Forwards Resident Safety Insp Rept 50-271/85-36 on 851021-1125 & Notice of Violation.Actions to Correct Violations Noted in Re Fire Sys Surveillance Procedures Verified
ML20137B041
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 01/06/1986
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Murphy W
VERMONT YANKEE NUCLEAR POWER CORP.
Shared Package
ML20137B044 List:
References
RTR-NUREG-0737, RTR-NUREG-737 NUDOCS 8601150031
Download: ML20137B041 (2)


See also: IR 05000271/1985036

Text

p.

. . .

,

  1. H 0 01936

Docket No. 50-271

Vermont Yankee Nuclear Power Corporation

ATTN: Mr. Warren P. Murphy

Vice President and Manager of Operations

RD 5, Box 169

Ferry Road

Brattleboro, Vermont 05301

Gentlemen:

Subject: . Inspection Report No. 50-271/85-36

This refers to the routine resident safety inspection conducted by Mr. W. J. Raymond

of this office on October 21 - November 25, 1985, at the Vermont Yankee Nuclear

Power Station, Vernon, Vermont. The inspection consisted of observation of acti-

vities,' interviews with personnel and document reviews. The results of the in-

spection are described in the NRC Region I Inspection Report enclosed with this

letter and were discussed with Mr. J. P. Pelletier of your staff at'the conclusion

of the inspection.

The inspector also reviewed the actions taken to correct the violations brought

to your attention in our. letter dated May 2, 1984, concerning system valve lineup

controls, and in our letter dated April 15, 1985, concerning fire system surveil-

lance procedures and the control procedures following system modifications. We

have no further questions regarding your actions at this time.

Based on the results of this inspection, it appears that one of your activities

were not conducted in full compliance with NRC requirements, as set forth in the

Notice of Violation, enclosed herewith as Appendix A. The violation concerns the

failure of technicians to follow and/or change approved calibration procedures when

the radiation sources used to calibrate a. safety related monitor became weak. This

violation has been categorized by severity level in accordance with the revised

NRC Enforcement Policy (10 CFR 2, Appendix C), published in the Federal Register

on March 8, 1984 (FR 8583). You are required to respond to this letter and in

preparing your response, you shoulo follow the instructions in Appendix A.

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice", a copy of this

letter and the enclosures will be placed in the NRC Public Document Room.

Your cooperation with us is appreciated.

Sincerely,

Orinic .2. Si:;ned ag4

Edward C. Wenzinger, Chief

Projects Branch No. 3'

'

106

11500 $ 21 D1 vision of Reactor Projects

G

,

9

7. .

-

. ...

.

Vermont. Yankee Nuclear JAN'0 61986

Power Corporation 2

Enclosure: NRC Region I Inspection Report No. 50-271/85-36

cc w/encls:

Mr. R. W. Capstick, Licensing Engineer

Mr. W. F. Conway, President and Chief Executive Officer

Mr. J. P. Pelletier, Plant Manager

Mr. Donald. Hunter, Vice President

Mr. Cort Richardson, Vermont Public Interest Research Group, Inc.

Public Document Room (POR)

Local Public Document Room (LPOR)

. Nuclear- Safety Information Center (NSIC)

State of.New Hampshire-

State of Vermont

NRC Resident Inspector

bec w encls:

Region I Docket Room (with concurrences)

DRP Section Chief

DRP Branch Chief

M. McBride, SRI, Pilgrim

H. Eichenholz, SRI, Yankee

V. Rooney, LPM, NRR

W

P RP R

aymond/meo T p nz ger

j r 1/3/(p gg

,

OFFICIAL RECCRD COPY IR VY 85-36 - 0002.0.0