MONTHYEARNPL-99-0569, Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with NPL-99-0051, Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with NPL-99-0449, Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with ML20209D2691999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Pbnps,Units 1 & 2 NPL-99-0328, Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with ML20209D2751999-05-31031 May 1999 Revised MORs for May 1999 for Pbnps,Units 1 & 2 NPL-99-0273, Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-99-0193, Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with NPL-99-0134, Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with NPL-99-0008, Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with NPL-98-1006, Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-98-0948, Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-98-0826, Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With ML20151W3851998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Pbnp Units 1 & 2 ML20151W4541998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 1 ML20151W4471998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 2 NPL-98-0653, Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 2 NPL-98-0558, Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 2 ML20151W4261998-06-30030 June 1998 Corrected Page to MOR for June 1998 for Pbnp Unit 2 ML20151W4221998-05-31031 May 1998 Corrected Page to MOR for May 1998 for Pbnp Unit 2 NPL-98-0481, Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W4011998-04-30030 April 1998 Corrected Page to MOR for April 1998 for Pbnp Unit 2 NPL-98-0356, Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20216D7071998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3981998-03-31031 March 1998 Corrected Page to MOR for March for Pbnp Unit 2 NPL-98-0159, Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3891998-02-28028 February 1998 Corrected Page to MOR for Feb 1998 for Pbnp Unit 2 ML20216D7121998-02-28028 February 1998 Revised Corrected MOR for Feb 1998 for Point Beach Nuclear Plant,Unit 2 NPL-98-0084, Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 21998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20198M2251997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20198M2331997-11-30030 November 1997 Corrected Monthly Operating Repts for Nov 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20203F9171997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Point Beach Nuclear Plant,Units 1 & 2 NPL-97-0715, Monthly Operating Repts for Oct 1997 for Point Beach Nuclear Plant,Units 1 & 21997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20203F9361997-10-31031 October 1997 Revised Monthly Operating Rept for Oct 1997 for Point Beach Nuclear Plant,Unit 2 NPL-97-0621, Monthly Operating Repts for Sept 1997 for Point Beach Nuclear Plant,Units 1 & 21997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20203F9311997-09-30030 September 1997 Revised Monthly Operating Rept for Sept 1997 for Point Beach Nuclear Plant,Unit 2 NPL-97-0553, Monthly Operating Repts for Aug 1997 for Point Beach Nuclear Plant,Units 1 & 21997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20203F9261997-08-31031 August 1997 Revised Monthly Operating Rept for Aug 1997 for Point Beach Nuclear Plant,Unit 2 ML20210H9531997-07-31031 July 1997 Monthly Operating Repts for Jul 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20210H9601997-06-30030 June 1997 Revised Monthly Operating Rept for June 1997 for Point Beach Nuclear Plant,Units 1 & 2,which Provides Corrected Forced Outage Rates NPL-97-0318, Monthly Operating Repts for May 1997 for Point Beach Nuclear Plant,Unit 1 & 21997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Point Beach Nuclear Plant,Unit 1 & 2 ML20141C2381997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20141C2461997-03-31031 March 1997 Corrected Operating Data Rept for Mar 1997 for Point Beach Nuclear Plant,Unit 1 ML20137P5781997-03-31031 March 1997 Monthly Operating Repts for March 1997 for Point Beach Nuclear Plant Units 1 & 2 ML20137P5711997-02-28028 February 1997 Corrected MOR for Feb 1997 for Point Beach Nuclear Plant Unit 1 ML20135F2721997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Point Beach Nuclear Plant,Units 1 & 2 ML20134J8711997-01-31031 January 1997 Monthly Operating Repts for Jan 1996 for Point Beach Nuclear Plant,Units 1 & 2 ML20135F2771997-01-31031 January 1997 Revised Monthly Operating Rept for Jan 1997 for Point Beach Nuclear Plant,Unit 2 ML20133N0601996-12-31031 December 1996 Revised MOR Rept for Dec 1996 for Point Beach Nuclear Plant, Units 1 & 2 ML20133F6471996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Point Beach Nuclear Plant,Unit 1 & 2 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARNPL-99-0569, Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with ML20212D5961999-09-15015 September 1999 Safety Evaluation Supporting Licensee IPEEE Process.Plant Has Met Intent of Suppl 4 to GL 88-20 NPL-99-0051, Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with NPL-99-0449, Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with ML20196J4251999-06-30030 June 1999 Safety Evaluation Authorizing Proposed Alternatives Described in Relief Requests VRR-01,ROJ-16,PRR-01 & VRR-02 ML20209D2691999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Pbnps,Units 1 & 2 ML20196F3341999-06-22022 June 1999 Safety Evaluation for Implementation of 422V+ Fuel Assemblies at Pbnp Units 1 & 2 ML20195F9781999-06-10010 June 1999 Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1 ML20209D2751999-05-31031 May 1999 Revised MORs for May 1999 for Pbnps,Units 1 & 2 NPL-99-0328, Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with NPL-99-0273, Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With ML20196F3521999-04-30030 April 1999 Non-proprietary WCAP-14788, W Revised Thermal Design Procedure Instrument Uncertainty Methodology for Wepc Point Beach Units 1 & 2 (Fuel Upgrade & Uprate to 1656 Mwt - NSSS Power) NPL-99-0193, Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with NPL-99-0134, Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with ML20207D6751999-02-22022 February 1999 Assessment of Design Info on Piping Restraints for Point Beach Nuclear Plant,Units 1 & 2.Staff Concludes That Licensee Unable to Retrieve Original Analyses That May Have Been Performed to Justify Removal of Shim Collars ML20206R9001999-01-13013 January 1999 SER Accepting Nuclear Quality Assurance Program Changes for Point Beach Nuclear Plant,Units 1 & 2 NPL-99-0008, Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with NPL-99-0091, 1998 Annual Results & Data Rept for Pbnps,Units 1 & 2. with1998-12-31031 December 1998 1998 Annual Results & Data Rept for Pbnps,Units 1 & 2. with ML20198C7671998-12-10010 December 1998 Safety Evaluation Accepting Licensee Proposed Alternative to ASME BPV Code,1986 Edition,Section XI Requirement IWA-2232, to Use Performance Demonstration Initiative Program During RPV Third 10-yr ISI for Plant,Unit 2 NPL-98-1006, Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With ML20195J5101998-11-16016 November 1998 Proposed Revs to Section 1.3 of FSAR for Pbnp QA Program ML20198J5941998-11-0303 November 1998 1998 Graded Exercise,Conducted on 981103 NPL-98-0948, Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-98-0880, Special Rept:On 980913,fire Alarm Control Panels Inoperable for More That Fourteen Days.Troubleshooting of D-401 Panel Following Installation of Replacement Batteries Revealed No Apparent Cause for Spurious Alarms.Panel D-401 Restored1998-10-21021 October 1998 Special Rept:On 980913,fire Alarm Control Panels Inoperable for More That Fourteen Days.Troubleshooting of D-401 Panel Following Installation of Replacement Batteries Revealed No Apparent Cause for Spurious Alarms.Panel D-401 Restored ML20154M9121998-10-14014 October 1998 Unit 1 Refueling 24 Repair/Replacement Summary Rept for Form NIS-2 ML20154L6751998-10-14014 October 1998 Unit 1 Refueling 24 ISI Summary Rept for Form NIS-1 NPL-98-0826, Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With ML20151W3851998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Pbnp Units 1 & 2 NPL-98-0653, Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W4471998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 2 ML20151W4541998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 1 ML20236Q3161998-07-10010 July 1998 Safety Evaluation Accepting Licensee Proposed Alternative to ASME Code Requirements PTP-3-01 & PTP-3-02 ML20236L6771998-07-0707 July 1998 Safety Evaluation Approving Wepco Implementation Program to Resolve USI A-46 at Point Beach NPP Units 1 & 2 NPL-98-0558, Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 2 ML20151W4261998-06-30030 June 1998 Corrected Page to MOR for June 1998 for Pbnp Unit 2 ML20151W4221998-05-31031 May 1998 Corrected Page to MOR for May 1998 for Pbnp Unit 2 NPL-98-0481, Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W4011998-04-30030 April 1998 Corrected Page to MOR for April 1998 for Pbnp Unit 2 NPL-98-0356, Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20217F3131998-04-17017 April 1998 Safety Evaluation Accepting Proposed Alternative to ASME Code for Surface Exam of Nonstructural Seal Welds,For Plant, Unit 1 ML20216D7071998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3981998-03-31031 March 1998 Corrected Page to MOR for March for Pbnp Unit 2 NPL-98-0209, Special Rept Re Fire Barrier Inoperable for Greater than Seven Days.Compensatory Measures Implemented in Accordance W/Fire Protection Program Requirements During Time That Barriers Were Inoperable1998-03-30030 March 1998 Special Rept Re Fire Barrier Inoperable for Greater than Seven Days.Compensatory Measures Implemented in Accordance W/Fire Protection Program Requirements During Time That Barriers Were Inoperable ML20217A8501998-03-19019 March 1998 SER Accepting Proposed Changes Submitted on 980226 by Wiep to Pbnp Final SAR Section 1.8 Which Will Impact Commitments Made in Pbnp QA Program Description.Changes Concern Approval Authority for Procedures & Interviewing Authority ML20216J0101998-03-17017 March 1998 Safety Evaluation Accepting Third 10-yr Inservice Insp Interval Relief Request RR-1-18 for Plant NPL-98-0159, Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3891998-02-28028 February 1998 Corrected Page to MOR for Feb 1998 for Pbnp Unit 2 ML20216D7121998-02-28028 February 1998 Revised Corrected MOR for Feb 1998 for Point Beach Nuclear Plant,Unit 2 NPL-98-0084, Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 21998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20198L1151998-01-0808 January 1998 SER Accepting Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Point Beach Nuclear Plant,Units 1 & 2 1999-09-30
[Table view] |
Text
. . . . . . . - -
l Wisconsin Electnc \
POWER COMPANY i i
l Point Beoch Nuclear Plant (414) 755-2321 6610 Nuclear Rd.. Two Rivers. WI 54241 j l
l PBL 97-0010 January 7,1997 Document Control Desk U. S. NUCLEAR REGULATORY COMMISSION Mail Station Pl-137 Washington, DC 20555 i
Gentlemen:
DOCKETS 50-266 AND 50-301 MONTHLY OPERATING REPORTS !
POINT BEACH NUCLEAR PLANT. UNJTS 1 AND 2 l Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of December 1996.
Sincerely, i
l l
l . A. Patulski General Manager Nuclear Operations smb i
l Attachments \l
\
14011
^
l cc: L. L. Smith, PSCW NRC Regional Administrator, Region III NRC Resident inspector ,]/[
9701140308 961231 PDR ADOCK 05000266 R PDR A sukskn ornomin Dryrmxath>n ,
OPERATING DATA REPORT -
DOCKET NO. 50-266 DATE: 01/06/97 COMPLETED BY: B. J. Vander Velde TELEPHONE: 414-755-6681 i OPERATING STATUS i
- 1. UNIT NAME: POINT BEACH NUCLEAR PLANT - UNIT 1 . NOTES .
- 2. REPORTING PERIOD: December - 1996 . .
- 3. LICENSED THERMAL POWER (MWT): 1518.5 .
- 4. NAMEPLATE RATING (GROSS MWE): 523.8 . .
- 5. DESIGN ELECTRICAL RATING (NET MWE): 497.0 . .
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.0 . , ,
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.0 .. ......... .. ... ..... ............
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
NA
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): Power 90%
- 10. REASONS FOR RESTRICTIONS, (IF ANY):
Self-imposed restriction.
THIS MONTH YEAR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 744.0 744.0 229,272.0
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 744.0 192,873.9
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 667.3
- 14. HOURS GENERATOR ON LINE 744.0 744.0 189,655.0
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 846.9
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,075,254.0 1.075,254.0 269,494,385.0
- 17. GROSS ELECTRICAL ENERGY GENERATED 368,290.0 368,290.0 91,091,090.0
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 352,505.5 352,505.5 86.856,419.5
- 19. UNIT SERVICE FACTOR 100.0 % 100.0 % 82.7 %
- 20. UNIT AVAILABILITY FACTOR 100.0 % 100.0 % 83.1 %
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 97.7 % 97.7 % 77.8 % ,
- 22. UNIT CAPACITY FACTOR .'USING DER NET) 95.3 % 95.3 % 76.2 % 6
- 23. UNIT FORCED OUTAGE RATE O.0% 0.0% 1.4%
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
Refueling, 05/10/97, 50 days
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
l NA DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22,1977 i
- _ . _ _ . . . _ _ - _ _ _ __ _. _ _ _ __ .______m ___ _ _ . . _ . . _
POINT BEACH NUCLEAR PLANT -
DOCKET NO. 50-266 AVERAGE DAILY UNIT POWER LEVEL UNIT NAME Point Beach Unit 1 MONTH DECEMBER - 1996 DATE 1/6/97 COMPLETED BY Brian J. Vander Velde TELEPHONE (414)755-6681 AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL DAY MWe NET DAY MWe NET DAY MWe NET 1 476 11 499 21 449 2 497 12 498 22 449 3 498 13 497 23 448 4 498 14 498 24 448 5 498 15 498 25 449 6 498 16 497 26 450 7 498 17 472 27 446 8 499 16 449 28 449 9 495 19 446 29 450 10 496 20 447 30 447 31 448
POINT BEACH NUCLEAR PLANT Docket No. 50-266 Unit Nane Point Beach. Unit 1 UNIT SIIUTDOWNS AND POWER REDUCTIONS Date 1/9/97 Completed By B. J. Vander Velde i REPORT MONTII DECEMBER - 1996 Telephone No. 414/755-6681 .
Method of Licensee Event .
Duration Reactor Report No. System Component Cause and Corrective Action j No. Date Type' (Hours) Reason' Shut Down' Code
- Code' To Prevent Recurrence 3 %I201 S 0 B 5 NA HB VALVEX The unit was reduced to 69% power for turbine stop valve tests, atmosphenc steam dump tears, crossover steam dump tests, and condenser steam dump tests.
4 % I217 5 0 F 5 NA ZZ ZZ7777 'Ihe unit entered a self-inrosed power reduction to 90% power.
'F: Forced ' Reason: ' Method: ' Exhibit G - Instructions S: Scheduled A - Equipment Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing 2 - Manual Scram data entry sheets C - Refueling 3 - Automatic Scram LER file (NUREG-0161)
D - Regulatory Restriction 4 - Continuation of E - Operator Training &- Previous Shutdown Licensing Exam 5 - Reduced Imad F- Administrative 6 - Other (explain) ' Exhibit 1 - Same Source G - Operational Error (explain)
H - Other (explain)
PBF-0028b (03-90),
- DOCKET NO. 50-266 UNIT NAME Point Beach Unit 1 DATE 1/7/97 COMPLETED BY B. J. Vander Velde TELEPHONE 414/755-6681 Unit 1 operated at an average of 474 MWe net for the December,1996 report period.
The following Licensee Event Reports were submitted to the NRC in December 1996:
Licensee Event Report 50-266/96-010, Emergency Diesel Generator (G-01) Governor Failure.
' Licensee Event Report 50-266/96-011, Delta T Trip Setpoints Not Reduced in Accordance with Technical Specifications.
Safety-related maintenance included:
- 1. C-02 main control board annunciator buzzer replaced.
- 2. P-012A spent fuel pool cooling pump flow tested.
- 3. PI-03368A emergency diesel generator turbo-charger oil pressure indicator calibrated.
- 4. D-06124 volt DC station battery flash arrestor replaced.
- 5. 120 volt system multi and/or non-numbered equipment receptacle replaced.
- 6. G-01 emergency diesel generator air start circuit repaired and tested, relay replaced.
- 7. G-02 emergency diesel genciator air start system headers cleaned and frequency meter replaced.
- 8. F-137A emergency diesel generator fuel oil pump discharge filters replaced.
- 9. C-2 personnel access air lock gear replaced.
- 10. Piping HB-19 rarvice water to engineered safeguards piping replaced.
OPERATING DATA REPORT DOCKET NO. 50-266 ,
DATE: 01/08/97 COMPLETED BY: B. J. Vander Velde TELEPHONE: 414-755-6681 OPERATING STATUS
- 1. UNIT NAME: POINT BEACH NUCLEAR PLANT - UNIT 2 $ NOTES .
- 2. REPORTING PERIOD: December - 1996 . .
- 3. LICENSED THERMAL POWER (MWT): 1518.5 . .
- 4. NAMEPLATE RATING (GROSS MWE): 523.8 .
- 5. DESIGN ELECTRICAL RATING (NET MWE): 497.0 . .
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.0 .
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.0 ............ ....... .... ............
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
NA
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NA
- 10. REASONS FOR RESTRICTIONS, (IF ANY):
NA THIS MONTH YEAR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD 744.0 8,784.0 214,057.0
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL O.0 6,660.5 185,987.6
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 . 0.0 233.9
- 14. HOURS GENERATOR ON LINE O.0 6,653.9 183,508.3
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 302.2
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 0.0 9,072,854.0 263,605,007.0
- 17. GROSS ELECTRICAL ENERGY GENERATED O.0 3,100,050.0 89,603,310.0
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 0.0 2,946,934.0 85,411,583.5
- 19. UNIT SERVICE FACTOR O.0% 75.8 % 85.7 %
- 20. UNIT AVAILABILITY FACTOR O.0% 75.8 % 85.9 %
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 0.0% 69.2 % 81.7 %
- 22. UNIT CAPACITY FACTOR (USING DER NET) 0.0% 67.5 % 80.3 %
- 23. UNIT FORCED OUTAGE RATE O.0% 0.3% 0.9%
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
None
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
02/15/U DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22,1977
_ _ _ . . - _ - _ _ . - _ . - - _ _ - , . _ _ . _ _ _ _ _ . _ . _ - . _ - - . . _ . , - . . . _ _ _ _ _ . - - - - - _ _ - . . . - _ _ _ - - _ _ - . _ . _ _ _ _ . _ - . - -.____.--_------------r - _ _ _ . , ,.____a -
- - a . - - ,s
POINT BEACH NUCLEAR PLANT - DOCKET NO. 50-301 '.
AVERAGE DAILY UNIT POWER LEVEL UNIT NAME Point Beach. Unit 2 MONTH DECEMBER - 1996 DATE 1/6/97 COMPLETED BY Brian J. Vander Velde TELEPHONE (414)755-6681 4
AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL DAY MWe NET DAY MWe NET DAY MWe NET 1 -2 11 -2 21 -3 2 -2 12 -2 22 -3 3 -2 13 -2 23 -3 4 -2 14 -2 24 -3 5 -2 15 -2 25 -4 6 -2 16 -2 26 -4 7 -2 17 -2 27 -3 8 -2 18 -3 28 -3 9 0 19 -2 29 -3 10 -1 20 -2 30 -3 31 -2
_ _ _-_-._._______.____..._m______ _ _ _ _ . _ _ _ _ _ _ . _ - . _ _ _ _ _ _ _ _ _ ___ __ _--_ - _ _ ______.__.___-_ _._____._ _ _ _ _____-_____._-___ - _ _ _ _ _ _ _ _ _ . - ________i____--____________-_____ -
POINT BEACH NUCLEAR PLANT Docket No. 50-301 Unit Name Point Beach. Unit 2 -
UNIT SHUTDOWNS AND POWER REDUCTIONS Date 1/6/97 +
Completed By B. J. Vander Velde -
REPORT MONTH DECEMBER - 1996 Telephone No. 414r755-6681 Method of Licensee Event '
Duration Reactor Report No. System Component Cause and Corrective Action No. Date Type' (Hours) Reason' Shut Down' Code' Code' To Prevent Recurtence 4 961005 S 744.0 C 1 NA NA NA Scheduled refueling and maintenance (U2R22). Major work items include: Replacire boeh Unit 2 steem generators; main control board wire separation resolution; repiece 8 main aseem condenser valves; HP turbine crosaunder piping; repair service water west header, replace boric acid and reactor makeup water totalizers; replace oefety irsection accunmistor levei trememitters; modify X02, XO3, and XO4 treneformer metering and relay circuite; and exciter modification.
'F: Forced ' Reason: ' Method: ' Exhibit G - Instructions S: Scheduled A - Equipment Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing 2 - Manual Scram data entry sheets C - Refueling 3 - Automatic Scram LER file (NUREG-0161)
D - Regulatory Restriction 4 - Continuation of E - Operator Training & Previous Shutdown Licensing Exam 5 - Reduced Imd F - Administrative 6 - Other (explain) Mahibit I - Same Source G - Operational Error (explain)
H - Other (explain) 4 PBF-0028b (0340).
4 4 *
. DOCKET NO. 50-301 UNIT NAME Point Beach Unit 2 DATE 1/7/97 COMPLETED BY B. J. Vander Velde TELEPHONE 414/755-6681 i
)
Unit 2 was in a refueling outage during the entire December,1996 report period.
Safety-related maintenance included: .
) 1. LT-00461 steam generator level transmitter shielded extension cable installed.
- 2. LT-00462 steam generator level transmitter shielded extension cable installed.
l 3. LT-00463 steam generator level transmitter shielded extension cable installed.
- 4. LT-00471 steam generator level transmitter shielded extension cab!e installed. '
l
- 5. LT-00472 steam generator level transmitter shielded extension cable installed.
- 6. LT-00473 steam generator level transmitter shielded extension cable installed.
- 7. SC-00955 reactor coolant hot leg sample isolation valve stroke tested.
- 8. C-1 equipment access air lock (lower) gasket repaired.
i
- 9. C-2 personnel air lock o-rings replaced.
- 10. P-011 A component cooling water pump probe mounting blocks installed.
I1. P-01IB component cooling water pump probe mounting blocks installed.
- 12. HS-32 steam generator main steam line east snubber tested.
- 13. HS-33 steam generator main steam line west snubber tested. ~
\
- 14. HS-36 steam generator north side snubber tested.
- 15. HS-37 steam generator middle side snubber tested.
- 16. HS-38 steam generator south side snubber tested.
- 17. HS-39 steam generator north side snubber tested.
- 18. B52-328F control power transformer replaced.
- 19. B52-3210C control power transformer replaced.
- 20. B52-425C control power transformer replaced.
- 21. B52-4275 control power transformer replaced.
- 22. CPP-39 containment cooler supply pipe penetration adapter neplaced.
- 23. SI-00825A reactor water storage tank outlet cleaned.
e l