r
.-
..
-
.
APPENDIX A
Duquesne Light Company
Docket No. 50-412
Beaver Valley Power Station, Unit 2
License No. CPPR-105
As a result of the inspection conducted on May 23 - June 28, 1985, and in accor-
dance with the NRC Enforcement Policy (10 CFR 2, Appendix C), published in the
Federal Register on March 8, 1984 (49 FR 8583), the following violation was iden-
tified:
10 CFR 50, Appendix B, Criterion V requires that activities affecting
quality shall be prescribed by procedures and shall be accomplished in
accordance with these procedures.
Drawing 12241-BZ-19A-48-0C defines the dimensions, associated tolerances, and
other necessary details to properly install pipe support 2SWS-PSST 625.
Contrary to the above, and even though the installed support was " final in-
spected," the relative piping / support centerline dimension of pipe support
25WS-PSST 625 did not conform to that specified on Drawing 12241-BZ-19A-48-0C.
This is a Severity Level IV Violation (Supplement II).
Pursuant to the provisions of 10 CFR 2.201, Duquesne Light Company is hereby re-
quired to submit to this office within thirty days of the date of the cover letter
to this Notice, a written statement or explanation in reply including: (1) the
corrective steps which have been taken and results achieved; (2) corrective steps
which will be taken to avoid further violations; and (3) the date when full com-
pliance is achieved. Where good cause is shown, consideration will be given to
extending your response time.
.