W Plants, Section 3.3.18 ML20154P8661998-10-19019 October 1998 Proposed Tech Specs,Providing Allowable RCS Specific Activity Limit Based on OTSG Insp Results Performed Each Refueling Outage ML20249B2421998-06-11011 June 1998 Proposed Tech Specs Re Alternate High Radiation Area Control ML20217J8201998-03-25025 March 1998 Proposed Tech Specs Page 6-1,reflecting Change in Trade Name of Owners & Operator of TMI-1 & Correcting Typo ML20217E5311998-03-23023 March 1998 Proposed Tech Specs Pages for Section 3.1.2 to Incorporate New Pressure Limits for Reactor Vessel IAW 10CFR50,App G for Period of Applicability Through 17.7 EFPY ML20217G0201997-10-0303 October 1997 Proposed Tech Specs Re Revised Pages 4-80 & 4-81 Previously Submitted ML20211F3781997-09-24024 September 1997 Proposed Tech Specs Revising Steam Line Break Accident Dose Consequence ML20211C3421997-09-19019 September 1997 Proposed Tech Specs Pages 3.8-3.9b to TS Section 3.1.4 Providing More Restrictive Limit of 0.35 Uci/Gram Dose Equivalent I-131 & Clarifying UFSAR Analysis ML20211C2431997-09-19019 September 1997 Proposed Tech Specs Re Decay Heat Removal Sys Leakage ML20210K0011997-08-14014 August 1997 Proposed Tech Specs Revising TMI-1 UFSAR Section 14.1.2.9 Environ Dose Consequences for TMI-1 Steam Line Break Analysis ML20141J4051997-08-12012 August 1997 Proposed Tech Specs Revising Surveillance Specification for Once Through Steam Generator Inservice Insp for TMI-1 Cycle 12 Refueling (12R) Exams Applicable to TMI-1 Cycle 12 Operation ML20198E7941997-07-30030 July 1997 Proposed Tech Specs Incorporating Addl Sys Leakage Limits & Leak Test Requirements for Systems Outside Containment Which Were Not Previously Contained in TS 4.5.4 Nor Considered in TMI-1 UFSAR DBA Analysis Dose Calculations for 2568 Mwt ML20151K2071997-07-25025 July 1997 Revised TS Page 6-19 Replacing Corresponding Page Contained in 970508 Transmittal of TS Change Request 264 ML20141E1491997-05-0808 May 1997 Proposed Tech Specs,Consisting of Change Request 264, Incorporating Addl NRC-approved Analytical Methods Used to Determine TMI-1 Core Operating Limits ML20140E2471997-04-21021 April 1997 Proposed Tech Specs 3.3.1.2,changing Required Borated Water in Each Core Flood Tank to 940 ft,4.5.2.1.b,lowering Surveillance Acceptance Criteria for ECCS HPI Flow to 431 Gpm & 3.3.1.1.f Re Operability of Decay Heat Valves ML20134M1211997-02-0707 February 1997 Proposed Tech Specs,Incorporating Certain Improvements from Revised STS for B&W plants,NUREG-1430 ML20133D2821996-12-24024 December 1996 Proposed Tech Specs 3.15.3 Re Auxiliary & Fuel Handling Bldg Air Treatment Sys ML20132F3301996-12-16016 December 1996 Proposed Tech Specs,Reflecting Change in Legal Name of Operator of Plant from Gpu Corp to Gpu Inc & Reflecting Plant License & TS Registered Trade Name of Gpu Energy ML20135D0991996-12-0303 December 1996 Proposed Tech Specs Incorporating Certain Requirements from Revised B&W Std TS,NUREG-1430 ML20135C5321996-12-0202 December 1996 Proposed Tech Specs Re Relocation of Audit Frequency Requirements ML20128H4121996-10-0303 October 1996 Errata to Proposed Ts,Adding Revised Table of Contents & Making Minor Editorial Corrections ML20117H0451996-08-29029 August 1996 Proposed Tech Specs,Consisting of Change Request 257, Incorporating Certain Improvements from STS for B&W Plants (NUREG-1430) ML20113D1971996-06-28028 June 1996 Proposed Tech Specs,Consisting of Change Request 259, Allowing Implementation of Recently Approved Option B to 10CFR50,App J ML20112C8791996-05-24024 May 1996 Proposed Tech Specs Re Pages for App A.Certificate of Svc Encl ML20101R1571996-04-10010 April 1996 Proposed Tech Specs,Revising Addl Group of Surveillances in Which Justification Has Been Completed ML20100J6931996-02-22022 February 1996 Proposed Tech Specs,Consisting of Change Request 254, Revising Proposed TS Page 4-46 on Paragraph 4.6.2 That Provides Addl Testing Requirements in Case Battery Cell Parameters Not Met ML20095J2311995-12-21021 December 1995 Proposed Tech Specs,Raising Low Voltage Action Level to 105 Volts DC ML20092K5471995-09-20020 September 1995 Revised Tech Spec Pages 4-31,4-32 & 4-33,incorporating Change in TS Section 4.4.1.5 ML20091L2911995-08-23023 August 1995 Proposed Tech Specs Page 6-11a,incorporating Ref to 10CFR20.1302 ML20087F4921995-08-11011 August 1995 Proposed TS Section 3.2 Re Makeup,Purification & Chemical Addition Sys Requirements ML20085N1601995-06-22022 June 1995 Proposed Tech Specs Revising Replacement Pages in Package & Remove Outdated Pages,In Response to NRC Request for Addl Info ML20084L4351995-06-0101 June 1995 Proposed TS 5.3.1.1,describing Use of Advanced Clad Assemblies ML20084N3501995-06-0101 June 1995 Proposed Tech Specs,Deleting RETS & Relocating TSs Per Guidance in GL 89-01 & NUREG-1430 ML20084B3361995-05-24024 May 1995 Proposed Tech Specs Re Change in Surveillance Test Requirements for source-range Nuclear Instrumentation ML20083N7841995-05-17017 May 1995 Proposed Tech Specs,Consisting of Change Requests 252, Removing Chemical Addition Sys Requirements from TS to COLR ML20079A7811994-12-23023 December 1994 Proposed Tech Specs Page 3-32a ML20069A6781994-05-20020 May 1994 Proposed Tech Specs,Supporting Cycle 10 Control Rod Trip Insertion Time Testing ML20065M6831994-04-19019 April 1994 Proposed Tech Specs,Reflecting Deletion of Audit Program Frequency Requirements ML20065K0451994-04-11011 April 1994 Proposed Tech Specs Reflecting Relocation of Detailed Insp Criteria,Methods & Frequencies of Containment Tendon Surveillance Program to FSAR & Providing Direct Ref to Existing Tendon Surveillance Program ML20073C7731994-03-22022 March 1994 Proposed Tech Specs Re Control Rod Trip Insertion Time Testing 1999-09-01
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20211M6651999-09-0101 September 1999 Errata Page 4-45,reflecting Proposed Changes Requested in ML20211D1551999-08-20020 August 1999 Proposed Tech Specs Pages,Revising Degraded Voltage Relay as-left Setpoint Tolerances ML20210S7691999-08-12012 August 1999 Rev 10 to 6610-PLN-4200.02, TMI Emergency Dose Calculation Manual ML20210J1261999-07-29029 July 1999 Proposed Tech Specs Revising ESF Sys Leakage Limits in post-accident Recirculation Surveillance TSs ML20195E6201999-06-0404 June 1999 Proposed Tech Specs,Modifying Conditions Which Allow Reduction in Number of Means for Maintaining Decay Heat Removal Capability During Shutdown Conditions ML20206R1171999-05-13013 May 1999 Proposed Tech Specs Section 3.1.1,incorporating Administrative Updating & Changing Bases Statement ML20206R6531999-05-13013 May 1999 Rev 39 to TMI Modified Amended Physical Security Plan ML20205H0781999-04-0101 April 1999 Proposed Tech Specs Adding LCO Action Statements,Making SRs More Consistent with NUREG-1430,correcting Conflicts or Inconsistencies Caused by Earlier TS Revs & Revising SFP Sampling ML20204B5291999-03-12012 March 1999 Rev 9 to 6610-PLN-4200.02, TMI Emergency Dose Calculation Manual (Edcm) ML20203B0511999-02-0202 February 1999 Proposed Tech Specs Expanding Scope of Systems & Test Requirements for post-accident RB Sump Recirculation ESF Systems & Increasing Max Allowable Leakage of TS 4.5.4 for Applicable Portions of ESF Systems Outside of Containment ML20196G4861998-12-0303 December 1998 Non-proprietary Proposed Tech Specs,Consenting to Transfer & Authorization for Amergen to Possess,Use & Operate TMI-1 Under Essentially Same Conditions & Authorizations Included in Existing License ML20196H5361998-12-0303 December 1998 Proposed Tech Specs Reflecting Decrease in RCS Flow Resulting from Revised Analysis to Allow Operation of Plant with 20% Average Level of SG Tubes Plugged Per SG ML20196F8661998-11-25025 November 1998 Proposed Tech Specs Revised Pages for TS Change 277 Changing Surveillances Specs for OTSG ISI for TMI Cycle 13 RFO Exams Which Would Be Applicable for One Cycle of Operation Only. with Certificate of Svc ML20154P8661998-10-19019 October 1998 Proposed Tech Specs,Providing Allowable RCS Specific Activity Limit Based on OTSG Insp Results Performed Each Refueling Outage ML20154Q6271998-10-19019 October 1998 Proposed Tech Specs Adding Operability & SRs for Remote Shutdown Sys Similar to Requirements in NUREG-1430, Std Tech Specs - B&W Plants, Section 3.3.18 ML20154D5491998-10-0101 October 1998 Cancellation Notification of Temporary Change Notice 1-98-0066 to Procedure 6610-PLN-4200.02 ML20206C0911998-09-0101 September 1998 Rev 17 to Odcm ML20249B2421998-06-11011 June 1998 Proposed Tech Specs Re Alternate High Radiation Area Control ML20216E9751998-04-13013 April 1998 Emergency Dose Assessment Users Manual, for Insertion Into Rev 7 of Edcm ML20216E9491998-04-0909 April 1998 Rev 7,Temporary Change Notice 1-98-003 to 6610-PLN-4200.02, Edcm, Changing Pages 2 & 57 & Adding New Emergency Dose Assessment Users Manual ML20217J8201998-03-25025 March 1998 Proposed Tech Specs Page 6-1,reflecting Change in Trade Name of Owners & Operator of TMI-1 & Correcting Typo ML20217E5311998-03-23023 March 1998 Proposed Tech Specs Pages for Section 3.1.2 to Incorporate New Pressure Limits for Reactor Vessel IAW 10CFR50,App G for Period of Applicability Through 17.7 EFPY ML20202B2061998-01-30030 January 1998 Rev 7,Temporary Change Notice 1-98-0013 to 6610-PLN-4200.02, Edcm ML20198T4721997-12-31031 December 1997 TMI-1 Cycle 12 Startup Rept ML20217G0201997-10-0303 October 1997 Proposed Tech Specs Re Revised Pages 4-80 & 4-81 Previously Submitted ML20211F3781997-09-24024 September 1997 Proposed Tech Specs Revising Steam Line Break Accident Dose Consequence ML20211C2431997-09-19019 September 1997 Proposed Tech Specs Re Decay Heat Removal Sys Leakage ML20211C3421997-09-19019 September 1997 Proposed Tech Specs Pages 3.8-3.9b to TS Section 3.1.4 Providing More Restrictive Limit of 0.35 Uci/Gram Dose Equivalent I-131 & Clarifying UFSAR Analysis ML20210K0011997-08-14014 August 1997 Proposed Tech Specs Revising TMI-1 UFSAR Section 14.1.2.9 Environ Dose Consequences for TMI-1 Steam Line Break Analysis ML20141J4051997-08-12012 August 1997 Proposed Tech Specs Revising Surveillance Specification for Once Through Steam Generator Inservice Insp for TMI-1 Cycle 12 Refueling (12R) Exams Applicable to TMI-1 Cycle 12 Operation ML20198E7941997-07-30030 July 1997 Proposed Tech Specs Incorporating Addl Sys Leakage Limits & Leak Test Requirements for Systems Outside Containment Which Were Not Previously Contained in TS 4.5.4 Nor Considered in TMI-1 UFSAR DBA Analysis Dose Calculations for 2568 Mwt ML20151K2071997-07-25025 July 1997 Revised TS Page 6-19 Replacing Corresponding Page Contained in 970508 Transmittal of TS Change Request 264 ML20217M7251997-06-22022 June 1997 Rev 16 to Procedure 6610-PLN-4200.01, Odcm ML20141E1491997-05-0808 May 1997 Proposed Tech Specs,Consisting of Change Request 264, Incorporating Addl NRC-approved Analytical Methods Used to Determine TMI-1 Core Operating Limits ML20140E2471997-04-21021 April 1997 Proposed Tech Specs 3.3.1.2,changing Required Borated Water in Each Core Flood Tank to 940 ft,4.5.2.1.b,lowering Surveillance Acceptance Criteria for ECCS HPI Flow to 431 Gpm & 3.3.1.1.f Re Operability of Decay Heat Valves ML20134M1211997-02-0707 February 1997 Proposed Tech Specs,Incorporating Certain Improvements from Revised STS for B&W plants,NUREG-1430 ML20133D2821996-12-24024 December 1996 Proposed Tech Specs 3.15.3 Re Auxiliary & Fuel Handling Bldg Air Treatment Sys ML20132F3301996-12-16016 December 1996 Proposed Tech Specs,Reflecting Change in Legal Name of Operator of Plant from Gpu Corp to Gpu Inc & Reflecting Plant License & TS Registered Trade Name of Gpu Energy ML20135D0991996-12-0303 December 1996 Proposed Tech Specs Incorporating Certain Requirements from Revised B&W Std TS,NUREG-1430 ML20135C5321996-12-0202 December 1996 Proposed Tech Specs Re Relocation of Audit Frequency Requirements ML20128H4121996-10-0303 October 1996 Errata to Proposed Ts,Adding Revised Table of Contents & Making Minor Editorial Corrections ML20117H0451996-08-29029 August 1996 Proposed Tech Specs,Consisting of Change Request 257, Incorporating Certain Improvements from STS for B&W Plants (NUREG-1430) ML20113D1971996-06-28028 June 1996 Proposed Tech Specs,Consisting of Change Request 259, Allowing Implementation of Recently Approved Option B to 10CFR50,App J ML20112C8791996-05-24024 May 1996 Proposed Tech Specs Re Pages for App A.Certificate of Svc Encl ML20138B4641996-05-0606 May 1996 Rev 14 to Procedure 6610-PLN-4200.01, Odcm ML20101R1571996-04-10010 April 1996 Proposed Tech Specs,Revising Addl Group of Surveillances in Which Justification Has Been Completed ML20100J6931996-02-22022 February 1996 Proposed Tech Specs,Consisting of Change Request 254, Revising Proposed TS Page 4-46 on Paragraph 4.6.2 That Provides Addl Testing Requirements in Case Battery Cell Parameters Not Met ML20096F0521995-12-31031 December 1995 TMI-1 Cycle 11,Startup Rept ML20095J2311995-12-21021 December 1995 Proposed Tech Specs,Raising Low Voltage Action Level to 105 Volts DC ML20092M1941995-09-21021 September 1995 TMI-1 Pump & Valve IST Program 1999-09-01
[Table view] |
Text
. .
3.5 INSTRUMENTATION SYSTEMS 3.5.1 OPERATIONAL SAFETY INSTRUMENTATION Applicability
' Applies to unit instrumentation and control systems.
Objective To delineate the conditions of the unit instrumentation and safety circuits necessary to assure reactor safety.
Specifications 3.5.1.1 The reactor shall not be in a startup mode or in a critical state unless the requirements of Table 3.5-1, Column ' A' and 'B' are met. Specification 3.0.1 applies.
3.5.1.2 For on-line testing or in the event of a protection instrument or channel failure, a key operated channel bypass switch associated with each reactor protection channel will be used to lock the reactor trip module in the untripped state as indicated by a light. Only one channel shall be locked in this untripped state at any one time. Unit operation at rated power shall be permitted to continue with Table 3.5-1, Column "A". Only one channel bypass key shall be kept in the control room.
3.5.1.3 In the event the number of protection channels operable falls below the limit given under Table 3.5-1, Column "A", operation shall be limited as specified in Column "C". Specification 3.0.1 applies.
3.5.1.4 The key operated shutdown bypass switch associated with each reactor protection channel shall not be used during reactor power operation (except for required maintenance or testing).
3.5.1.5 During START-UP when the intermediate range instruments come on l scale, the overlap between the intermediate range and the source range instrumentation shall not be less than one decade.
3.5.1.6 During START-UP, HOT STANDBY or POWER OPERATION, in the event that a control rod drive trip breaker is inoperable, within one hour place the breaker in trip. Specification 3.0.1 applies.
3.5.1.7 During START-UP, HOT STANDBY or POWER OPERATION, in the event one of the control r'od drive trip breaker diverse trip feature,that s
. (shunt trip or undervoltage trip attachment) is inoperable:
- a. Restore to OPERABLE status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or
- b. Within one additional hour place the breaker in trip.
Specification 3.0.1 applies.
h P
Amendment No. 62, 98
, 3-27 L
I i
3.5.1.7.1 Power may be restored through the breaker with the failed trip feature for up to two hours for surveillance testing per T.S. 4.1.1.
3.5.1.8 During. START-UP, HOT STANDBY or POWER OPERATION, in the event that one of the two regulating control rod power SCR electronic trips is inoperable, wit.hin one' hour:
- a. Place the inoperable SCR electronic trip in the tripped condition or
- b. Remove the power supplied to the associated SCRs.
Specification 3.0.1 applies.
.3.5.1.8.1. Power may be restored through the SCRs with the failed electronic trip for up to~ two hours for surveillance testing per T.S. 4.1.1.
Amendnent No. 62, 98 3-27a E______--__________---______.--________--.--_________---.-- - - - - . - - _ _ - - - _ - - _ - - - - - _ - - - - - - . _ - - -
Bases Every reasonable effort will be made to maintain all safety instrumentation in operation. A startup is not permitted unless three power range neutron instrument channels and two channels each of the following are operable: ~four reactor coolant temperature instrument channels, four reactor coolant flow instrument channels, four reactor coolant pressure instrument channels, four pressure-temperature instrument channels, four flux-imbalance flow instrument channels, four power-number of pumps instrument channels, and four high reactor building pressure instrument channels. The reactor trip, on loss of feedwater may be bypassed below 7% reactor power. The bypass is automatically removed when reactor power is raised above 7%. The reactor trip, on turbine trip, may be bypassed below 20% reactor power. The safety features actuation system must have two analog channels functioning correctly prior to startup.
The anticipatory reactor trips on loss of feedwater pumps and turbine trip have been added to reduce the number of challenges to the safety valves and power operated relief valve but have not been credited in the safety analyses.
Operation at rated power is permitted as long as the systems have at least the redundancy requirements of Column "B" (Table 3.5-1). This is in agreement with redundancy and single failure criteria of IEEE 279 as described in FSAR Section 7.
There are four reactor protection channels. Normal trip logic is two out of four. Required trip logic for the power range instrumentation channels is two out of three. Minimum trip logic on other instrumentation channels is one out of two.
The four reactor protection channels were provided with key operated bypass switches to allow on-line testing or maintenance on only one channel at a time during power operation. Each channel is provided alarm and lights to indicate when that channel is bypassed. There will be one reactor protection system bypass switch key permitted in the control room.
Each reactor protection channel key operated shutdown bypass switch is provided with alarm and lights to indicate when the shutdown bypass switch is being used.
Power is normally supplied to the control rod drive mechanisms from two separate parallel 460 volt sources. Redundant trip devices are employed in each of these sources. The AC Trip Breaker is one means to trip a source.
The redundant means is a parallel configuration consisting of two DC Trip Breakers and five SCR power supplies. The SCRs are turned off by the
" electronic trip relays."
Diverse trip features are provided on each breaker. These are the undervoltage relay and shunt trip attachment. Each trip feature is tested separately. Failure of one breaker trip feature does not result in loss of redundancy and a reasonable time limit is provided for corrective action.
Amendment No. 78 3-28 u _ _ - _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ _
. . . . . g Failure in the untripped state of a breaker or SCR electronic trip results in loss of redundancy and prompt action is required. Failure of both trip features on one breaker is considered failure of the breaker.
Power may be restored through the failed breaker (SCRs) for a limited time to perform required testing.
Reference FSAR, Section 7.1 J
f Amendment No. 78 3-28a
1
.**g Channels subject only to " drift" errors induced within the instrumentation itself can tolerate longer intervals between calibrations. Process system instrumentation errors induced by drift can be expected to remain within acceptance telerances if recalibration is performed at the intervals of each refueling period.
Substantial calibration shifts within a channel (essentially a channel failure) will be revealed during routine checking and testing procedures.
Thus, minimum' calibration frequencies set forth are considered acceptable.
Testing On-line testing of reactor protection channels is required monthly on a rotational basis. The rotation scheme is designed to reduce the probability of an undetected failure existing within the system and to minimize the likelihood of the same systematic test errors being introduced into each redundant channel.
The rotation schedule for the reactor protection channels is as follows:
Channels A, B, C & D Before Startup, when shutdown greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />
- Channel A One Week After Startup Channel B Two Weeks After Startup Channel C Three Weeks After Startup
, Channel D Four Weeks After Startup The reactor protection system instrumentation test cycle is continued with one i channel's instrumentation tested each week. Upon detection of a failure that prevents trip action in a channel, the instrumentation associated ~with the protecticn parameter failure will be tested in the remaining channels. If actuation of a safety channel occurs, assurance will be required that actuation was within the limiting safety system setting.
The protection channels coincidence logic, the control rod drive trip breakers and the regulating control rod power SCRs electronic trips, are trip tested
' monthly. The trip test checks all logic combinations and is to be performed on a-rotational basis. The logic and breakers of the four protection channels and the regulating control rod power SCRs shall be trip tested prior to startup when the reactor has been shutdown for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Discovery of a failure that prevents trip action requires the testing of the instrumentation associated with the protection parameter failure in the remaining channels.
Amendment No. 78 4-2
TABLE 4.1-1 INSTRUMENT SURVEILLANCE REQUIREMENTS l CHANNEL DESCRIPTION CHECK TEST CALIBRATE REMARKS
- 1. Protection Channel NA M NA Coincidence Logic
- 2. Control Rod Drive Trip NA M NA Includes independent. testing of s, hunt trip and Breaker & Regulating Rod undervoltage trip features.
Power SCRs
- 3. Power Range Amplifier D(1) NA (2) (1) When reactor power is greater than 15%.
(2) When above 15% reactor power run a heat balance check once per shift. Heat balance calibration shall be performed whenever heat balance exceeds indicated neutron power by more than 2%.
$ 4. Power Range Channel S M M(1)(2) (1) When reactor power is greater than 60% verify imbalance using incore instrumentation.
(2) When above 15% reactor power calculate axial l offset upper and lower chambers after each startup if not done within the previous 7 days.
S. Intermediate Range Channel S(1) P NA (1) When in service.
I
- 6. Source Range Channel S(1) P NA (1) When in service. -
E 7. Reactor Coolant Temperature S M R j
Channel 2 8. High Reactor Coolant S M R
. Pressure Channel w
. 9. Low Reactor Coolant 5 M R Pressure Channel E3 l
l