Forwards Safety Insp Rept 50-461/85-63 on 851118-1216 & Notice of Violation.Nrc Understanding of Corrective Actions for Violation Noted in Previous Insp Described in Paragraph 6.d of Insp Rept
ML20137E020
Person / Time
Site: Clinton Constellation icon.png
Issue date: 01/10/1986
From: Warnick R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Gerstner W
ILLINOIS POWER CO.
Shared Package
ML20137E025 List:
References
NUDOCS 8601170144
Download: ML20137E020 (2)


See also: IR 05000461/1985063

Text

O

d7///d

,

~

Docke't No. : 50-461 - JAN 101986

Illinois Power Company

ATTN: Mr. W. C. Gerstner

Executive Vice President

500 South 27th Street

Decatur, IL 62525

Gentlemen:

This refers to the routine safety inspection conducted by Mr. T. P. Gwynn-

and others of this office on November 18 through December 16, 1985, of

activities at Clinton Power Station authorized by NRC Constructicn Permit

No. CPPR-137, and to the discussion of our findings with you and others of

your staff at..the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspec. tion consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

During this inspection, certain of your activities appeared to be in violation

of NRC requirements, as described in the enclosed Notice. During the inspection

it was noted that action had been taken to correct the identified violation and

to prevent recurrence. Our understanding of your corrective actions are

described in Paragraph 6.d. of the enclosed inspection report. Consequently,

no reply to'the violation is required and we have no further questions regarding

this matter at this time.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter and the enclosures will be placed in the NRC Public Document Room.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

s6o1170144 e6011o

'

"OrtotMJ signed}y 2. F. ll4.*alg

PDR ADOCK 05000461

G PDR

R. F. Warnick, Chief

Reactor Projects Branch 1

Enclosures:

1. Notice of Violation

2. Inspection Report

No. 50-461/85063(DRP)

See Attached Distribution g,p

RIII~ RI RII RIII g RIII

n/jlk J

a

onski Tambling

.) &

Danielson arrison

(?fa ) RM k

RIII

ni,ck Greenman

lll 0{ $L, i * /24 ll1 Way///IA

I/ Y#/E {

$ ,)

__ _ _ _ _ _ __ _ _ _ _ . _ _ . _ __ .

._.

,

s

s $6:' .

o .

6

. Illinois Power Company- 2

J.At1 ! 01986

g

Distribution

cc w/ enclosures:

DCS/RSB.(RIDS)_

' Licensing Fee Management Branch

Resident Inspector, RIII

Richard Hubbard

Gary N. Wright, Manager

Nuclear. Facility Safety

LJ ean Foy, Prairie Alliance

Mark Jason, Assistant

Attorney General,

Environmental Control Division

H. S. Taylor, Quality Assurance

Division-

..