Application for Amend to License DPR-6,adding New Air Compressor to Svc Air Segment of Svc & Instrument Air Sys
ML20134H628
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 11/07/1996
From: Addy R
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20134H630 List:
References
NUDOCS 9611140193
Download: ML20134H628 (4)


Text

--

.c Consumers Power Patrick M Donnelly Plant Manorer hiWJNGAN's NEDGetES$

Beg Rock Point Nuclear Plant,10269 US 31 North, Charlevoix, MI 49720 November 7, 1996 i

Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 4

DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT - TECHNICAL SPECIFICATION CHANGE REQUEST - ADDITION OF A 100 SCFN AIR CONPRESSOR TO THE SERVICE AND INSTRUNENT AIR SYSTEN.

A request for change to the Big Rock Point Technical Specifications is enclosed.

A recent modification has added a new air compressor to the service air segment of the Service and Instrument Air System.

This modification was performed to increase instrument air capacity by eliminating service air demands on the three existing air compressors. The new air compressor can also be aligned to provide j

air to the instrument air system in the event off a loss of normal instrument

air, i

i In accordance with 10 CFR 50.92, Consumers Power Company has made a determination that the proposed amendment involves no significant hazards considerations TbetJAddy Assistant Plant Manager CC: Administrator, Region III, USNRC NRC Resident Inspector - Big Rock Point g

ATTACHMENT q

9611140193 961107

(

PDR ADOCK 05000155 i

p PDR A CM5GV672GYCOMPANY

CONSUMERS POWER COMPANY DOCKET 50-155 Request for Change to the Technical Specifications License DPR-6 For the reasons hereinafter set forth, it is requested that the Technical Specifications contained in the Facility Operating License DPR-6, Docket 50-155, issued to Consumers Power Company on May 1, 1964, for the Big Rock Point Plant be changed as described in Section I below:

Revised Technical Specification pages are attached. Proposed changes are shown by a back-slash in the right-hand margin.

I.

CHANGES

1) Revise Technical Specification 4.2.9 to read:

Service and Instrument Air System Service and instrument air shall be supplied by three, nonlubricated air compressors, each rated at 70 scfm and one, nonlubricated air compressor, rated at 100 scfm. Instrument air shall also pass through a dryer.

II. DISCUSSION Facility Change FC-648C adds a new 100 standard cubic feet per minute (scfm) air compressor to the service air portion of the Service and Instrument Air System.

This addition allows the instrument air portion to be completely isolated from j

the service air portion of the Service and Instrument Air System.

Isolation of 1

instrument air from service air increases instrument air's available capacity by eliminating service air demands from the three (3) existing 70 scfm air compressors. Utilizing the existing piping configuration and cross-connect, both i

the new and the existing air compressors are capable of supporting the Service and Instrument Air System as determined necessary by the Operations Department.

Air quality will be unchanged by the addition of the new air compressor regardless of how the air compressors are placed into operation.

The new air compressor has similar design characteristics as the existing air compressors and the instrument air piping is essentially unchanged.

III. ANALYSIS OF NO SIGNIFICANT HAZARDS CONSIDERATION In accordance with 10 CFR 50.92, Consumers Power Company has made a determination i

that the proposed amendment involves no significant hazards considerations. To i

make this determination, Consumers Power Company has established that operation in accordance with the proposed amendment will not : 1) involve a significant j

increase in the probability or consequences of an accident previously evaluated, or 2) create the possibility of a new or different kind of accident from any accident previously evaluated, or 3) involve a significant reduction in a margin of safety.

The proposed change does not:

1) Involve a significant increase in the probability or consequences of an accident previously evaluated.

Big Rock Point Plant 2

Technical Specification Change Request November 7, 1996 Utilizing the existing piping configuration, both the new and the existing air compressors are capable of supporting either portion of the Service and l

Instrument Air System. The addition of the fourth air compressor will decrease i

the probability of an accident previously evaluated, because capacity is being

.dded to the system.

\\

f The consequences of an accident previously evaluated will not be affected by the

. addition of a fourth air compressor. The Service and Instrument Air System i

performs the non-safety related function of providing compressed air for service use and moisture free compressed instrument air for control air demands. The:

instrument air portion is designed so that its operation is required for plant reliability, not plant nuclear safety. Safety-related equipment supplied by instrument air is designed to fail in its safe condition upon loss of instrument air or, safety-related equipment (and nonsafety-related equipment determined to be important to safety) required to operate subsequent to instrument air failure is suppled by backup nitrogen accumulators.

2) Create the possibility of a new or different kind of accident from any accident previously evaluated.

t The operation of the equipment in the Service and Instrument Air System is essentially unchanged.

The. new air compressor is a

similar. design (nonlubricated), providing additional air volume at a quality comparable to the three existing air compressors. Therefore, the possibility of an accident of a different kind than any previously evaluated has not been created.

l

3) Involve a significant reduction in a margin of safety The Technical Specification does not specify a margin of safety for the operation of the Service and Instrument Air System, other than specifying that " service and instrument air shall be supplied'by three, nonlubricated air compressors, each rated at 70 scfm. Instrument air shall also pass through a dryer". Addition of a fourth air compressor will increase the available capacity, thus increasing the margin of safety. Therefore, adding the statement "and one, nonlubricated air compressor rated at 100 scfm" to Technical Specification 4.2.9. will not reduce the margin of safety.

IV. CONCLUSION The Big Rock Point Plant Review Committee has reviewed this Technical Specification Change Request and has determined this change does not involve an unreviewed safety - question and, therefore, involves no significant hazards

-consideration. This change has been reviewed by the Nuclear Performance Assessment Department. A' copy of this change request has been sent to the State of Michigan official designated to receive such Amendments to the Operating License.

Big Bock Point Plant 3

Technical Specification Change Request l

November 7, 1996 l

l l

l CONSUMERS POWER COMPANY To the best of my knowledge, information and belief, the contents of ' this submittal are truthful and complete.

BM

- U Robert J Addy

- Assistant Plant Manger Sworn and subscribed to before me this 7th day of November 1996.

I 00stdih.

Y1 Mvh.

nniffrLynhHelms,NotaryPublic Charlevoix County, Michigan My commission expires August 29, 1999.

I l