COMANCHE PEAK STEAM ELECTRIC STATION 4

EMERCENCY PLAN MANUAL l

w. _w

}

PROCEDURE INDEX CO M OL

($

o 0 73 s

VOLUME II l

REVISION 29 se O "'Y h

PAGE 1 0F 2 63 fv.

x1:NT Cot Procedure No.

Revision No.

Procedure Title v ew Date

  • EPP-204 4

Activation of the TSC and October, 1986

)

TSC Personnel Duties 1

  • EPP-205 3

Activation of the Operations August, 1986 Support Center and Operations Support Center Personnel Duties l

l

  • EPP-206 3

Activation of the Emergency August, 1986 Operations Facility (EOF) and l

EOF Personnel Duties i

  • EPP-207 3

Activation of the News Center October, 1986

{

/

and Personnel Duties

  • EPP-208 5

Access Control During September, 1986 Emergency Conditions t

  • EPP-209 1

Personnel Assembly &

July, 1986 Accountability 1

  • EPP-210 5

Evacuation August, 1986 j

  • EPP-211 1

Release of Toxic Material Proc. Retired i

l

  • EPP-212 1

Release of Information to the Proc. Retired Public

)

  • EPP-300 2

Manual Calculation of Release January, 1986 Rates

  • EPP-301 1

Computer Assessment of August, 1986 Radiological Conditions

  • EPP-302 3

Manual Assessment of Radio-January, 1986 logical Conditions 0

!V g]3A6 i

n I

8510300011 US 445 g

PDR ADOCK O pg F

COMANCHE PEAK STEAM ELECTRIC STATION EMERGENCY PLAN MANUAL PROCEDURE INDEX VOLUME II REVISION 29 PAGE 2 0F 2 Procedure No.

Revision No.

Procedure Title Review Date

  • EPP-303 2

Micro-Computer Based.

July, 1986 Emergency Dose Assessment

  • EPP-304 6

Protection Action Guides May, 1986

  • EPP-305 4

Exposure Guidelines and July, 1986 Personnel Dosimetry During Emergency Conditions

  • EPP-306 5

Use of Thyroid Blocking Agents February, 1986 e

  • EPP-307 3

Radiological Monitoring of August, 1986 Site Evacuees

  • EPP-308 4

Transporting Contaminated January, 1986 Injured Personnel

  • EPP-309 5

Offsite Radiological October, 1986 Monitoring

  • EPP-310 3

On-Site and In-Plant October, 1986 Radiological Surveys

,r 's

~

i i

,i COMANCHE PEAK STEAM ELECTRIC STATION EMERGENCY PLAN MANUAL I

l

]

r ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) t AND l

TSC PERSONNEL DUTIES i G V

1 f

PROCEDURE NO. EPP-204 j

REVISION NO. 4 i

n I?

P..s,f.,s 7,,

f.il.

"T,, i.t.

i 6

6.

d)h,.3 L H ll"n!s Lf E U,7 CPSES '

c I

/

con ract

/

\\

i

-z o

0 73 5

1 4

e

\\o COPY-JI

%'JNT COTp'.

i i

--[0-((

I SUBMITTED BY:

)

DATE:

l SUPERINTENDEN, SUP. ORT SERVICES 1

APPROVEDBY:(

M t/ 24v DATE: /d - /[cf l

j

MANAUER, CLEAR OPERATIONS I

4

m.

i i

i

. CPSES ISSUE DATE PROCEDURE NO.

i EMERGENCY PLAN MANUAL MT1R' g EPP-204

{

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 2 0F 26 i

1.0 Purpose L

)

This procedure provides instructions for the activation of the l

l Technical Support Center (TSC). This procedure also identifies the i

required actions, responsibilities, authorities and interfaces of those personnel assigned to the TSC.

j 2.0 Applicability This procedure shall be initiated following the declaration of an

)

];!

Alert, a Site Area Energency or General Emergency at CPSES. This i

procedure is applicable to the TSC Manager and his staff. During an emergency condition classified as a Notification of Unusual Event, the Emergency Coordinator at his discretion, may direct activation of the i

TSC.-

j This procedure becomes effective when issued.

i 3.0 Definitions

[

i f

3.1 Technical Support Center - The TSC is the onsite emergency i

response facility located in close proximity to the Control Room 3

I that shall provide plant management and technical support to Control Room personnel during an emergency condition at CPSES.

The TSC is equipped with technical data displays, plant records and other documents to assist TSC personnel in the detailed analysis and diagnosis of abnormal plant conditions and any releases of radioactivity to the environment. The TSC shall be the primary communications center for the plant during an emergency. At CPSES, the TSC is located in the classroom and office areas above the Control Room, at elevation 840'-6" of the i

l Electrical and Control Building. The TSC is provided with the j

same habitability conditions as the Control Room. An example of i

the TSC layout for emergencies is illustrated in Attachment 2 to j

this procedure.

4.0 Instructions l

4.1 Precautions 4.1.1 The names of personnel assigned specific duties and responsibilities according to this procedure are listed in l

EPP-203, " Emergency Communications". These individuals i

make up the nucleus of the CPSES emergency response.

If required, emergency organization personnel may be sup-piemented under the provisions of procedures EPP-208 and EPP-209.

O i

-._-_-_,.v.,..~_,---,-__-,--.___.__.--

.,,. -. _ _, _., _. _, _. -,,. _, _ _ _ _ - _,. _ _.., ~... -

i CPSES ISSUE W PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT 18 mm EPP-204 l

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 3 0F 26 17 4.2 Facility Activation 4.2.1 If conditions warrant activation of the TSC, either an Alert or higher class emergency or at the discretion of the Emergency Coordinator, the following shall be met in order to declare the facility operational:

4.2.1.1 Minimum staffing and function requirements:

I a.

Management Representative - Facility i

Management b.

Engineering Representative - Technical Evaluations c.

Operations Representative - Operations Evaluations d.

Maintenance Representative - Maintenance Functions e.

Radiation Protection Representative -

Radiological Evaluations f.

TSC Communicator - Communications 4.2.1.2 Complete the TSC Checklist, Form EPP-204-1.

NOTE:

Form EPP-204-1 should be used to document / verify proper staffing after shift changes.

4.2.1.3 Compliance with these conditions should not exceed sixty (60) minutes f rom the declaration of an Alert or higher class emergency.

4.3 Technical Support Center (TSC) Personnel Duties 4.3.1 Technical Support Center Manager 4.3.1.1 The individuals designated to assume this position upon activation of the TSC (in descending order of succession):

4.3.1.1.1 Manager, Plant Operations 4.3.1.1.2 Engineering Superintendent 4.3.1.1.3 Operations Superintendent 4.4.1.1.4 Maintenance Superintendent.

4.3.1.2 Responsibilities:

4.3.1.2.1 Contact the on-duty Shift Supervisor (Emergency Coordinator) to obtain

CPS E'S 0 S{}g gggj.

PROCEDURE NO.

EPP-204 EMERGENCY PLAN MANUAL ll ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 4 0F 26 information regarding th( plant status and the status of onsite and offsite emergency response activities.

4.3.1.2.2 In addition to assuming the duties of the TSC Manager, assume duties of the Emergency Coordinator if the E0F has not been activated as specified in Procedure EPP-109, until such time as:

a.

The event is closed out, or b.

The Recovery Organization is formed (EPP-121), or c.

The EOF Manager is prepared to accept the duties of the Emergency Coordinator.

4.3.1.2.3 Complete the TSC Checklist form EPP-204-1.

,e~x Ik-4.3.1.2.4 Control access to the TSC.

If additional personnel are needed for the facility, refer to procedure EPP-208, " Access Control During Emergency Conditions".

4.3.1.2.5 Verify the activation of the Opera-tions Support Center (OSC).

4.3.1.2.6 Check notifications of State and local authorities and other agencies in accordance with EPP-203, " Emergency Notification".

4.3.1.2.7 Assume control of the direction and coordination of all onsite activities conducted from the TSC, including:

a.

The establishment of proper communications with the Control Room, OSC, EOF, and other emerg-ency response facilities and coordination of all emergency response ' activities condu'eted 7'~'3 within the Protected Area.

/

b.

The determination of the severity of the emergency conditions and

CPSE5 ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT 181985 EPP-204 ACTIVATION OF THE TECHNICAL SUPPORT g

CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 5 0F 26 the current status of onsite emergency response activities, c.

Review of key plant manipulations.

4.3.1.2.8 Verify that all TSC emergency response functions are being performed.

4.3.1.2.9 Relieve the Control Room personnel of any administrative functions and decisions that are not directly 4

related to the safe shutdown of the station.

4.3.1.2.10 Interface with the Onsite Radiological Assessment Coordinator to evaluate changes in plant status for potential offsite radiological consequences.

4.3.1.2.11 Ensure coordination of activities conducted from the TSC with those activities conducted from the EOF.

4.3.1.2.12 Interpret plant technical information as required.

4.3.1.2.13 Initiate personnel rescue or emergency repair and damage control operations as appropriate.

4.3.1.2.14 Provide input to the NRC represent-ative stationed at the TSC regarding plant operating license requirements.

4.3.2 Maintenance Coordinator 4.3.2.1 The individuals designated to assume this position upon activation of the TSC are (in descending order of succession):

4.3.2.1.1 Maintenance Superintendent 4.3.2.1.2 Maintenance Engineer 4.3.2.1.3 Electrical Maintenance Engineer.

4.3.2.2 Responsibilities:

G 4.3.2.3.2 Coordinate and direct emergency repair and damage control activities through

CPSE'S f

PROCEDURE NO.

OC,SfY'MbE EPe-204 EMERGENCY PLAN MANUAL O

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 6 0F 26 the OSC Supervisor.

4.3.2.3.3 Advise the OSC Supervisor of any changes in plant conditions which may affect emergency repair and damage control activities.

4.3.2.2.4 Advise the TSC Manager and other TSC personnel regarding the status of onsite emergency repair and damage control activities.

4.3.3 Operations Coordinator 4.3.3.1 The individuals designated to assume this position upon the activation of the TSC are (in descending order of succession):

4.3.3.1.1 Operations. Superintendent 4.3.3.1.2 Operations Engineer

(

)

't /

4.3.3.1.3 Operations Supervisor.

4.3.3.2 Responsibilities:

4.3.3.3.1 Advise the TSC Manager and other TSC personnel regarding plant conditions and operational manipulations.

4.3.3.3.2 Evaluate the effects of proposed operational manipulations.

4.3.3.3.3 Coordinate with the Operations Advisor.

4.3.3.3.4 Interface with the Maintenance Coordinator and the Engineering Team Coordinator.

4.3.3.3.5 Ensure that the Operational Statur Sheet, EPP-204-2 (Attachment 3), is completed in a timely manner, and establish and maintain a file of completed forts.

('"x, 4.3.4 Engineering Team Coordinator

\\

/

4.3.4.1 The individuals designated to assume this

ISSU PROCEDURE NO.

OCT 1) L CPSES O

l EPP-204 EMERGENCY PLAN MANUAL l

)

ACTIVATION OF THE TECHNICAL SUPPORT

' l'. * -

CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 7 0F 26 position upon the activation of the TSC are (in descending order of succession):

4.3.4.1.1 Engineering Superintendent 4.3.4.1.2 Results Engineering Supervisor 4.3.4.2 Responsibilities:

4.3.4.2.1 Direct and coordinate the efforts of the TSC Engineering Team.

4.3.4.2.2 Verify that emergency response engineering support personnel with TSC assignments are in position or have been notified and are proceeding to the TSC.

4.3.4.2.3 Advise the TSC Hanager on technical matters relating to the NSSS, fuel integrity, plant systems and 9

equipment, plant electrical systems and electrical systems and equipment, and plant instrumentation.

4.3.4.2.4 Perform an independent assessment of critical plant parameters.

4.3.4.2.5 Coordinate any TUGC0 requests for technical assistance and support from within the Texas Utilities System or from outside organizations.

4.3.4.2.6 Direct requests for outside assistance to Engineering Support Coordinator at the EOF when the EOF is activated.

4.3.5 TSC Engineering Team 4.3.5.1 The TSC Engineering Team shall be composed of four (4) members with general knowledge in the following areas:

4.3.5.1.1 Mechanical Engineering 4.3.5.1.2 Instrument and Controls Engineering O

( )

4.3.5.1.3 Electrical Engineering

CPSEis ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT 181985 EPP-204 ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 8 0F 26 4.3.5.1.4 Nuclear Engineering 4.3.5.1.5 Operations.

4.3.5.2 Responsibilities:

NOTE: The responsibilities described may be performed by individuals or by the entire team.

4.3.5.2.1 Trend and evaluate current and historical plant parameters.

4.3.5.2.2 Assess the severity of the emergency conditions.

4.3.5.2.3 Estimate time available to perform critical actions or before crucial parameters are exceeded or vital equipment is lost.

4.3.5.2.4 Prepare plant trend data and formulate

's actions based on the trend data.

4.3.5.2.5 Recommend corrective or preventative actions to the Engineering Team Coordinator.

4.3.5.2.6 Provide time estimates for the perforeances of repair activities to place vital equipment back in se rvice.

4.3.5.2.7 Provide Engineering Support to Control Room and TSC Emergency Organization Groups.

4.3.5.2.8 As appropriate, prepare messages for

~

the Nucicar Network System and transmit the messages to the Nuc1 car Network operator at the EOF.

4.3.6 Onsite Radiologien1 Assessment Coordinator 4.3.6.1 The individual designated to assume this position upon activation of the TSC is a member of the Nucicar Operations or Plant Staf f who in CN trained and has experience in Hcalth Physics.

()

CPSES ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT 181985 EPP-204

{

ACTIVATION OF THE TECHNICAL SUPPORT CENIER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PACE 9 0F 26 4.3.6.2 Responsibilities:

4.3.6.2.1 Initiate operation of the iodine monitor and area radiation monitor.

NOTE:

If either monitor alarms or if it fails or is suspect, initiate the actions specified in Section 4.5.

4.3.6.2.2 Direct the issue and collection of additional dosimetry to TSC and Control Room personnel, if required.

4.3.6.2.3 Ensure the radiological safety of all emergency response personnel working within the Protected Area.

4.3.6.2.4 Coordinate the activities of the TSC Radiation Monitoring System (RMS)

Computer Operators Field Teams O

Communicator, Onsite Survey Teams Director and the Chemistry Supervisor at the OSC.

4.3.6.2.5 Direct and coordinate all radiological-related emergency response activities prior to the activation of the EOF.

4.3.6.2.6 Ensure that emergency sampling and radiological survey procedures are being properly implemented.

4.3.6.2.7 Review, and evaluate data concerning in-plant and on-site radiological conditions and distribute to the appropriate personnel as' required.

4.3.6.2.8 Ensure that the in-plant use of protective clothing and respiratory protection, and access control measures are properly implemented.

4.3.6.2.9 Ensure that appropriate bionssay procedures have been implemented for

(~]

onsite personnel.

LJ

CPSE'S ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT 181985 EPP-204 O

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES nEVISION NO. 4 PAGE 10 0F 26 4.3.6.2.10 Ensure that personnel radiation exposures are maintained in accordance with CPSES administrative limits unless otherwise authorized by the Emergency Coordinator.

4.3.6.2.11 Ensure that personnel are properly decontaminated, if necessary.

4.3.6.2.12 Assist in planning personnel search and rescue operations, if necessary.

4.3.6.2.13 Assist in the transfer of injured and non-essential personnel if radiation or contamination hazards are involved.

4.3.6.2.14 Direct requests for additional support to the Radiation Protection Coordinator, or in his absence TSC Advisor, including any requests for:

,n

(,,

a.

Additional radiological monitoring equipment, b.

Engineering evaluations of temporary shielding on special tools and equipment.

c.

Additional health physics support personnel.

d.

Additional instrumentation and equipment.

4.3.6.2.15 Advise and assist the Radiation Protection Coordinator on matters involving radiological safety.

4.3.6.2.16 Maintain records of all onsite radiological emergency response activities.

4.3.6.2.17 Ensure that the Radiological Status Sheet, EPP-204-3 (Attachment 4) is completed in a timely manner, and establish and maintain a file of

,s

(

)

completed forms.

CPSE'S ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT18 MS EPP-204

{

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 11 0F 26 4.3.6.2.18 Maintain personnel dosimetry records for the duration of the emergency situation.

i 4.3.7 TSC Radiation Monitoring System (RMS) Computer Operators

.4.3.7.1 The two TSC RMS Computer Operator positions shall be filled by individuals from the Radiation Protection Section or qualified contract personnel.

4.3.7.2 Responsibilities:

4.3.7.2.1 Report directly to, and respond to requests f rom the Onsite Radiological Assessment Coordinator.

4.3.7.2.2 Calculate the projected onsite and offsite doses.

4.3.7.2.3 Provide the completed dose C-projections to the Onsite Radiological Assessment Coordinator.

4.3.7.2.4 Obtain information regarding current and forecasted meteorological conditions.

4.3.7.2.5 Provide input as required for the timely completion of the Radiological Status Sheet EPP-204-3 (Attachment 4).

4.3.8 Technical Support Center (TSC) Advisor 4.3.8.1 The primary individual designated to assume this position upon activation of the TSC is the Results Engineer. The designated alternates are Engineers from the Results Engineering Section.

4.3.8.2 Responsibilities:

4.3.8.2.1 Provide technical advice to the TSC Manager and other members of the TSC Staff as required.

4.3.8.2.2 Conduct and maintain accountability O

of TSC personnel in accordance with the procedure EPP-209, " Personnel Assembly and Accountability."

=

CPSE'S S

PROCEDURE NO.

EMERCENCY PLAN MANUAL Ow EPP-204 9

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PACE 12 0F 26 i

4.3.8.2.3 Coordinate warehouse support services.

f 4.3.8.2.4 Direct and coordinate the activities of the following personnel:

a.

TSC Communicator i'

b.

TSC Clerk c.

TSC Events Recorder d.

TSC Operational Status Recorder L

e.

TSC Radiological Status Recorder 4.3.8.2.5 Ensure that adequate logistical support is provided both to the onsite and offsite emergency response I

and recovery efforts prior to the j

activation of the EOF.

Such logistical support may include, but

/

is not limited to, the following:

a.

Additional clerical and administrative support personnel; b.

Warehouse support, procurement j

and expediting services; j

c.

Life-support services (e.g.,

food, clothing, and sleeping quarters) for onsite emergency j

personnel; and d.

Additional consnunications support and equipment repair services.

4.3.8.2.6 Inform the Logistical Support Coordinator of any logistical activities, requests, etc. upon activation of the EOF.

i i

4.3.8.2.7 If the EOF has not been activated, verify the technical accuracy and adequacy of all public information releases prior to their dissemination i

to the news media, i

j i

i

.w.,

-,,..-..._..,,_----..-,._.----...,..,.,,__,-_,n

S PR Ctw RE NO.

Olfl f8 $3 CPSES EPP-204 EMERGENCY PLAN MANL'AL l

)

ACTIVATION OF THE TECHNICAL SUPEORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 13 0F 26 4.3.8.2.8 Inform the Public Information Coordinator of any news /information releases made prior to activation of the EOF.

4.3.8.2.9 Conduct and record plant trend date analysis (i.e. indications of long term degradation of plant or situation outlooks getting better).

4.3.8.2.10 Ensure that coczmunications procedures are properly implemented, and that records of incoming and outgoing communications are maintained and prioritized.

4.3.9 TSC Communicator 4.3.9.1 The TSC Communicator position shall be filled by engineers or technicians trained in the responsibilities of the position.

4.3.9.2 Responsibilities:

4.3.9.2.1 Perform communications duties.

4.3.9.2.2 Log all incoming and outgoing communications in accordance with EPP-202, " Emergency Communications",

and EPP-203 " Emergency Notification".

4.3.10 TSC Clerk 4.3.10.1 The TSC Clerk position shall be filled by Engineers or Technicians trained in the responsibilities of the position.

4.3.10.2 Responsibilities:

4.3.10.2.1 Perform clerical and administrative duties (e.g., distributing or posting information and copying documents).

4.3.10.2.2 Assist and respond to any requests from the TSC Manager.

O 4.3.11 TSC Events Recorder V

4.3.11.1 The TSC Events Recorder position shall be filled by Engineers or Technicians trained in the responsibilities of the position.

CPSES ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT18t985 EPP-204 O

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PACE 14 0F 26 4.3.11.2 Responsibilities:

4.3.11.2.1 Maintain a log of all pertinent emergency response activities occurring in the TSC.

4.3.11.2.2 Obtain information related to the emergency situation from TSC personnel.

4.3.11.2.3 Post information related to the emergency situation on the TSC j

Sequence of Events Board.

NOTE: The TSC Sequence of Events Board should list, in i

chronological order, only I

those event-type items related to the emergency situation.

Operational and radiological 3

data shall be posted on separate status boards.

(

4.3.12 TSC Operational Status Recorder 4.3.12.1 The TSC Operational Status Recorder position at the TSC shall be filled by Engineers or Technicians trained in the responsibilities of the position.

l 4.3.12.2 Responsibilities:

4.3.12.2.1 Complete the Operational Status Sheet l

EPP-204-2 (refer to Attachment 3).

and maintain the Operational Status Board located in the TSC command l

center.

l 4.3.12.2.2 File the Operational Status Sheet.

4.3.12.2.3 Ensure that the EOF Operational Status Recorder is provided with the same information that appears on the status sheets.

l 4.3.12.2.4 Maintain communications with the Control Room Communicator.

l i

l

?

,,m.

-,n.--y,,m, ne,.

--,-,----m-

CPSEb ISS PROCEDL*RE NO.

OCT SE DNFB EPP-204 8

EMERGENCY PLAN MANUAL c

ACTIVATION OF THE TECHNICAL SUPPORT q

CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 15 0F 26 l

4.3.13 TSC Radiological Status Recorder j

4.3.13.1 The TSC Radinlogical Status Recorder position in i

the TSC shall be filled by Engineers or Technicians trained in the responsibilities of the position.

4.3.13.2 Responsibilities:

l j

4.3.13.2.1 Complete the Radiological Status Sheets (refer to Attachment 4), and l

maintain the Radiological Status i

Board located in the TSC command center.

4.3.13.2.2 File the Radiological Status Sheets.

1 4.3.13.2.3 Ensure that the EOF Radiological l

Status Recorder is provided with the I

same information that appears on the status sheets.

4.4 Subsequent Actions 1

i 4.4.1 In the event of extended operations, the TSC staff may be l

altered as necessary by the TSC Manager to maintain 24 i

hour operations capability.

i i

i 4.4.2 Operation of the TSC shall continue until such time that j

the Emergency Coordinator or the Recovery Manager directs its deactivation.

j 3

4.4.3 Any records or forms generated by this procedure, as the i

result of an actual or potential emergency, shall be handled in accordance with STA-302, " Station Records".

il 4.5 Facility Habitability 4.5.1 If a habitability monitor alarms, the Onsite Radiological Assessment Coordinator (ORAC) shall direct a check of the l

current TSC radiological conditiont.. This check should be l

4 conducted as follows:

I i

4.5.1.1 Using form EPP-309-1, determine and record the general Beta-Gamma dose rate in the TSC in accordance with EPP-310.

j i O i

4 l

I

, -., _ -.. - - -,., ~ - -. - - -.. -. -. - - - - - - - -, -

OdiU[.ESS IS PROCEDURE NO.

CPSES Ere-204 EMERGENCY PLAN MANUAL j

l ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 16 0F 26 4.5.1.2 Replace the iodine cartridge on the portable iodine monitor and obtain one iodine concentration measurement based upon a 15 minute sampling period using the methodology described in HPI-863, " Operation of the Technical Associates Model FM-5ABNI Iodine Monitor."

NOTE:

All filters and iodine cartridges shall be labeled with the present date and time, total collection time, average sample flow rate and person performing the survey. These filters or cartridges shall be retained for future analysis.

All results shall be documented and retained using HPI-863-1.

4.5.2 If a habitability monitor fails or is suspect, the ORAC shall direct a check of the current TSC Radiological condition and commence periodic monitoring as follows:

4.5.2.1 Using form EPP-309-1, determine and record the e

general Beta-Camma dose rate in the TSC in accordance with EPP-310, 4.5.2.2 Determine the average iodine concentration in accordance with EPP-310, 4.5.2.3 TSC habitability conditions should be periodically monitored. These checks should be performed as a minimum every hour while radioactive releases to the atmosphere are in progress.

4.5.3 The ORAC shall notify the TSC Manager and take appropriate actions at the specific radiological conditions shown below:

4.5.3.1 If the area dose rates exceed 10 mrem /hr but is less than 50 mrem /hr notify the TSC Manager.

4.5.3.2 If the average iodine concentration exceeds 1.0E-8 uCi/cc, notify the TSC Manager.

4.5.3.3 If the area dose rate exceeds 50 mrem /hr, notify the TSC Manager. Continuously monitor dose rates using the ARM or other done rate monitor until they drop below 50 mrem /hr, then resume 7

s

(

normal monitoring.

CPSE'S ISSUE DATE PROCEDURE NO.

EPP-204 EMERGENCY PLAN MANUAL fif'.T 1 R in 9

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 17 0F 26 4.5.3.4 If the average iodine concentration exceeds 1.0E-7 uCi/ce, notify the TSC Manager and continue to monitor iodine concentrations using the portable iodine monitor as described in HPI-863 or take portable air samples every 1/2 hour until concentrations drop below 1.0E-7 uCi/cc, then resume normal monitoring.

4.5.4 Determine if protective actions are necessary:

4.5.4.1 If area dose rates exceed 100 mrem /hr, evacuation of the TSC to an alternate location should be considered.

4.5.4.2 If iodine concentrations exceed 1.0E-6 uCi/ce, protective measures should be considered including evacuation to an alternate location, donning respiratory protection and taking KI in accordance with EPP-306, "Use of Thyroid Block-ing Agents".

O 4.5.4.3 Protective action recommendations should take into account the estimated time which dose rates or iodine air concentrations will be at these high levels.

NOTE: The suggested iodine concentration for evacuation, 1.5E-5 uCi/ce, is that concentration of I-131 that will give a total accumulated dose of 5 rem to the thyroid for a 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> inhalation period.

This is passed on EPA graph 5.2 of EPA-520/1-75-001, " Manual of Protective Action Guides and Protective Actions for Nuclear Accidents."

5.0 References 5.1 CPSES Emergency Plan 5.2 EPP-109, " Duties of the Emergency Coordinator" 5.3 EPP-202, " Emergency Communications" 5.4 EPP-203, " Emergency Notification" 5.5 EPP-208, " Access Control During Emergency Conditions" l

l l

CPSES ISSUE DATE PROCEDUfE NO.

EMERGENCY PLAN MANUAL OCT 181985 EPP-204 ACTIVATION OF THE TECHNICAL SUPPORT

{

CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 18 0F 26 5.6 EPP-209, " Personnel Assembly & Accountability" 5.7 EPP-306, "Use of Thyroid Blocking Agents" 5.8 EPP-309, "Of f-Site Radiological Surveys" 5.9 EPP-310. "On-Site and In-Plant Radiological Surveys" 5.10 EPP-520/1-75-001, " Manual of Protective Action Guides and Protective Actions for Nuc1 car Accidents" 5.11 HPT-801, " Operation of Portable Survey Instruments" 5.12 HPI-863, " Operation of the Technical Associates Model FM-5ABNI Iodine Monitor" 5.13 STA-302, " Station Records" 6.0 Attachments 6.1. "TSC Operations Checklist" 6.2 Attachment 2 " Suggested TSC Layout" 6.3 Attachment 3, " Operational Status Sheet" 6.4 Attachment 4, " Radiological Status Sheet"

,Q

CPSES ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT 181985 EPP-204 uu, ACTIVATION OF THE TECHNICAL SUPPORT O

CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 19 0F 26 ATTACHMENT 1 PAGE 1 0F 1 TSC CHECKLIST Texas Utilities Generating Company Comanche Peak Steam Electric Station TSC ACTIVATION CHECKLIST Page 1 of 1 VERIFIED ITEM RESPONSIBII.ITY OR COMPLETE 1.

TSC activation / turnover Started Date/ Time 2.

TSC Layout (Attachment 2)

TSC Personnel 3.

TSC telephones installed TSC Personnel (Attachment 2) 4.

Conduct TSC personnel TSC Manager accountability check report results to security.

5.

Verify minimum staff TSC Advisor requirement a.

Management b.

Engineering c.

Operations d.

Maintenance e.

Radiation Protection f.

TSC Comunicator 6.

Establish cersunications TSC Cormunicator per EPP-203 7.

Activate lodine scnitor ORAC and area radiation monitor 8.

TSC checklist / turnover complete Date/ Time TSC Panager/Date

,O rev/5-85 EPP-204-1

g T&AMc PROCEDURI NO.

CPSES EPP-204 EMERGENCY PLAN MANUAL ACTIVATION OF THE TECHNICAL SUPPORT

{

g CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 20 0F 26 ATTACHMENT 2 PAGE 1 0F 2 SUGGESTED TSC LAYOL7 eeousace o, svente so.am

/

usse 7""

.. f_

v 2..

:g

.p..

..p:

v d

h

@ 1 P'**i,0),, g(,*

8 ',3

-Jo= e 8 "

9

==='a' 3

o

,, = = p v

mm s

(. o o o

mm es!

9.

c O

v ' "'"

(*

o o gogo g

y a

w

.c evane so se

@o3 ww g

GO

~

WW Q

i: i)

_[: 39 o *l

?......P-,,h?:-

.. : L.

~ ;.;s:.;l lv

. u..

nl l <.. ' _x b

.. -... I,

=' /

ga,,,,, **"

=

S, R00m 1 0 Tremeu.su ercoura OV

CPSES ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT i 81985 EPP-204 9

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 21 0F 26 ATTACHMENT 2 PAGE 2 0F 2 SUCCESTED TSC LAYOUT 1 TSC MANAGER 2 OPERATIONS COORDINATOR 3 MAINTENANCE COORDINATOR 4 ENGINEER 500 TE AM COORDIN ATOR S ONSITE R ADIOLOGICAL ASSESSMENT COORDIN ATOR S TSC ADVISOR T TSC ENGINEERING TEAM S TSC COMMUNICATOR S TSC CLERE 10 TSG EVENTS RECORDER 11 OPERATIDNAL STATUS RECORDER 12 RAINOLOGICAL STATUS IWC00mER 13 IRIS COtmMWI OPWIATORS 14 NRC OR DfilLL CONTROLLER C

Q PSX TELEPHONE

@ PSX/ TRUNK LINE TELEPHONE

@ DEDICATED TELEPHONE TO EOF I

@ DECICATED TELE 7NONE TO OSC

@ DEDICATED TELEPHONE TO CONTROL ROOM O STATE AND COUNTY RINGDOWN LINE O EMERGENCY NOTIFICATION SYSTEM TELEPHONE C RADIO S ASE STATION EPOS SAPETY PARAMETER DISPL AY SYSTEM O

COMPUTER TERMINAL SP SCREEN PRINTER RADIATION MONITORING SYSTEM COMPUTER TERMINAL O

ROOM 149 /149A

CPSES ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL 0CT 181985 EPP-204 ACTIVATION OF THE TECHNICAL SUPPORT g

g CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PACE 22 0F 26 ATTACHMENT 3 PAGE 1 0F 3 OPERATIONAL STATUS SHEET Texas Utilities Generating Coogany Comanche Peak Steam Electric Station OPERATICNAL STATUS SHEET Page 1 of 3 1.

Af fected Unit: one Two 2.

M a.

Pressure PSIG b.

Tavg:

  • r c.

PRZR Level:

4 d.

Est. RCS Leak GPM e.

RCP:

On Off f.

T/C (Hi/ Avg):

/

'r 9

C:

PPM B

h.

Loop Status:

1 2

3 4

T r

H T

  • r c

3.

ECCS No. Punip s Total GPM a.

CC b.

RHR c.

SI d.

Cont. Spray e.

PWST Invels g

f.

Accumulators 1

2 3

4 Accumulator Level 4

g.

Accumulator Pres.

PSIC 4.

Emergency Pesponse Guidelines a.

Procedures b.

Stept c.

Diagnosed Event:

I i

e e

i e

rev/5-85 EPP-204-2

CPSES ISSUE DATE PROCEDURE NO.

OCT 181985 EMERGENCY PLAN MANUAL EPP-204

{

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 23 0F 26 ATTACHMENT 3 PAGE 2 0F 3 OPERATIONAL STATUS SHEET l

Texas Utilities Generating Company Comanche Peak Steam Electric Station OPERATIONAL STATUS SHEET Page 2 of 3 5.

Critical Safety Functions Tin:e Red Orange Yellow Green Sub Crit.

FRS-0.1 FRS-0.1 FRS-0.2 Sat FRC-0.2 Core Cooling FRC-0.1 FRC-0.3 FRC-0.4 Sat RCS Integrity FRP-0.1 FRP-0.1 FRP-0.2 Sat FRH-0.2 FRB-0.4 Heat Sink FRH-0.1 FRB-0.3 FPH-0.5 Sat FRZ-0.1 Containment FR2-0.1 FR2-0.2 FRI-0.3 Sat FRI-0.1 FRI-0.2 Inventory FRI-0.3 Sat 6.

Plant Status a.

Rx Trip b.

SI Actuation c.

Containment Spray Actuation d.

Power Level e.

Comments O

rev/5-85 EPP-204-2a

CPSES ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL 0CT 181985 EPP-204 l

l ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 24 0F 26 ATTACHMENT 3 PAGE 3 0F 3 OPERATIONAL STATUS SHEET Texas Utilities Generating Company Comanche Peak Steam Electric Station CPERATIONAL STATUS SHEET Page 3 of 3 7.

Containment Conditions a.

Pressures PSIG b.

Temperature:

  • F c.

Humidity:

4 d.

Rad. Level R/RR e.

Phase A Isolation:

f.

Phase B Isolation:

g.

Vent. Isolation:

h.

Hydrogen Concentration:

4 Volume 8.

Steam Generators a.

Steam Generators 1

2 3

4 b.

SG Levels t

c.

SG Pressure PSIG d.

MSIV Status e.

AFW Flow:

GPM f.

AFW Pumps on:

Motor 1 Motor 2 Turbine g.

CST Level:

4 9.

Support Systems No. Putrp s a.

SSW Pumps Operating:

b.

CCW Pufrps Operating:

c.

Emergency Bus Energized: Train A Train B d.

Offsite Powert Yes No e.

Diesel Gen. Available No. I No. 2 10.

Femarks:

Status Sheet Completed By Date/ Time e

rev/5-85 EPP-204-2b

CPSES ISSUE DATE PROCEDURE NO.

EMERGENCY PLAN MANUAL OCT 181985 EPP-204 ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 25 0F 26 ATTACHMENT 4 PAGE 1 0F 2 RADIOLOGICAL STATUS SHEET Tamme Ott11tteo Generating Company Comanche Peak Steam Electric Stattee RADIM4CICAL STATL'S SEIIT Pase 1 of 2 DC ROP COMNT A5 0Ft RE12ASE INTW MATirE

_ Bot Occurring Release Path

_ not Projected flee began _

_ Plset ven t

_ In Occurring Time Ended: _

_ 5 team Line

_ Bao Occurred

!bration

_ Cantatteent Idah e

( Ac tual/ Projected)

Ot he r:

Physical Fore antease sete

_ Ligote Waterborne

_ Ct/see B.C.

_ Caseous

_ Airboree

___ C1/see lod.

Other

_ Ct/see Part.

SOFACI agr!AprJATims TOTAL CuerDr3AT10N:

  • site

_ uC/cc n.C.

_ uC1/o*

dps/100 co'

_ uC/cc lod, location (highest)

_ aC/cc Part.

Of fatte (measured / projected)

_ uC1/e' Total Anleases location

_ thighest)

_ Cl MTORIMC TEAM IN70PPATim:

Team (A/1)*: Location:

Time of krvey:

Rad. Isvel ares /hr Air. Cont. Invel eC1/s' Tess (5/2):

tocations Time of h.rvey Rad. level mRea/br Air. Coct. Isvel uCt/s' Team (C/3):

locat ice Time of Surveys Rad. level mRee/hr Air. Cont. level uCt/e3 e Alpha Destpator a On site Ihmeric Destpator - Offsite e

rev/5-85 EPP-20k-3

EMERGENCY N MANUAL j8 5

E 4

ACTIVATION OF THE TECHNICAL SUPPORT CENTER (TSC) AND TSC PERSONNEL DUTIES REVISION NO. 4 PAGE 26 0F 26 ATTACHMENT 4 PAGE 2 0F 2 RADIOLOGICAL STATUS SHEET Texas Utilittei Generating Capany Cemanche Peak Steam Itectric $tation RAD 10tI1CICAL STAIt3 SHIET Page 2 of 2 se*tkU1CICAL 'N*f0N:

Primary Towet lackup lower Wind Speed MPH; MP1; Pr;w Stability Class:

at 04 Precip _

Other tefe:

RAr!OII1CICAL DOSE IMFCPMATION:

Otid Thyreid Weie bq pose late Dene (Rea)

Di st.

Dese Rate h*

Done ( Aes)

I m

i 2

S l

10 l

i I

i l

PRalCTITY AC* ION RI'N ATI3:

%ee at this time Shelter (5/D)

Zone

_ Evacuate (5/C)

Zone Baels: Radiation _ Plant Gmdtticce _

Precauttaary _

te:Jimesca: ors 'aplerected: Ye s _

If k, Actiona lates.

(Below Sections Apply to T.S.C. Status Board Only)

Primary Oesistry Results: Time Semple Taken Total Activity! _ uC1/cc; Ecron: _ ppt IN-Pirr! DIir9 3A*A:

Nmitor:

locatica Reading s fuC1/ce, mR/br):

Status het Completed by:

Da te/ Time rev/$-s5 EPP-2(A - la