Twelfth Interim Deficiency Rept Re Seismic Qualification of B&W Equipment in TVA Panels.Initially Reported on 801124. Results from Transmitters Sent to Wyle Labs for Retesting Expected by 850801.Next Rept Will Be Submitted by 851015
ML20133P109
Person / Time
Site: Bellefonte  Tennessee Valley Authority icon.png
Issue date: 07/02/1985
From: Hufham J
TENNESSEE VALLEY AUTHORITY
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8508140155
Download: ML20133P109 (2)


Text

.

TENNESSEE VALLEY AUTHORITY CH ATTANOOG A. TENNESSEE 37401 1630 Chestnut Street Tower II July 2, 1985 u

U.S. Nuclear Regulatory Commission n.

Region II

j Attn

Dr. J. Nelson Grace, Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 a

Dear Dr. Grace:

c.o BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 - SEISMIC QUALIFICATION OF B&W W C1 C - 2 EQUIPMENT IN TVA PANELS - NCR BLN BLP 8011 - TWELFTH INTERIM REPORT Cry The subject deficiency was initially reported to NRC-0IE Inspector R. W. Wright on November 24, 1980 in accordance with 10 CFR 50.55(e).

This was followed by our interim reports dated December 23, 1980 and April 23 and October 28, 1981, February 18, May 18, July 16, and September 24, 1982, February 7 and September 7,1983, and June 28 and December 17, 1984. Enclosed is our twelfth interim report. We expect to submit our next report on or about October 15, 1985.

If you have any questions concerning this matter, please get in touch with R. H. Shell at FTS 858-2688.

Very truly yours, TENNESSEE VALLEY AUTHORITY dmi-t G. W. Hufham, Manager Licensing and Risk Protection Enclosure cc (Enclorare):

Mr. James Taylor, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Mr. H. B. Barkley 205 Plant Project Services P.O. Box 10935 Lynchburg, Virginia 24506-0935 Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 l

Atlanta, Georgia 30339 egeigg68RBi8]p{ge g

S An Equal Opportunity Employer g

.~

a u

ENCLOSURE BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 SEISMIC QUALIFICATION OF B&W EQUIPMENT IN TVA PANELS-NCR BLN BLP 8011 10 CFR 50.55(e)

TWELFTH INTERIM REPORT Description of Deficiency A number of Babcock and Wilcox (B&W) supplied instruments are intended for installation on TVA's freestanding, open, local instrument panels. Because of imprecise specifications in a TVA procurement document, the instrumentation listed below and supplied by B&W has not been seismically qualified to a response spectra which is compatible with the response spectra for TVA local instrument panels. Consequently, the responsibility for this deficiency is TVA's.

A list of the instruments to be qualified follows:

Type of Device Vendor Vendor ID No.

Differential pressure transmitter Bailey Meter Co.

Type N1BQ86221 Differential pressure transmitter Bailey Meter Co.

Type N2BQ74221 Differential pressure transmitter Bailey Meter Co.

Type N2BQ76221 Differential pressure transmitter Bailey Meter Co.

Type N2BQ85221 Differential pressure transmitter Bailey Meter Co.

Type N2BQ86221 Pressure transmitter Bailey Meter Co.

Type N2KS69221 Indicator meter Bailey Meter Co.

ES-342 Operator station Bailey Meter Co.

TT-10 Interim Progress As reported in our previous responses, the equipment in question was seismically tested to the higher "g" values of the correct response spectra.

The results showed that all equipment is qualified except the N2BQ74221 and N2BQ86221 transmitters and the TT-10 operator station. A contract was set up with Wyle Laboratory to retest the three devices. The results of Wyle's test are scheduled to be submitted to TVA on August 1,1985. TVA must evaluate these results and determine if the devices successfully passed the seismic test and are seismically qualified.

)

.