ENCLOSURE HEETING
SUMMARY
Licensee: Carolina Power and Light Company Facility: Shearon Harris Nuclear Plant Docket No.: 50-400
Subject:
Initial Cperator Licensing Examinations On July 23, 1985, representatives of Carolina Power and Light Company (CP&L) met with NRC Region 11 personnel in Atlanta, Georgia, to discuss CP&L's upcoming examinations for the initial licensed operator cadre at the Shearon Harris Nuclear Plant.
The meeting was held at the request of the NRC. The attendance list is attached as Attachment A to this Sumary.
Mr. A. C. Tollinson coordinated the CP&L presentation.
The highlights of this presentation included:
construction schedule overview and fuel load projection; training program status and schedules; synoasis of licensee candidate qualifica-tions; and status of plant reference mater'.als, to include simulator delivery schedule. The briefing vu-graphs are enclosed as Attachment D and provide a more detailed description of the presentation.
Upon completion of the CP&L presentation, Mr. B. A. Wilson, Chief, Operator Licensing Section, addressed the need for contingency plans concerning the initial licensing exams.
Comission and Region !! policy was stated as being to give initial examinations as close as possible to actual fuel load, while ensuring that this did not adversely delay licensing activities.
While current schedule projections support March 1986, as a reasonable fuel load projection, experience suggests the possibility of slippage.
Based upon when such slippage is discovered and the extent of such slippage, the Comission reserves the right to adjust both the schedule and scope of the initial licensing exams. Attachment C summarizes the contingency plans identified by the Region !! staff; schedule variations beyond those identified will require further modifications.
we $r" lk 6 4 ??
fenneth E. Drocmany eactor Engineer Date R
Attachnents:
A.
Attendance List D.
Presentation Vu Graphs C.
Contingency Plans 0500130144 n3oogy (UN ADOCK OD000400 l*DH
ATTACHMENT A ATTENDANCE LIST NRC Personnel Name Position Bruce Wilson Section Chief, Operator Licensing Section Ken Brockman Principal Examiner Paul Fredrickson Section Chief Projects Section 1C' CP&L Personnel Name Position Howard Smith Director, Nuclear and Simulator Training Wayne Powell Director Training - Harris Gregg A. Sinders Senior Licensing Engineer Jim Willis Plant General Manager, SHNPP Fred To111 son Manager, Nuclear Training W
L
ATTACHMENT B 7-23-85 NRC/CP&L MEETING 1.
PURPOSE ACT 11.
SCHEDULE OVERVIEW ACT 111.
FUEL LOAD DATE JLW IV.
TRAINING STATUS AND SCHEDULE ACT V.
PREllCENSE REVIEW COURSE ACT VI.
LICENSE CANDIDATES ACT Vll.
STATUS OF REFERENCE MATERIAL AWP Vill.
DISCUSSION ALL i
t
e T
PURPOSE TO DISCUSS PLANS FOR OPERATOR LICENSING EXAMINATIONS FOR SHNPP COLD LICENSE CANDIDATES.
I
8 SCHEDULE OVERVIEW FUEL LOAD DATE MARCH 11 3>.
' '..g s,["
EXAM DATES NOVEMBER li JANUARY 20 SIMULATOR RFT NOVEMBER 18 i
l
[
't 9
f
\\
)
O 9
9 TRAINING STATUS AND SCHEDULE TRAINING SCHEDULE (CHART)
SIMULATOR SCHEDULE (CHART)
CONCLUSIONS AND PROPOSAL 1
-- CANDIDATES HAVE BEEN PROPERLY AND ADEQUATELY TRAINED TO OPERATE THE PLANT.
TIME ON NEW SIMULATOR NOT ESSENTIAL TO SAFE OPERATION.
-- CANDIDATES SHOULD TAKE EXAMS AS SCHEDULED (NOV., JAN.),
INDEPENDENT OF FUEL LOAD DATE MORALE AVAILABILITY FOR START-UP PROGRAM i
ENTER REQUALIFICATION EARLY
-- WITH FUEL LOAD DATE OF MARCH
- 1986, NOV.
AND JAN.
CANDIDATES NOT BE EXAMINED ON SIMULATOR i
-- MAY 1986 CANDIDATES (DEFERRALS AND MAKEUPS)
RECEIVE SIMULATOR EXAM 1
-- NOV.
AND JAN.
CANDIDATES ARE FORECASTED TO RECEIVE TRAINING ON NEW SIMULATOR BY MARCH, SUBJECT TO SIMULATOR AND OPERATOR AVAILABILITY
-- ALL LICENSED PERSONNEL WILL RECEIVE ANNUAL SIMULATOR TRAINING AS PART OF REQUALIFICATION PROGRAM WHICH BEGINS WITH INITIAL LICENSING
PRELICENSE REVIEW COURSE FSAR, SECTION 13.2 ABOUT FOUR WEEKS IN DURATION SUBJECTS TO INCLUDE " SIMULATOR REVIEW" FSAR CHANGE WILL BE PROCESSED TO DELETE THIS SUBJECT i
LICENSE CANDIDATES DISTRIBUTION R0 SRO MANAGERS AND SUPERVISORS (3) 3 SHIFT FOREMAN (6) 6 STA (9) 9 SCO-IN-TRAINING (12) 12 CO-IN-TRAINING (37) 8 29 INSTRUCTORS (4) 4 TECH. SUPP./ REG. COMP. (3) 3 TOTAL (74) 8 66 NOV. (41)
JAN. (33)
SCREENING
-- REVIEW AND AUDIT COURSE AND PRELICENSE REVIEW COURSE WILL BE USED AS FINAL SCREEN FOR SRO, R0, DEFERRALS
-- TOTAL CANDIDATES AND SR0 CANDIDATES ARE MAXIMUM NUMBERS
1 i
.t j
-,-j TOTAL STARTUP TEAM j
i STARTUP.
~
i.1
- /Rb.
/
F \\ NNs 7 /
/ 'l
\\
N x
/
i
/
/
/
N N
I
/
/
\\
\\
N N
f
/
/
- /
, 'L.
\\
\\
N
'i
\\
/
/
/~
n g
/
/
[
'\\
\\
N j
.c N
i LINE
/
i{ '_
\\
\\
N l CRCANIZATION
/
/
N
' !i J L J i JL J 6 J L a
l l
l MAINT.
E&RC OPS CONST.
ENGINEERING OA i
I&C TECHS CHEM-TECHS OPERATORS CRAFT DESIGN ENG.
INSPECTORS MECHANICS
'HP TECHS i
- )
A
HARRIS NUCLEAR PROJECT READINESS FOR OPERATIONS '
4 HPOS STAFFING l
l (As OF JULY 17, 1985)
PERMANENT PLANT t
1 i
AUTHORIZED SLOTS 439 i
ACTUALLY FILLED 412 0FFERs OUTSTANDING 7
SUBTOTAL 419 SUPPLEMENTAL STAFFING i
j CP&L TRAVELING MAINTENANCE CREW 30 MAINTENANCE SUPPORT CONTRACTORS 80 SU SUPPORT CONTRACTORS 27 SUBTOTAL 137 l
TOTAt 556 i
?
HARRIS NUCLEAR PROJECT READINESS FOR OPERATIONS l
KEY MILESTONES STEAM GENERATOR FILL AND HYDR 0 STATIC TEST - COMPLETED DECEMBER 84 EMERGENCY PREPAREDNESS APPRAISAL BY NRC
- COMPLETED HARCH AND APRIL, 1985 EMERGENCY DRILL
- COMPLETED MAY 17-18 INP0 NTOL Assist. VISIT
- COMPLETED JUNE 17-28 l
PRIMARY PLANT COLD HYDRusTATIC TEST
- COMPLETED JUNE 20 I
hot FUNCTIONAL IEsTs
- NOVEMBER - DECEMBER 1985 OPERATOR LICENSE EXAMS
- START NOVEMBER 1985 t
1 i
i i
li MRASTONE SCHEDULE MANAGEMENT TARGET SCHEDULE 2
l 1
I JAN ASAR ISAY JUL SSP NSW JAN 884 4 MAY JUL SSP NOW
?
0 I
O O
0 0
0 I
O O
I I
0 0
0 I
l g
l y
- l
-l 8
CURRENT PROJECTNMet I
j m-
=.*w erase,-
9
-e-4
- w e + ew=44 e,-'a-.sw N#w,em e
=W.**-t+we-+=-
- =--,-n-sed
=<**-ew e- + - ~t
...*-e-we=
e==v
--e-,--e
,,e4 t
u
-e-
-h
--e w
PLANT STATUS I.
CONSTRUCTION % COMPLETE 92%
II.
RFT STATUS TOTAL RFTs 1303 ACCEPTED BY START UP 7/12/85 790 III.
FST STATUS TOTAL FSTs 326 ACCEPTED BY START UP 61
e o
HARRIS NUCLEAR PROJECT READINESS FOR OPERATIONS COMPLETION
SUMMARY
CONSTRUCTION 92%
TESTING 11 7 %
STAFFING 95%
TRAINING 86%
PROCEDURES 72% (95%)
~
HARRIS IIUCLEAR Pit [LIECT READillESS FOR OPERATI0llS HPOS STAFFilIG
~
(As or Juty 17, 1985)
PERMANENT PLANT AUTHORIZED SLOTS 439 AcTuaLLY FILLED 412 OFFEns OursTanDins 7
SusT0TAL 419 SUPPLEMENTAL STAFFING CPEL TnavELIles Na:NTENancE CnEw 30 NAINTENaNCE $UPPORT CONTRACTons 90 SU Surroni CONinacions
_2Z Suele1AL 137
[
~
TaTat 556
~
^
t
^
'I' e'
~w 7
l y
a i
,i
=
U W
5 l
0 i
=
i 5
- U" t
g 5
.g e
1 d
5 5
E E
2 2
E
=
E 8
I i
-i i lE Is 1
e
.I a
g g
I IlE 1
Eiit I
e
-g
- I g
gs i.l s
E E
I e
3 85 3
lj&
I g
g.
i JI E l
h Z
5
=
s 8
k
(
i
l 1
l l
l ATTACHMENT C CONTINGENCY PLANS Exam Date Scope Fuel Load Date Final Decision Date November 4-15, 1985 40 Candidates March 1986 -
September 30, 1985 Written June 1986 Oral January 1986 30 Candidates March 1986 -
November 30, 1985 Written June 1986 Oral May 1986
?? Candidates March 1986 -
March 31, 1986 (Retest)
June 1986 Written Oral Simulator NOTE: Any slippage in fuel load beyond June 30, 1986, will require i
reconsideration of both the schedule and scope of each individual examination. Such decisions will be made no later than the final decision date for each exam.
1 i
l l
[
I i
!