OPERATING DATA REPORT DOCKET NO. 50-336 DATE 7/is/as COMPLETED BY G. Neron TELEPHONE (203) 447-1791 Extension 4417 OPERATING STATUS
- 1. Unit Name: Millstone Unit 2 Notes Items 21 and 22
- 2. Reporting Period: June 1985 cumulative are weighted
- 3. Licensed Thermal Power (MWt): 2700 averages. Unit operated
- 4. Nameplate . Rating (Gross MWe): 909 at 2560 MW thermal prior
- 5. Design Electrical Rating (Net MWe): 870 to its uprating to the
- 6. Maximum Dependable Capacity (Gross MWe): 866.25 current 2700 MW thermal
- 7. Maximum Dependable Capacity (Net MWe): 833.25 power level.
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7)
Since Last' Report, Give Reasons:
N/A
- 9. Power Level To Which Restricted, If Any.(Net MWe): .
N/A
- 10. Reasons For Restrictions, If Any:
N/A This Month Yr.-to-Date Cumulative l 11. Hours In Reporting Period 720 4343 83399
- 12. Number Of Hours Reactor Was Critical 2.8 1114.9 58077
- 13. Reactor Reserve Shutdown Hours 0 0 2205.5
- 14. Hours Generator On-Line 0 1109.8 55502.8
- 15. Unit Reserve Shutdown Hours 0 0 468.2
- 16. Gross Thermal Energy Generated (MWH) 0 2895103 140579560
- 17. Gross Elec. Energy Generated (MWH) 0 945800 45627479
- 18. Net Electrical Energy Generated (MWH) (-4874) 895827 43719350
- 19. Unit Service Factor 0 25.6 66.6
- 20. Unit Availability Factor 0 25.6 - 67.1
- 21. Unit Capacity Factor (Using MDC Net) 0 24.8 62.9
- 22. Unit Capacity Factor (Using DER Net) 0 23.7 62.0
- 23. Unit Forced Outage Rate 0 0 16.8
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
N/A
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup: N/A
' 26. Units In Test Status (Prior to Commercial Operation): Torecast Achieved INITIAL CRITICALITY N/A N/A
-INITIAL ELECTRICITY N/A N/A CO M ERCIAL OPERATION N/A N/A 8509110262 850715 PDR ADOCK 05000336 R PDR by
,' AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-336 UNIT Millstone 2 DATE 7/15/85 COMPLETED BY G. Neron TELEPHONE (203) 447-1791 Extension 4417
! MONTH June 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net)
I O 17 0 2 0 18 0 3 0 19 0 4 0 20 0 5 0 21 0 6 0 22 0 7 0 23' 0 8 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 12 0 28 0 4
13 0 29 -
0 i
14 0 30 0 2
15- 0 31 16 0 .
4 INSTRUCTIONS On this format,-. list the average daily unit power level -in MWe-Net' for each day in the reporting month. Compute to the nearest whole_ megawatt. .,
i l
i 1
, I
i DOCKET NO. 50-336 .
UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Millstone 2 .' .
l DATE 7/15/85 '.
COMPLETED BY G. Neron-
- l REPORT MONTH June TELEPHONE (203) 447-1791' Extension 4417 No. l 2
.Date_ . Type Duration Reason Method of Licensee Systeg Compogent Cause & Corrective (Hours) Shutting 3 Event Code Code Action to Down Reactor Report #- Prevent Recurrence:
I i
1- ~ 850216 S 720 C 1 N/A N/A N/A- Continuation of Refuel Maintenance Outage from previous-month.
1 2 3 4 F: Forced Reason: Method: Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test. 2-Manual. Scram- Enter Sheets for LicensG
'C-Refueling 3-Automatic' Scram Event Report'(LER) File D-Regulatory Restriction 4-Continued from (NUREG-0161)
-E-Operator Training & License Examination previous month F-Administrative 5-Power Reduction 5 G-Operational Error (Explain) (Duration = 0) Exihibit 1 - Same ' Source H-Other (Explain) 9-Other (Explain)
~
L D:ckst N2. 50-336 ,
Date 7/1sfas
- t Unit Name Millstone 2 -
Completed By G. Neron .
Telephone (203) 447-1791 Extension 4417 CORRECTIVE MAINTENANCE SUPMARY FOR SAFETY RELATED. EQUIPMENT REPORT MONTH June 1985.
DATE SYSTEM COMPONENT MAINTENANCE ACTION f 2/22/85 Reactor Coolant'& Vessel Spare Pressurizer Replaced precision resistor valued 9 i Transmitter N-E11GM 25.01 ohms.
l 4/30/85-- Reactor Coolant & Vessel Pressure Transmitters. Grease and replace transmitter "0" l PT-100Y and PT-100X rings, torque covers.
6/3/85 Reactor Coolant & Vessel RCP Speed Sensor Pulse Verified connections, corrected Transmitter leads on TB-9 lower from 5, 6, 7 & 8 to 1, 2, 3 & 4.
6/3/85- Safety Injection Tanks SIT T390 Low Level Alarm Installed new microswitch #BZR241.
l 6/3/85 Safety Injection Tanks SIT T390 Pressure Installed new seal tite assembly.
Transmitter 6/8/85 Containment Structure CTMT Electrical Penetration Replaced broken teritii:41 with spare l SEX-E6 Wiedmuller terminal.
6/8/85 Containment Structure CTMT Electrical Penetration- Replaced broken terminal with spare.
SWX-E5 3/12/85 Service Water SW Pump PSB Filter Pressure Installed new switch and calibrated.
Diff Switch
D:ck t N2. 50-336 -
Date 7/15/85
- Unit Name Millstone 2 -
Completed By G. Neron l Telephone (203) 447-1791 Extension 4417 CORRECTIVE MAINTENANCE SUPMARY FOR SAFETY RELATED EQUIPMENT REPORT MONTH June 1985 l
DATE SYSTEM COMPONENT MAINTENANCE ACTION
'6/20/85 Incore Nuclear Monitor Incore Detector E20 Replaced mineral cable.
Incore Detector F19 Incore Detector J7 Incore Detector T2 6/13/85 Incore Nuclear Monitor Incore Detector L18 Replaced ICI L-18 cable.
l l 5/31/85 ESAS Automatic Test Inserter Replaced lamp socket.
L
! 6/17/85 ESAS Bus 24C LNP (A3) UV Trip Replaced bistable trip module BA-212.
l Bistable l
6/17/85 Reactor Protection Power Ratio Calculator Replaced the B2-3 Module.
3/26/85 Reactor Protection S/G #2 Pressure Transmitter- Installed new amplifier, calibrated, replaced "0" ring and torqued cover.
3/16/85 Reactor Protection Reactor Protection System Replaced all noise suppressor diodes on RPS Channel A thru D and checked.
5/10/85 Reactor Protection Reactor Protection System Performed component swap of CR1 and l R3 for Channels A, B & C. Installed l new Channel "D" pre-amp assembly.
Docket No. 50-336
- Date 7/15/85 ,
Unit Name Millstone 2 -
- Completed By G. Neron .
. Telephone (203) 447-1791 Extension 4417 CORRECTIVE MAINTENANCE SUMARY FOR SAFETY RELATED EQUIPMENT REPORT MONTH June 1985 DATE SYSTEM COMPONENT MAINTENANCE ACTION 4/9/85 Reactor Protection Reactor Protection System Cleaned contacts on trip test relay K1-
! on Channel A, B & D.
4/11/85 Reactor Protection Reactor Protection System Replaced trip test pots on Channel "A" l
thru "D" RPS linear range drawers.
4/9/85 Reactor Protection Calibration and Indication Burnished K1 relay contacts and Panel RPS-C reinstalled / verified proper operation.
6/11/85 Reactor Protection Calibration and Indication Replaced old fuse holder with new holder.
Panel RPS-D 6/19/85 Reactor Protection Wide Range Log Channel D Replaced Channel "D" Wide' Range Detector.
6/17/85 Reactor Protection Wide Range Drawer RPS-D Replaced Scaling Resistor.
l
- 6/19/85 Reactor Regulating RRS Channel X Neutron Installed new detector in well #12.
l . Detector 4/16/85 Reactor Regulating Reactor Coolant Loop 2A Installed new RTD, S/N 963.
Cold Leg Temp 6/13/85 CEA Position Indication Reed Switch Assembly Replaced reed switch "A" cable for switch 09.
i l
l t - -
Dockst No. 50-336 -
Date 7/15/85 ,
Unit Name Millstone 2 -
Completed By G. Neron .
Telephone (203) 447-1791~
Extension 4417 CORRECTIVE MAINTENANCE
SUMMARY
FOR SAFETY RELATED EQUIPMENT REPORT MONTH June 1985 DATE SYSTEM COMPONENT MAINTENANCE ACTION 4/11/85 Reactor Coolant & Vessel Reactor Internals - UGS Removed three (3) bent CEA extension shafts.
4/23/85 Reactor Coolant & Vessel Reactor Internals - Cut locks and removed #5 cluster.
ICI Plate 6/8/85 Reactor Coolant & Vessel Reactor Coolant Pump Overhauled M-2 RCP seal.
6/12/85 Reactor Coolant & Vessel RCP Suction Line Drain Repacked 2-RC-0358.
Isolation Valve 5/29/85 Reactor Coolant & Vessel Pressurizer PORV Assembly Removed flange elbow and spool piece, straightened spool piece and welded-new flange and elbow onto 2-RC-404.
3/1/85 Fuel / Reactor Component Spent Fuel Handling Tool Replaced old grapple with new grapple Handling assembly, replaced upper tool section and inner sections of old tool with sections from spare tool.
6/20/85 CVCS "A" Charging Pump Repacked pump, torqued plunger head nuts.
Dockat No. 50-336 -
Date 7/15/85
- Unit Name Millstone 2
- Completed By G. Neron .
Telephone (203) 447-1791 Extension 4417 CORRECTIVE MAINTENANCE SUPMARY FOR SAFETY RELATED EQUIPMENT REPORT MONTH June 1985 DATE SYSTEM COMPONENT MAINTENANCE ACTION 6/22/85 Safety Injection Tanks Hanger #410018 for 12-CCA-5 Removed hanger base plate, drilled Piping new Hilti-Bolt holes, installed new hanger base plate and welded to hanger.
3/30/85 HPSI "B" Header Relief Valve Bench tested and set valve at 1740 PSI.
6/2/85 HPSI "A" Header to Loop 1A Removed stem nut and installed new Injection Valve Motor operator on 2-SI-617.
6/2/85 HPSI "B" Header to Loop IB Removed stem nut and installed new i
Injection Valve Motor operator on 2-SI-626.
, 4/23/85 HPSI "A" Header to Loop Replaced MOV with a new MOV and new l
IB Injection Valve Motor stem nut, set limits and adjusted flow.
6/6/85 HPSI HPSI Pump Suction Pipe Replaced missing pipe clamp bolt with j 3/4" x 7" stud and four (4) nuts.
4/24/85 Shutdown Cooling Pipe Hanger #402008 Retorqued bolts on mounting plate to proper torque values.
5/3/85 Containment and Enclosure CTMT Purge Supply Isolation Installed new T-ring and tested.
Building Purge Valve Assy (Inside CTMT) 6/5/85 EBFS Motor Operated Damper Assy Replaced motor operator.
. - . - - - ~ . - . . .- - _ - - - . -. - . ---. - -- --- --
\
Dockst No. 50-336 -
Date 7/15/85 '
Unit Name Millstone 2 -
~
Completed By G. Neron .
l Telephone (203) 447-1791 Extension 4417 CORRECTIVE MAINTENANCE SIM4ARY FOR SAFETY-RELATED EQUIPMENT l
REPORT MONTH June 1985 l
DATE SYSTEM COMPONENT MAINTENANCE ACTION-1 4/9/85 Service Water Underground SVC Water Pipe Applied belzona super metal, grout 16-KE-1 and burlap.
, 6/7/85 Service Water Isolation Valve 2-SW-181A Temporary Weld Repair of Pipe.
l Flange j Isolation Valve 2-SW-1818 Flange Isolation Valve 2-SW-181C Flange 4/17/85 Service Water Inlet Valve 2-SW-3.1B Assy Repaired Manual Operator by making new clutch mechanism.
! 6/19/85 Service water. Inlet Valve 2-SW-3.1B Assy. Installed new dual valves, attached l sealtight. Made up air fittings, lugged wires and added C-fittings w/ covers. Ring terminals bolted tight and tapped. Covers installed.
l 4/22/85 Service Water Stop Valve 2-SW-3.2A Assy. Remounted connection box, two limit l switches, two solenoid valves and replaced a 3/4" elbow. Installed valve 2-SW-3.2A and piping.
4/23/85 Service Water Stop Valve 2-SW-3.28 Assy. Replaced wire between terminal box and solenoid.
,- - - n. . , ,
Dock;t No. 50-336 -
Date 7/15/85 .
Unit Name Millstone 2 -
Completed By G. Neron Telephone 1203)447-1791 Extension 4417 CORRECTIVE MAINTENANCE
SUMMARY
FOR SAFETY RELATED EQUIPMENT REPORT MONTH June 1985 DATE SYSTEM COMPONENT MAINTENANCE ACTION 5/5/85 Service Water Stop Valve 2-SW-55A Replaced valve.
6/3/85 Service Water Stop Valve 2-SW-8A Installed new gasket and retightened flange.
4/13/85 Service Water Discharge Pipe Header from Installed new cross tie between SW Pumps (Above Ground) 2-SW-17A and 2-SW-97B.
3/19/85 Service Water Discharge Pipe from SW Pumps Pad welded eroded area and (Above Ground) repainted.
4/23/85 Service Water Discharge Pipe from SW Pumps Modified studs to "6". Cut old studs (Above Ground) - Flange off and removed them. Reconnected lines using new gaskets.
6/5/85 Service Water SW Outlet Pipe 24-JGD-6 Performed weld repair on 24-JGD-6.
4/24/85 RBCCW "C" RBCCW Pump Motor Cleaned motor, redrilled lower pump i side bearing for RTD. Filled both
) bearings with oil.
- 4/28/85 RBCCW "B" Heat Exchanger Removed shellfish shells from heat i exchanger.
l l
l l
Docket No. 50-336 .
Date 7/15/85 .
Unit Name Millstone 2 .
Completed By G. Neron Telephone (203) 447-1791
. Extension 4417 CORRECTIVE MAINTENANCE St# MARY FOR SAFETY RELATED EQUIPMENT REPORT MONTH June 1985 DATE SYSTEM COMPONENT MAINTENANCE ACTION 4/14/85 RBCCW "C" Heat Exchanger Plugged one tube.
5/14/85 RBCCW Inlet Valve 2-RB-28.1A Af ter testing T-ring was adjusted.
5/11/85 RBCCW Outlet Valve 2-RB-28.2A After testing T-ring was adjusted.
' Outlet Valve 2-RB-28.2C Outlet Valve 2-RB-28.3A 3/28/85- R8CCW Outlet Valve 2-RB-28.38 Assy. Adjusted T ring. '
l 3/26/85 RBCCW Relief Valve 2-RB-314 Disassembled valve, replaced disc, machined seat, reassembled and set at 150 psig lift.
l 3/23/85 R8CCW Drain Valve 2-RB-898 Disassembled bonnet and reassembled with new bonnet gasket. ,
6/2/85 Aerated Liquid Radwaste Isolation Valve 2-SSP-16.1 Disassembled, cleaned internals and inspected disc and seat.
4/24/85 Gaseous Radwaste Isolation Valve 2-GR-11.2 Lapped valve to seat, replaced Assy. diaphragm and replaced flex gasket.
Dock;t No. 50-336 -
Date 7/15/85
- Unit Name Millstone 2 -
Completed By G. Neron Telephone (203) 447-1791 .
Extension 4417 CORRECTIVE MAINTENANCE
SUMMARY
FOR SAFETY RELATED EQUIPMENT REPORT MONTH June 1985 DATE SYSTEM COMPONENT MAINTENANCE ACTION 6/20/85' Station Elec. Service 24G to 24C Feeder Breaker Disassembled trip latch mechanism.
4.16 KV (A302) Cleaned, lubricated and reassembled.
Adjusted depth of set screw in tripper shaft.
3/20/85 Station Elec. Service Breaker - Diesel Generator Overhauled ML-13 operating device 4.16 KV 15G-130-2 (A401) and replaced 13 bushings (2 TUF-LOC) ;
with new aluminum-bronze bushings.
Cleaned and lubed moving parts.
3/23/85 Station Elec. Service Breaker - Safety Injection Cleaned and replaced TUF-LOC 4.16 KV Pump 2403-2 (A404) bushings with al-bronze bushings.
l 3/20/85 Station Elec. Service Breaker - RBCCW Pump 24D1-2 Cleaned and replaced TUF-LOC I 4.16 KV (A402) bushings with al-bronze bushings.
4/13/85 Station Elec. Service Breaker - Aux Feed Pump Readjusted pick-up of relay coil.
4.16 KV 24D5-2 (A406) 3/23/85 Station Elec. Service Breaker - SVC Wtr Pump Disassembled, cleaned and replaced 4.16 KV 2406-2 (A407) all TUF-LOC bushings with brass bushings.
L I
i
Docket No. 50-336 .
Date 7/15/85 -
Unit Name Millstone 2 .
Completed By G. Neron Telephone (203) 447-1791 Extension 4417 CORRECTIVE MAINTENANCE SUM 4ARY FOR SAFETY RELATED EQUIPMENT l
REPORT MONTH June 1985 ,
1 DATE SYSTEM COMP 0NENT MAINTENANCE ACTION l 3/22/85 Station Elec. Service Breaker - 24D to 24E Tie Lubricated elevator mechanism and
' 4.16 KV 240-2T-2 (A408) adjusted drive wheel of elevator motor.
3/22/85 Station Elec. Service Breaker - Bus 24D to 22F Disassembled, installed new bushings.
l 4.16 KV 4160/480 Xfmr Feeder 24D7-2 l- (A409) 3/21/85 Station Elec. Service Bus 24B to 24D Tie 240-1T-2 Replaced all TUF-LOC bushings with l 4.16 KV (A410) Al-Bronze bushings.
l l 3/23/85 Station Elec. Service Bus 24G to 24D Feeder Cleaned out metal shavings and j 4.16 KV Breaker 2253-24D-2 (A411) replaced bushings.
i l 6/13/85 Station Elec. Service Breaker - PSB SVC Water Pump Cleaned, lubricated and reassembled l 4.16 KV 24El-2 (A502) trip latch assembly.
l i 4/4/85 Station Elec. Service Breaker - RBCCW Pump 24E3-2 Replaced TUF-LOC bushings with l
4.16 KV (A504) Al-Bronze bushings.
3/28/85 Station Elec. Service Breaker - RBCCW Pump 24E3-2 Replaced broken fuse holder in 4.16 KV (A504) 4.16 KV cabinet, breaker A504.
, 4/5/85 Station Elec. Service Breaker - Bus 24F to 24E Tie Cleaned and replaced bushings.
l 4.16 KV 2153-24E-2 (A505)
Dockst No. 50-336 -
Date 7/15/85 ,
Unit Name Millstone 2- ,
Completed By G. Neron Telephone (203) 447-1791 Extension 4417 CORRECTIVE MAINTENANCE St# NARY FOR SAFETY RELATED EQUIPMENT REPORT MONTH June 1985 l -
DATE SYSTEM COMPONENT MAINTENANCE ACTION i-l' 4/5/85 Station Elec. Service Breaker - Bus 24F to 24E Lubricated mechanism.
i 4.16 KV Feed (A602)
I-3/8/85 Station Elec. Service Breaker - Spare, S/N Welded striker plate.
4.16 KV 0228A2415-003 i 3/12/85- Station Elec. Service Breaker - Spere, S/N Deburred Al-Bronze bushings, l 4.16 KV 0228A2415-003 cleaned and reassembled with ...
l 11 new Al-Bronze bushings.
l 2/20/85 480 V Load Centers Breaker - F14B C. A.R. Fan Straightened track lock link.
L (B0605) i j 3/9/85 480 V Load Centers Breaker - DC2 "B" DC Split breaker, installed new/
f Battery Bus Battery Charger rebuilt EC-2A series overcurrent-l, (80607) devices, cleaned and lubricated.
! 6/20/85 125 Volt DC "B" 125 Volt DC Station Cut end rail of battery rack to l Battery adjust clearance approx. " for l cell #12 and #43. Adjusted end ;
i rail of cell #13 and #42.
4/23/85 ESAS Channel "D" Stop Valve Removed bonnet and plug, lapped 2-AC-99 plug and seat, installed bonnet with new flex gasket.
4 l
l l-
. Docket No. 50-336 Date: 7/15/85 Completed By: G. Neron Telephone: (203) 447-1791 Extension 4417 REFUELING INFORMATION REQUEST
- 1. Name of facility: Millstone 2
- 2. Scheduled date for next refueling shutdown: September 1986
- 3. Schedule date for restart following refueling: N/A
- 4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
N/A
- 5. Scheduled date(s) for submitting licensing action and supporting information:
A. Technical support information for reracking the spent fuel pool will be submitted approximately July 31, 1985 to support a proposed license ammendment.
- 8. Results of the sleeving and plugging of the steam generator tubes was submitted to the NRC on June 18, 1985.
- 6. Important licensing considerations associated with refueling, e.g.,
new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:
None.
- 7. The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool:
(a) In Core: 217 (b) 449
- 8. The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:
Currently 667 Plans are being formulated to rerack the spent fuel pool beginning in August 1985, to increase the storage capacity to 1106 fuel assemblies.
- 9. The' projected date of the last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:
1965, Spent Fuel Pool, Full core off load capacity is reached.
1987, Core Full, Spent Fuel Pool contains 648 bundles.