Monthly Operating Repts for Jul 1985
ML20134E927
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 07/31/1985
From: Reavis J
DUKE POWER CO.
To:
Shared Package
ML20134E920 List:
References
NUDOCS 8508200598
Download: ML20134E927 (11)


Text

..

OPERATLNG DATA REPORT DOCKET NO.

50-369 DATE 8-15-85 COMPLETED BY

<T A - naavis

- TELEPHONE 7n4-373-7567 OPERATING STATUS Notes

  • Nameplate Rating
l. Unit Name:

McGuire 1

2. Reporting Period:

July 1. 1985 - Julv 31. 1985 (Gross MWe) calculated as

3. Licensed Thermal Power (MWt):

3411 1450.000 MVA x.90 power 1305*

factor per Page lii,

4. Nameplate Rating (Gross MWe):

NUREG-0020.

1180

5. Design Electrical Rating (Net MWe):
6. Maximum Dependable Capacity (Gross MWe):
7. Maximum Dependable Capacity (Net MWe):

1190

8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

None None

9. Power Level To Which Restricted,if Any (Net MWe):
10. Reasons For Restrictions,if Any:

This Month Yr..to.Date Cumulative

11. Hours in Reporting Period

~744.0 5 087.0 32 135.0

12. Number Of Hours Reactor Was Critical 744.0 3 414.5 21 578.1
13. Reactor Reserve Shutdown Hours
14. Hours Generator On.Line 744.0 3 329.2 21 291.8
15. Unit Reserve Shutdown Hours
16. Gross Thermal Energy Generated (MWH) 2 344 677 9 199 104 56 003 404
17. Gross Electrical Energy Generated (MWH) 803 912 3 132 180 19 361 405 i
18. Net Electrical Energy Generated (MWH) 772 998 2 980 560 18 355 815
19. Unit Service Factor 100.0

'65.5 66.3

20. Unit Availability Factor 100.0 65.5 66.3 l
21. Unit Capacity Factor (Using MDC Net) 88.1 49.7 48.4
22. Unit Capacity Factor (Using DER Net)

RR 1 49.7 48.4

23. Unit Forced Outage Rate 0.0 11.3 15.4
24. Shutdowns Scheduled Over Next 6 Months (Type. Date,and Duration of Each):

None l

25. If Shut Down At End Of Report Period. Estimated Date of Startup:
26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIA L CRITICA LITY INITIAL ELECTRICITY COMMERCIAL OPERATION B508200598 850815 (9/77)

DR ADOCK O g

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-369 UNIT McGuire 1 DATE 8/15/85 COMPLETED BY J.A.

Reavis TELEPHONE 704-373-7567 MONTH July, 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Ne t) 1 517 17 1 133 2

527 18 1 131 3

536 19 1 133 4

538 20 1 134 5

728 21 1 133 6

1 040 22 1 133 l

7 1 132 23 1 134 8

1 132 24 1 134 9

1 119 25 1 134 10 1 133 26 1 129 11 1 131 27 1 133 12 1 127 28 1 141 13-1 129 29 1 139 14 1 131 30 1 140 15 1 132 31 1 141 16 1 133 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.

Compute to the nearest whole megawatt.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.

50-369 UNIT NAME Mccuire i DATE August 15, 1985 REPORT MONTH July, 1985 COMPLETED BY J. A.

Reavis TELEPHONE 704-373-7567 "s.

O gj License Cause & Corrective y

c27 "c

v." 2 No.

Date

~.

% 5; jg, Event h

h Action to o

O.

5-O so 4.a 3 3 mn N 55 E

E5S Report #

NO

$.g Prevent Recurrence 8

24-p 85-07-01 F

A CH PUMPXX Feedwater Pump Turbine Alignment Problem 25-p 85-07-05 S

F RC XXXXXX Power Escalation Testing 26-p 85-07-09 F

B IA INSTRU Adjust Overpower Delta T Circuitry 27-p 85-07-27 S

F CC VALVEX Turbine Governor Valve Testing 1

2 3

4 Reason:

Method:

Exhibit G - Instructions SS led A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)

D-Regulatory Restriction 4-Other (Explain)

File (NUREG-0161)

E-Operator Training 4 License Examination F-Adninistrative 5

G-Operational Error (Explain)

Exhibit I - Same Source H-Other (Explain) 9/77)

a,.n

--,es,

-=_a

el a

w-M

.s

.2 a--

-u.a<

-.4--

J.a,-

a

--n EJ2--'-,

DOCKET NO:

50-369 UNIT:

McGuire 1 DATE:

Augurt 15, 1985 NARRATIVE SUbefARY Month:

July 1985 J

McGuire Unit 1 began the month at 52% power with a feedpump out of service.

The pump was placed in service and the unit returned to 100% on July 6 where it operated for the balance of the month.

W d

l i

y

MONTHLY REFUELING INFORMATION REQUEST 1.

Facility name:

McGuire Unit 1 2.

Scheduled next refueling shutdown:

June. 1986 3.

Scheduled restart following refueling:

Aunust. 1986 4.

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

Yes If yes, what will these be?

Technical Specification Revision If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

N/A 5.

Scheduled date(s) for submitting proposed licensing action and supporting information:

N/A 6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).

7.

Number of fuel assemblies (a) in the core:

193 (b) in the spent fuel pool:

152 8.

Present licensed fuel pool capacity:

1463 Size of requested or planned increase:

9.

Projected date of last refueling which can be accommodated by present licensed capacity: Aucust 2010 DUKE POWER COMPANY Date: Aunust 15, 1985 Name of

Contact:

J. A. Reavis Phone: 704-373-7567

_. =-_

OPERATLNG DATA REPORT DOCKET NO.

50-370 DATE 8-15-85 COMPLETED BY J.A. Reavis TELEPHONE 7nd-373-7567 OPERATING STATUS 1

Notes

  • Nameplate Rating
1. Unit Name:

McGuire 2 (Gross MWe) calculated as

2. Reporting Period:

July 1. 1985-Julv 31. 1985 1450.000 MVA x.90 power

3. Licensed Thermal Power (MWt):

3411 factor per Page lii, 1305*

4. Nameplate Rating (Gross MWe):

NUREG-0020.

1180

5. Design Electrical Rating (Net MWe):
6. Maximum Dependable Capacity (Gross MWe):

1180

7. Maximum Dependable Capacity (Net MWe):
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:

None None

9. Power Level To Which Restricted,if Any (Net MWe):
10. Reasons For Restrictions. If Any:

1 This Month Yr..to Date Cumulative

11. Hours in Reporting Period 744.0 5 087.0 12 431.0
12. Number Of Hours Reactor Was Critical 350.3 2 184.8 8 323.0
13. Reactor Reserve Shutdown Hours
14. Hours Generator On Line 281.8 2 039.2 8 130.2
15. Unit Reserve Shutdown Hours s
16. Gross Thermal Energy Generated (MWH) 949 838 6 592 515 25 963 186
17. Gross Electrical Energy Generated (MWH) 326 022 2 313 748 9 151 471
18. Net Electrical Energy Generated (MWH) 303 645 7 141 164 R 740 160
19. Unit Service Factor 37.9 40.1 65.4
20. Unit Availability Factor 37.9 40.1 65.4 l
21. Unit Capacity Factor (Using MDC Net) 34.6 36.5 59.7
22. Unit Capacity Factor (Using DER Net) 34.6 36.5 59.7
23. Unit Forced Outage Rate 62.I 43.0 25.0
24. Shutdowns Scheduled Over Next 6 Months (Type.Date,and Duration of Each):

None

25. If Shut Down At End Of Report Period. Estimated Date of Startup: Auenst 2.

1985

26. Units in Test Status iPrior to Commercial Operation):

Forecast Achieved INITIA L CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION (4/77) c

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

50-370 UNIT McGuire 2 DATE 08/15/85 COMPLETED BY J.A.

Heavis TELEPHONE 704-373-7567 MONTH July, 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Ne t)

(MWe-Ne t) 1 1 146 17 2

1 148 18 3

1 149 19 4

1 149 20 5

1 150 21 6

1 150 22 7

1 150 23 8

1 148 24 9

1 147 25 10 1 147 26 11 1 146 27 12 270 28 69 13 29 33 14 30 15 31 16 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.

Compute to the nearest whole megawatt.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.

50-370 UNIT NAME McGuire 2 DATE August 15, 1985 REPORT MONTH July, 1985 COMPLETED-BY J. A Reavis TELEPHONE 704-373-7567 o

o o,$

License y

Cause & Corrective e32 "c

a5E No.

Date

~.

jg Event

,Be, h

Action to o

S Report #

$'b

$b Prevent Recurrence o

Ge' erator Phase Dif ferential X-Phase, 5

85-07-12 F

381.62 A

3 HA INSTRU n

Channel 1 Relay Actuation 6

85-07-28 F

11.37 A

1 HA TURBIN Fan Shaft Vibration 7

85-07-29 F

69.17 A

3 HA INSTRU Generator Phase Differential, X-Phase, Channel 1 Relay Actuation 1

2 3

4 Reason:

Method:

Exhibit G - Instructions F

e 3

yg A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)

D-Regulatory Restriction 4-Other (Explain)

File (NUREG-0161)

E-Operator Training 4 License Examination F-Mninistrative S

G-Operational Error (Explain)

Exhibit I - Same Source H-Other (Explain) p/~7)

i

=

s e

DOCKET NO:

50-370 UNIT:

McGuire 2 DATE:

August 15, 1985 NARRATIVE

SUMMARY

Month: July 1985 McGuire 2 began the month at 100% power. The unit tripped on July 12 due to a generator phase differential. The unit returned to service on July 28, but was taken off-line because of shaft. vibration.

It was placed in service later that day but tripped on July 29 because of a generator phase differential and remained off line through the end of the month.

H

MONTHLY REFUELING INFORMATION REQUEST 1.

Facility name:

McGuire Unit 2 2.

Scheduled next refueling shutdown:

April. 1986 3.

Scheduled restart following refueling:

June. 1986 4.

Will refueling or resumption of operation thereaf ter require a technical specification change or other license amendment? Yes If yes, what will these be?

Technical Specification Revision If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions? N/A

5. ' Scheduled date(s) for submitting proposed licensing action and supporting information:

N/A 6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).

7.

Number of fuel assemblies (a) in the core:

193 (b) in the spent fuel pool:

60

,t' 8.

Present licensed fuel pool capacity:

1463 Size of requested or planned increase:

9.

Projected date of last refueling which can be accommodated by present licensed capacity:

Anonst 2010 DUKE POWER COMPANY Date:

August 15. 1985 Name.of

Contact:

J. A. Reavis Phone: 704-373-7567 i

r McGUIRE NUCLEAR STATION Monthly Operating Status Report

\\

1.

Personnel Exposure For the month of June, 3 individuals exceeded 10 percent of their allowable annual radiation dose limit with the highest dose being 1.360 Rem, which represents approximately 11.3% of that person's allowable annual limit.

2.

The total station liquid release for June has been compared with the Technical Specifications maximum annual dose commit-ment and was less than 10 percent of this limit.

The total station gaseous release for June has been compared with the Technical Specifications maximum annual dose commit-ment and was less than 10 percent of this limit.

[

,